Appellant / Complainant
Chetan Manohar Shashtri
Respondent
Alpine Infraprojects Pvt Ltd
alpine infraprojects pvt ltd
₹39,12,195
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126073062022 by Chetan Manohar Shashtri against Alpine Infraprojects Pvt Ltd before up_rera.
for delivery of Judgment/Order
The Tribunal set aside the RERA Authority's order and quashed the cancellation of three allottees' units, directing the promoter to issue fresh offers of possession with valid OC/CC and restore the units. Additionally, the Tribunal ruled that any third-party transfers made during pendency are subject to this decision under the doctrine of lis pendens and directed RERA to proceed with penalties against the promoter.
Final Hearing
The Tribunal heard arguments from both the appellant and respondent and has reserved its judgment for a later date.
Final Hearing
The Tribunal has ordered the matter to be listed for orders before the appropriate Bench (Bench No. 2) on July 31, 2025.
Final Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the next hearing for July 14, 2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal heard arguments from both parties and directed the appellant to file a reply to the supplementary affidavit within five days, adjourning the matter for further arguments on 21.05.2025.
Hearing
The Tribunal noted the respondent's filing of supplementary objections and the appellant's refusal to file an additional rejoinder, subsequently scheduling the matter for final hearing on 09.05.2025.
Hearing
The Tribunal granted a request from the respondent's counsel to adjourn the appeal and scheduled the next hearing for April 23, 2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal directed the appellant to file a rejoinder to the respondent's supplementary objections within 10 days and scheduled the next hearing for April 4, 2025.
Hearing
The Tribunal has adjourned the appeal to 11.03.2025 upon the joint request of the parties and directed that pleadings be completed in the interim.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for orders/hearing on 13.02.2025.
Hearing
The Tribunal granted a request from the respondent's counsel to reschedule the hearing of Appeal-13/2023 to 27.01.2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal granted an adjournment request from the respondent's counsel and rescheduled the hearing for December 19, 2024, noting that no further adjournments will be permitted.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the hearing for 26.11.2024, with a clarification that no further adjournments will be permitted.
Hearing
The Tribunal has adjourned the matter to 21.10.2024 to be heard alongside other appeals of a similar nature.
Hearing
The Tribunal granted the appellant seven days to file a Vakalatnama and scheduled the appeal for a final hearing on September 9, 2024.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and rescheduled the hearing for July 5, 2024.
Hearing
The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing/orders on 08.05.2024.
Hearing
The Tribunal adjourned the matter to 05.04.2024 to align with similar cases and directed the appellant to file replies to the respondent's supplementary affidavit within one week.
Hearing
The Tribunal directed that Appeal-13/2023 be clubbed with Appeal No. 3/2023 for a joint hearing on 01.03.2024 and ordered the parties to exchange pleadings in the interim.
Hearing
The Tribunal rejected the appellant's application to recall an order dated 03.07.2023 due to delays and lack of cooperation, and imposed a nominal cost of Rs. 1/- on the appellant's counsel for appearing without preparation.
Hearing
The Tribunal adjourned the proceedings and rescheduled the hearing for October 17, 2023, due to a lawyer strike called by the Bar Council of Uttar Pradesh.
Hearing
The Tribunal directed that the appeal be listed for a hearing on 11.09.2023.
Hearing
The Tribunal granted an adjournment due to the appellant's health but closed the appellant's opportunity to file a reply to the respondent's objections due to previous delays and failure to comply with prior timelines.
Hearing
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the appeal for hearing on 03.07.2023.
Hearing
The Tribunal has scheduled the case for a hearing or orders on 24.04.2023, referencing a previous order passed in Appeal No. 11/2023.
For Order
The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and scheduled the matter for hearing on March 16, 2023.
Admission
The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and directed the parties to exchange replies and upload documents to the e-portal before the next hearing on 13.02.2023.
Tribunal Order #0901126073062022-03-07-2023
The Tribunal granted an adjournment due to the appellant's health but closed the appellant's opportunity to file a reply to the respondent's objections due to previous delays and failure to comply with prior timelines.
Tribunal Order #0901126073062022-30-10-2025
The Tribunal set aside the RERA Authority's order and quashed the cancellation of three allottees' units, directing the promoter to issue fresh offers of possession with valid OC/CC and restore the units. Additionally, the Tribunal ruled that any third-party transfers made during pendency are subject to this decision under the doctrine of lis pendens and directed RERA to proceed with penalties against the promoter.
Tribunal Order #0901126073062022-19-01-2024
The Tribunal rejected the appellant's application to recall an order dated 03.07.2023 due to delays and lack of cooperation, and imposed a nominal cost of Rs. 1/- on the appellant's counsel for appearing without preparation.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside the RERA Authority's order and quashed the cancellation of three allottees' units, directing the promoter to issue fresh offers of possession with valid OC/CC and restore the units. Additionally, the Tribunal ruled that any third-party transfers made during pendency are subject to this decision under the doctrine of lis pendens and directed RERA to proceed with penalties against the promoter. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside the RERA Authority's order and quashed the cancellation of three allottees' units, directing the promoter to issue fresh offers of possession with valid OC/CC and restore the units. Additionally, the Tribunal ruled that any third-party transfers made during pendency are subject to this decision under the doctrine of lis pendens and directed RERA to proceed with penalties against the promoter.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Anurag Misra
- Santosh Yadav
Respondent Advocate(s)
- Anurag Singh
Official RERA Tribunal Orders (3)
The Tribunal granted an adjournment due to the appellant's health but closed the appellant's opportunity to file a reply to the respondent's objections due to previous delays and failure to comply with prior timelines.
The Tribunal set aside the RERA Authority's order and quashed the cancellation of three allottees' units, directing the promoter to issue fresh offers of possession with valid OC/CC and restore the units. Additionally, the Tribunal ruled that any third-party transfers made during pendency are subject to this decision under the doctrine of lis pendens and directed RERA to proceed with penalties against the promoter.
The Tribunal rejected the appellant's application to recall an order dated 03.07.2023 due to delays and lack of cooperation, and imposed a nominal cost of Rs. 1/- on the appellant's counsel for appearing without preparation.
Need to research all rulings for alpine infraprojects pvt ltd?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.