up_reraStatus: Completed
CASE ID: 0901126068722022

Appellant / Complainant

Ans Developers Private Limited, Shalimar Lakecity Private Limited

VS

Respondent

Rashmi Gupta

Developer Firm

ans developers private limited

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

28 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126068722022 by Ans Developers Private Limited, Shalimar Lakecity Private Limited against Rashmi Gupta before up_rera.

2
Stage 112/12/2024

Delay condonation

The Uttar Pradesh Real Estate Appellate Tribunal allowed the appeal filed by M/s ANS Developers Pvt. Ltd. and set aside/quashed the order dated 13.10.2022 passed by the U.P. Real Estate Regulatory Authority in favor of Rashmi Gupta.

3
Stage 211/12/2024

Delay condonation

The Tribunal has granted a joint request from the counsel to list Appeal-100/2023 along with the records of Appeal No. 234 of 2019 for orders on 12.12.2024.

4
Stage 312/11/2024

Delay condonation

The Tribunal has granted a request from the appellant's counsel to reschedule the matter for orders or hearing on 11.12.2024.

5
Stage 403/10/2024

Hearing

The Tribunal adjourned the proceedings due to an application for adjournment filed by the respondent's counsel on the grounds of illness and rescheduled the hearing for 12.11.2024.

6
Stage 510/09/2024

Hearing

The Tribunal granted the appellant one week to file a rejoinder and ordered the appeal to be listed alongside Appeal No. 234/2019 on 03-10-2024 for consideration of condonation of delay and final hearing.

7
Stage 607/08/2024

Hearing

The Tribunal granted the appellant a 7-day extension to file a reply to the respondent's objections and scheduled the matter for hearing on 10.09.2024.

8
Stage 708/07/2024

Hearing

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for consideration of the condonation of delay application on 07.08.2024.

9
Stage 806/05/2024

Hearing

The Tribunal noted the absence of the respondent and ordered that the defective appeal be listed for orders or hearing on 08.07.2024.

10
Stage 902/05/2024

Hearing

The Tribunal granted the respondent three days to file supplementary objections to establish their status as an allottee and scheduled the matter for hearing on May 6, 2024.

11
Stage 1001/04/2024

Hearing

The proceedings were adjourned due to the counsel for the applicant's medical emergency, and the defective appeal has been rescheduled for hearing on 02.05.2024.

12
Stage 1127/02/2024

Hearing

The Tribunal noted the respondent's objection to the appeal and directed the applicant to file a reply within one week, scheduling the matter for hearing on 01.04.2024.

13
Stage 1231/01/2024

Hearing

The Tribunal granted a final 10-day extension to the respondent for filing objections and directed that a soft copy be provided to the applicant, with the matter listed for hearing on 27.02.2024.

14
Stage 1319/01/2024

Hearing

The Tribunal adjourned the proceedings of Appeal-100/2023 upon a joint request from the counsels and scheduled the defective appeal for further hearing on 31.01.2024.

15
Stage 1418/01/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to his presence at the High Court and rescheduled the hearing for 19.01.2024 to consider the application for condonation of delay.

16
Stage 1516/01/2024

Hearing

The Tribunal refused the respondent's request to recall an ex-parte order dated 07.07.2023 due to undue delay and lack of diligence, directing the respondent's counsel to proceed with arguments based on existing records.

17
Stage 1612/10/2023

Hearing

No text available.

18
Stage 1704/09/2023

Hearing

The Tribunal adjourned the proceedings due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh and rescheduled the hearing for 12.10.2023.

19
Stage 1811/08/2023

Compliance of section 43(5)

The Tribunal granted an adjournment requested by the appellant's counsel due to a scheduling conflict and rescheduled the matter for orders on 04.09.2023.

20
Stage 1907/07/2023

Compliance of section 43(5)

Due to the respondent's failure to file objections or a Vakalatnama despite previous extensions, the Tribunal has ordered to proceed ex parte against the respondent and listed the matter for hearing on 11.08.2023.

21
Stage 2027/04/2023

Compliance of section 43(5)

The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and directed that a soft copy be emailed to the applicant. The matter is scheduled for hearing on July 7, 2023.

22
Stage 2116/03/2023

Compliance of section 43(5)

The Tribunal issued notice to the respondent following the appellant's compliance with the mandatory deposit requirement under Section 43(5) of the Act and scheduled the matter for hearing on 27.04.2023.

23
Stage 2203/03/2023

Defect Removal

The Tribunal granted the appellant 24 hours to ensure compliance with Section 43(5) of the Act and scheduled the defective appeal for hearing on 16.03.2023.

24
Stage 2323/02/2023

Defect Removal

The Tribunal granted a request from the appellant's counsel for more time to ensure compliance with Section 43(5) of the Act and adjourned the defective appeal to 03.03.2023.

25
Stage 24Interim Order

Tribunal Order #0901126068722022-07-07-2023

Due to the respondent's failure to file objections or a Vakalatnama despite previous extensions, the Tribunal has ordered to proceed ex parte against the respondent and listed the matter for hearing on 11.08.2023.

26
Stage 25Final Ruling Order

Tribunal Order #0901126068722022-12-12-2024

The Uttar Pradesh Real Estate Appellate Tribunal allowed the appeal filed by M/s ANS Developers Pvt. Ltd. and set aside/quashed the order dated 13.10.2022 passed by the U.P. Real Estate Regulatory Authority in favor of Rashmi Gupta.

27
Stage 26Interim Order

Tribunal Order #0901126068722022-16-01-2024

The Tribunal refused the respondent's request to recall an ex-parte order dated 07.07.2023 due to undue delay and lack of diligence, directing the respondent's counsel to proceed with arguments based on existing records.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Uttar Pradesh Real Estate Appellate Tribunal allowed the appeal filed by M/s ANS Developers Pvt. Ltd. and set aside/quashed the order dated 13.10.2022 passed by the U.P. Real Estate Regulatory Authority in favor of Rashmi Gupta. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Uttar Pradesh Real Estate Appellate Tribunal allowed the appeal filed by M/s ANS Developers Pvt. Ltd. and set aside/quashed the order dated 13.10.2022 passed by the U.P. Real Estate Regulatory Authority in favor of Rashmi Gupta.

Ruling Awarded To

Appellant

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Anurag Singh

Respondent Advocate(s)

  • Vaibhav Krishna

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126068722022-07-07-2023

Due to the respondent's failure to file objections or a Vakalatnama despite previous extensions, the Tribunal has ordered to proceed ex parte against the respondent and listed the matter for hearing on 11.08.2023.

FINAL_ORDEROrder ID: 0901126068722022-12-12-2024

The Uttar Pradesh Real Estate Appellate Tribunal allowed the appeal filed by M/s ANS Developers Pvt. Ltd. and set aside/quashed the order dated 13.10.2022 passed by the U.P. Real Estate Regulatory Authority in favor of Rashmi Gupta.

INTERIM_ORDEROrder ID: 0901126068722022-16-01-2024

The Tribunal refused the respondent's request to recall an ex-parte order dated 07.07.2023 due to undue delay and lack of diligence, directing the respondent's counsel to proceed with arguments based on existing records.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ans developers private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →