Appellant / Complainant
Gorakhpur Development Authority
Respondent
Parwati Devi
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126064972021 by Gorakhpur Development Authority against Parwati Devi before up_rera.
For Order
The Tribunal allowed an application to correct typographical errors regarding specific dates within the judgment and order dated 25.11.2024.
Further Hearing
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the original completion date declared to RERA (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).
Further Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and scheduled the case for orders on 25.11.2024.
For Order
The Tribunal allowed the appellant's application for amendment (IA No.1268 of 2024) and scheduled the appeal for further hearing on 16.10.2024.
For Order
The Tribunal granted an adjournment requested by the respondent's counsel due to a bereavement in her family and rescheduled the hearing for 04.10.2024.
For Order
The Tribunal refers the parties to a previous order passed in Appeal No. 290/2022 for the relevant orders.
For Order
This is a procedural order directing the parties to refer to a previously passed order dated 09.05.2024 in Appeal No. 285/2022.
For Order
The Tribunal directed that the appeal be listed for hearing on 09.05.2024, referring to a previous order passed in Appeal No. 293 of 2022.
For Order
The Tribunal has adjourned the matter and scheduled the next hearing for April 8, 2024.
For Order
The Tribunal noted the absence of the appellant's counsel due to sanctioned leave and scheduled the defective appeal for orders on 18.03.2024.
For Order
The Tribunal has scheduled the appeal for a further hearing on 29.02.2024.
For Order
This is a procedural order directing the parties to refer to a previously passed order dated in Appeal No. D 285/2022.
For Order
The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 13.10.2023.
Delay condonation
The Tribunal refers the matter to a previous order passed in Appeal No. (D) 285/2022 regarding Gorakhpur Development Authority Vs. Jagdhatri Mishra.
Delay condonation
This is a procedural order referring the matter to a previous order passed on Appeal No. (D) 285/2022.
Delay condonation
The Tribunal directed the appellant to provide a hard copy of the memo of appeal and annexures to the respondent within 48 hours to facilitate the filing of objections.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for November 17, 2022.
For Order
The Tribunal granted the respondent one week to file objections to the application for condonation of delay and grounds of appeal, scheduling the next hearing for October 21, 2022.
Defect Removal
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with the case scheduled for hearing on 19.09.2022.
Defect Removal
The Tribunal granted the respondent 15 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for July 21, 2022.
Tribunal Order #0901126064972021-25-11-2024
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the original completion date declared to RERA (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).
Tribunal Disposal & Final Award Ruling
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the original completion date declared to RERA (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021). Awarded in favor of Partial.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the original completion date declared to RERA (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).
Ruling Awarded To
Partial
Interest Period
from 13.04.2017 till handing over possession, excluding the period of injunction granted by the NGT from 17.12.2018 to 12.01.2021
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rakesh Bajpai
Respondent Advocate(s)
- Abhishek Khare
Official RERA Tribunal Orders (1)
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the original completion date declared to RERA (13.04.2017), while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021).
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.