Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126073802022 by New Okhla Industrial Development Authority against Suresh Singh Bhadauria before up_rera.

2
Stage 103/08/2023

Hearing

The Tribunal rejected the applicant's application for condonation of delay, dismissed the appeal, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee in accordance with the original order.

3
Stage 213/07/2023

Delay condonation

The Tribunal relieved Sri Ashok Shukla of his responsibility as counsel for the New Okhla Industrial Development Authority following his resignation from their panel and adjourned the matter to 03.08.2023.

4
Stage 302/05/2023

Notice

The Tribunal granted a 10-day extension to the applicant for filing a reply to the respondent's objections and scheduled the case for hearing on July 13, 2023.

5
Stage 421/03/2023

Notice

No text available.

6
Stage 513/02/2023

Delay condonation

The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and directed the procedural steps for service of notice and filing of objections.

7
Stage 6Final Ruling Order

Tribunal Order #0901126073802022-03-08-2023

The Tribunal rejected the applicant's application for condonation of delay, dismissed the appeal, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee in accordance with the original order.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the applicant's application for condonation of delay, dismissed the appeal, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee in accordance with the original order. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the applicant's application for condonation of delay, dismissed the appeal, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee in accordance with the original order.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ashok Shukla

Respondent Advocate(s)

  • Ram Bhadauria

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126073802022-03-08-2023

The Tribunal rejected the applicant's application for condonation of delay, dismissed the appeal, and directed that the pre-deposited amount be transferred to U.P. RERA for disbursement to the allottee in accordance with the original order.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →