Appellant / Complainant
Uppal Chadha Hi-Tech Developers Pvt. Ltd.
Respondent
Sandeep Mishra
uppal chadha hi-tech developers pvt. ltd.
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126071842022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Sandeep Mishra before up_rera.
Delay condonation
The Tribunal rejected the applications for condonation of delay in seven appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all appeals; consequently, the Tribunal directed that the pre-deposited amounts be transferred to U.P. RERA for distribution to the allottees during execution proceedings.
Delay condonation
The Tribunal noted the absence of the appellant's counsel and scheduled the defective appeal for consideration of a delay condonation application on 27.05.2024.
Delay condonation
The Tribunal noted the absence of the respondent and scheduled a hearing for May 24, 2024, to consider the application for condonation of delay in this defective appeal.
Delay condonation
The Tribunal noted the absence of the appellant's counsel and adjourned the matter to 24.04.2024 for hearing or orders.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and scheduled the matter for hearing on the application for condonation of delay on 19.03.2024.
Delay condonation
The Tribunal closed the respondent's opportunity to file objections to the condonation of delay application and grounds of appeal due to non-compliance with previous orders, while allowing the respondent to argue based on existing documents.
Delay condonation
The Tribunal listed the defective appeal for 29.09.2023 and granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal.
Delay condonation
The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and directed specific procedures for service of notice and exchange of objections.
Tribunal Order #0901126071842022-27-05-2024
The Tribunal rejected the applications for condonation of delay in seven appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all appeals; consequently, the Tribunal directed that the pre-deposited amounts be transferred to U.P. RERA for distribution to the allottees during execution proceedings.
Tribunal Order #0901126071842022-08-01-2024
The Tribunal closed the respondent's opportunity to file objections to the condonation of delay application and grounds of appeal due to non-compliance with previous orders, while allowing the respondent to argue based on existing documents.
Tribunal Disposal & Final Award Ruling
The Tribunal rejected the applications for condonation of delay in seven appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all appeals; consequently, the Tribunal directed that the pre-deposited amounts be transferred to U.P. RERA for distribution to the allottees during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal rejected the applications for condonation of delay in seven appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all appeals; consequently, the Tribunal directed that the pre-deposited amounts be transferred to U.P. RERA for distribution to the allottees during execution proceedings.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 09.10.2016 to date of getting OC/CC or to the date when possession of plot was offered whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Amit Yadav
- Bal Kishor Verma
Respondent Advocate(s)
- Prasoon Kumar Anjor
- Abhay Gupta
Official RERA Tribunal Orders (2)
The Tribunal rejected the applications for condonation of delay in seven appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all appeals; consequently, the Tribunal directed that the pre-deposited amounts be transferred to U.P. RERA for distribution to the allottees during execution proceedings.
The Tribunal closed the respondent's opportunity to file objections to the condonation of delay application and grounds of appeal due to non-compliance with previous orders, while allowing the respondent to argue based on existing documents.
Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.