CASE ID: 0901126002462021

Appellant / Complainant

Samiah International Builders Limited

VS

Respondent

Melrose Avenue Apartment Allottee(s) Association, U.P. Real Estate Regulatory Authority Lucknow

Developer Firm

samiah international builders limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferStructural Defects & QualityMaintenance & Utility DisputesJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126002462021 by Samiah International Builders Limited against Melrose Avenue Apartment Allottee(s) Association, U.P. Real Estate Regulatory Authority Lucknow before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferStructural Defects & QualityMaintenance & Utility DisputesJurisdiction & Maintainability
2
Stage 104/10/2021

Compliance of section 43(5)

The Appellate Tribunal dismissed the appeal filed by M/s Samiah International Builders Ltd. due to their failure to comply with the mandatory pre-deposit requirements under Section 43(5) of the Real Estate (Regulation and Development) Act, 2016.

3
Stage 223/09/2021

Compliance of section 43(5)

The Tribunal granted the appellant a one-week extension to comply with Section 43(5) of the Act and rectify registry defects, noting that failure to do so by the next hearing will result in dismissal.

4
Stage 312/04/2021

Compliance of section 43(5)

No text available.

5
Stage 417/03/2021

Compliance of section 43(5)

The Tribunal granted the appellant one week to comply with Section 43(5) of the Act and granted the respondent two weeks to file objections and authorization documents, scheduling the next hearing for April 12, 2021.

6
Stage 525/02/2021

Hearing

The Tribunal adjourned the defective appeal to 17.03.2021 and directed the appellant's counsel to ensure complete compliance with Section 43(5) of the Act, warning of potential dismissal for non-compliance.

7
Stage 612/02/2021

For Order

The Tribunal granted the appellant's counsel a one-week extension to comply with the provisions of Section 43(5) of the Act and scheduled the defective appeal for hearing on 25.02.2021.

8
Stage 721/01/2021

Defect Removal

No text available.

9
Stage 815/01/2021

Hearing

No text available.

10
Stage 9Interim Order

Tribunal Order #0901126002462021-25-02-2021

The Tribunal adjourned the defective appeal to 17.03.2021 and directed the appellant's counsel to ensure complete compliance with Section 43(5) of the Act, warning of potential dismissal for non-compliance.

11
Stage 10Final Ruling Order

Tribunal Order #0901126002462021-04-10-2021

The Appellate Tribunal dismissed the appeal filed by M/s Samiah International Builders Ltd. due to their failure to comply with the mandatory pre-deposit requirements under Section 43(5) of the Real Estate (Regulation and Development) Act, 2016.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal filed by M/s Samiah International Builders Ltd. due to their failure to comply with the mandatory pre-deposit requirements under Section 43(5) of the Real Estate (Regulation and Development) Act, 2016. Awarded in favor of Respondent. Awarded interest rate: MCLR+ 1 percent.

Disposal Winner: RespondentInterest Rate: MCLR+ 1 percentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal filed by M/s Samiah International Builders Ltd. due to their failure to comply with the mandatory pre-deposit requirements under Section 43(5) of the Real Estate (Regulation and Development) Act, 2016.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+ 1 percent

Interest Period

from 31.12.2011 till the date of giving offer of possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 14(3)Section 11(4)(d)Section 19(6)Section 43(5)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra

Respondent Advocate(s)

  • Preeti Bajpai

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126002462021-25-02-2021

The Tribunal adjourned the defective appeal to 17.03.2021 and directed the appellant's counsel to ensure complete compliance with Section 43(5) of the Act, warning of potential dismissal for non-compliance.

FINAL_ORDEROrder ID: 0901126002462021-04-10-2021

The Appellate Tribunal dismissed the appeal filed by M/s Samiah International Builders Ltd. due to their failure to comply with the mandatory pre-deposit requirements under Section 43(5) of the Real Estate (Regulation and Development) Act, 2016.

TathyaGrid RERA Intelligence AI

Need to research all rulings for samiah international builders limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →