CASE ID: 0901126068942022

Appellant / Complainant

Alkesh Kumar Gupta

VS

Respondent

Citizen Housing and Developing Cooperative Society

Developer Firm

citizen housing and developing cooperative society

Disputed Amount

8,97,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferUnfair Cancellation & ForfeitureJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

42 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126068942022 by Alkesh Kumar Gupta against Citizen Housing and Developing Cooperative Society before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferUnfair Cancellation & ForfeitureJurisdiction & Maintainability
2
Stage 106/04/2026

for delivery of Judgment/Order

The Tribunal set aside the RERA Authority's order, declared the cancellation of the appellant's plot allotment illegal, and directed the respondent to restore the allotment, deliver possession, and pay delay interest from February 13, 2017.

3
Stage 206/01/2026

Part Heard

The Tribunal heard arguments from both the appellant and respondent regarding the appeal and objections, but has reserved the judgment for a later date.

4
Stage 309/12/2025

Part Heard

The Tribunal noted the absence of both parties and ordered the appeal to be listed for a subsequent hearing on 06.01.2026.

5
Stage 427/11/2025

Part Heard

No text available.

6
Stage 506/11/2025

Part Heard

The Tribunal noted that the appeal is part-heard from a previous Bench and scheduled the matter for further hearing on 27.11.2025.

7
Stage 616/10/2025

Hearing

The Tribunal noted the respondent's request for more time to file an affidavit and scheduled the appeal for a final hearing on November 6, 2025, as part-heard.

8
Stage 709/10/2025

Hearing

The Tribunal granted the respondent seven days to file a list of 498 plots for the New Suncity project and a reply to the appellant's affidavit, with the matter listed for hearing on 16.10.2025.

9
Stage 816/09/2025

Hearing

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the appeal for hearing on 09.10.2025.

10
Stage 903/09/2025

Hearing

The Tribunal granted the respondent counsel time to file a reply to the appellant's supplementary affidavit and adjourned the matter to 16.09.2025, noting it as part-heard.

11
Stage 1018/08/2025

Hearing

The Tribunal has scheduled the case for orders on September 3, 2025, and directed that any objections to the supplementary affidavit be filed in the interim.

12
Stage 1123/07/2025

Hearing

The Tribunal granted a prayer to list the appeal for hearing or orders on 18.08.2025.

13
Stage 1203/07/2025

Hearing

The Tribunal granted the respondent seven days to reply to the appellant's objection and scheduled the appeal for a hearing on 23.07.2025.

14
Stage 1327/05/2025

Hearing

The Tribunal directed the respondent to serve a soft copy of their affidavit to the appellant and granted the appellant ten days to file a reply, with the matter listed for 03.07.2025.

15
Stage 1401/05/2025

For Order

The Tribunal noted the respondent's filing of an affidavit and directed the appellant to file any objections, adjourning the matter to 27.05.2025.

16
Stage 1507/04/2025

For Order

The Tribunal granted the respondent additional time to file an affidavit regarding plot availability in Phase-I and adjourned the appeal to 01.05.2025.

17
Stage 1610/03/2025

For Order

The Tribunal has ordered the appeal to be listed for a hearing on 07.04.2025.

18
Stage 1724/02/2025

For Order

The Tribunal granted the appellant time to file an affidavit regarding the availability of plots in Phase-1 and adjourned the matter to 10.03.2025.

19
Stage 1811/02/2025

For Order

The Tribunal granted the respondent additional time to check unit inventory availability following their return to the country and adjourned the matter to 24.02.2025.

20
Stage 1931/01/2025

For Order

The Tribunal granted the respondent time to seek instructions regarding the matter and scheduled the case for further orders/hearing on 11.02.2025.

21
Stage 2030/01/2025

For Order

The Tribunal has scheduled the appeal for orders or hearing on the following day, 31.01.2025.

22
Stage 2120/01/2025

For Order

The Tribunal has scheduled the case for orders on January 30, 2025.

23
Stage 2225/09/2024

Hearing

The Tribunal heard arguments from both parties regarding the applicability of a previous judgment involving the same project and subsequently reserved its judgment for further deliberation.

24
Stage 2302/09/2024

Hearing

The Tribunal has scheduled the matter for a hearing on September 25, 2024.

25
Stage 2428/08/2024

Hearing

The Tribunal granted the respondent one final opportunity to argue the matter, noting that if they fail to do so on the next date, the case will be decided based on available records. The matter is listed for final hearing on 02.09.2024.

26
Stage 2512/08/2024

Hearing

The Tribunal granted a final opportunity to the respondent to present arguments and scheduled the appeal for hearing on 28.08.2024.

27
Stage 2612/07/2024

Hearing

No text available.

28
Stage 2704/07/2024

Hearing

The Tribunal has adjourned the appeal to a new hearing date of 12.07.2024 following a request from the learned counsel for the parties.

29
Stage 2806/05/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal for a hearing on 04.07.2024.

30
Stage 2904/04/2024

Hearing

The Tribunal granted a request for adjournment from the respondent's counsel and scheduled the appeal for hearing on 06.05.2024.

31
Stage 3004/03/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and rescheduled the hearing for April 4, 2024.

32
Stage 3131/01/2024

Hearing

The Tribunal noted that the appeal is ready for hearing and scheduled it for a subsequent hearing on March 4, 2024.

33
Stage 3201/11/2023

Hearing

No text available.

34
Stage 3319/09/2023

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to prior engagements and rescheduled the hearing for 01.11.2023.

35
Stage 3418/08/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to personal difficulty and rescheduled the hearing for 19.09.2023.

36
Stage 3503/07/2023

Hearing

The Tribunal granted the appellant two weeks to file a reply to the respondent's objections and scheduled the appeal for hearing on 18.08.2023.

37
Stage 3621/04/2023

Hearing

The Tribunal granted the respondent 10 days to file objections against the grounds of appeal and scheduled the matter for hearing on July 3, 2023.

38
Stage 3713/03/2023

Notice

The Tribunal granted the respondent 10 days to file objections and a vakalatnama, with the appellant directed to reply within one week thereafter; the matter is listed for hearing on 21.04.2023.

39
Stage 3802/02/2023

Notice

No text available.

40
Stage 3922/12/2022

Admission

The Tribunal issued notice to the respondent and directed the appellant to serve the appeal documents via speed-post and email, while also requiring the submission of a legible copy of the document on page 49.

41
Stage 40Final Ruling Order

Tribunal Order #0901126068942022-06-04-2026

The Tribunal set aside the RERA Authority's order, declared the cancellation of the appellant's plot allotment illegal, and directed the respondent to restore the allotment, deliver possession, and pay delay interest from February 13, 2017.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the RERA Authority's order, declared the cancellation of the appellant's plot allotment illegal, and directed the respondent to restore the allotment, deliver possession, and pay delay interest from February 13, 2017. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the RERA Authority's order, declared the cancellation of the appellant's plot allotment illegal, and directed the respondent to restore the allotment, deliver possession, and pay delay interest from February 13, 2017.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

from 13.02.2017 till the date of valid offer of possession/physical possession whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 11(5)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anuuj Taandon

Respondent Advocate(s)

  • Saurabh Misra
  • Gautam Johri

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126068942022-06-04-2026

The Tribunal set aside the RERA Authority's order, declared the cancellation of the appellant's plot allotment illegal, and directed the respondent to restore the allotment, deliver possession, and pay delay interest from February 13, 2017.

TathyaGrid RERA Intelligence AI

Need to research all rulings for citizen housing and developing cooperative society?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →