up_reraStatus: Completed
CASE ID: 0901126072342022

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Maya Buildcon Private Limited

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

9 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126072342022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Maya Buildcon Private Limited before up_rera.

2
Stage 128/03/2024

Delay condonation

The Tribunal allowed the appellant's application to withdraw the appeal following a settlement between the parties and directed the release of the amount deposited under Section 43(5) of the Act, including accrued interest, via RTGS.

3
Stage 219/03/2024

Delay condonation

The Tribunal has scheduled the defective appeal for consideration regarding the application for condonation of delay on 28.03.2024, following a request from the appellant's counsel.

4
Stage 315/02/2024

Delay condonation

The Tribunal granted the appellant one week's extension to file an affidavit of service following a request for adjournment on health grounds and scheduled the matter for hearing on 19.03.2024.

5
Stage 408/01/2024

Defect Removal

The Tribunal noted the appellant's compliance with Section 43(5) of the Act via a deposit of Rs. 4,22,492/- and directed that notice be issued to the respondent regarding the application for condonation of delay and grounds of appeal.

6
Stage 522/12/2023

Defect Removal

The Tribunal directed the Registry to communicate existing defects in the appeal to the applicant and ordered that the appeal will be dismissed if these defects are not removed within a week of notification.

7
Stage 6Interim Order

Tribunal Order #0901126072342022-08-01-2024

The Tribunal noted the appellant's compliance with Section 43(5) of the Act via a deposit of Rs. 4,22,492/- and directed that notice be issued to the respondent regarding the application for condonation of delay and grounds of appeal.

8
Stage 7Final Ruling Order

Tribunal Order #0901126072342022-28-03-2024

The Tribunal allowed the appellant's application to withdraw the appeal following a settlement between the parties and directed the release of the amount deposited under Section 43(5) of the Act, including accrued interest, via RTGS.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appellant's application to withdraw the appeal following a settlement between the parties and directed the release of the amount deposited under Section 43(5) of the Act, including accrued interest, via RTGS. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appellant's application to withdraw the appeal following a settlement between the parties and directed the release of the amount deposited under Section 43(5) of the Act, including accrued interest, via RTGS.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav
  • Bal Kishor Verma

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126072342022-08-01-2024

The Tribunal noted the appellant's compliance with Section 43(5) of the Act via a deposit of Rs. 4,22,492/- and directed that notice be issued to the respondent regarding the application for condonation of delay and grounds of appeal.

FINAL_ORDEROrder ID: 0901126072342022-28-03-2024

The Tribunal allowed the appellant's application to withdraw the appeal following a settlement between the parties and directed the release of the amount deposited under Section 43(5) of the Act, including accrued interest, via RTGS.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →