Appellant / Complainant
Gorakhpur Development Authority
Respondent
Shobha Singh
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126064932021 by Gorakhpur Development Authority against Shobha Singh before up_rera.
For Order
The Tribunal allowed an application to correct several typographical errors regarding specific dates within the judgment and order dated 25.11.2024.
Further Hearing
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event.
Further Hearing
The court granted an adjournment requested by the appellant's counsel due to illness and scheduled the case for orders on 25.11.2024.
Hearing
The Tribunal allowed the appellant's application for amendment (IA No. 1267 of 2024) and scheduled the appeal for further hearing on October 16, 2024.
Hearing
The Tribunal granted the appellant three days to serve the correct amendment application and directed the respondent to file a reply within one week thereafter, listing the matter for hearing on 04.10.2024.
Hearing
The Tribunal granted the respondent one week to file objections to the appellant's amendment application and scheduled the matter for hearing on 02.08.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and rescheduled the appeal for hearing on 08.07.2024.
Hearing
The Tribunal granted the appellant's counsel time to examine cited precedents and adjourned the appeal to 09.05.2024.
Hearing
Upon the joint request of the counsel for both parties, the appeal has been adjourned and scheduled to be listed along with similar appeals on 08.04.2024.
Hearing
The Tribunal noted that the appeal is ready for hearing and scheduled it for a subsequent hearing on 18.03.2024.
Hearing
The Tribunal noted that the appeal is ready for hearing and scheduled it for a subsequent hearing on March 1, 2024.
For Order
The Tribunal granted an adjournment requested by the appellant's counsel due to him being out of station and rescheduled the hearing for 11.05.2023.
For Order
The Tribunal refers the parties to a previously passed order dated regarding Appeal No. (D) 285/2022.
For Order
The Tribunal granted the appellant a final 10-day extension to file a reply to the respondent's objections and directed that a soft copy be emailed to the respondent and uploaded to the e-portal.
Delay condonation
The Tribunal condoned the delay in filing the appeal based on Supreme Court guidelines regarding the extension of limitation and directed the Registry to convert the defective appeal into a regular appeal.
For Order
The Tribunal granted the applicant one week to file a reply to the respondent's objections and scheduled the matter for hearing on 21.10.2022.
Defect Removal
The Tribunal granted the appellant one week's time to file a reply to the respondent's objections and scheduled the case for hearing on 19.09.2022.
Defect Removal
The Tribunal granted the respondent 10 days to file objections and a Vakalatnama, and scheduled the matter for August 22, 2022, to consider an application for condonation of delay.
Defect Removal
The Tribunal granted the respondent 15 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for July 21, 2022.
Tribunal Order #0901126064932021-25-11-2024
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event.
Tribunal Disposal & Final Award Ruling
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event. Awarded in favor of Partial.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event.
Ruling Awarded To
Partial
Interest Period
from 13.04.2017 till handing over possession, excluding the period of injunction granted by the NGT from 17.12.2018 to 12.01.2021
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rakesh Bajpai
Respondent Advocate(s)
- Gulam Ali Rashidi
Official RERA Tribunal Orders (1)
The Tribunal ruled that delay interest for the 'Lohia Enclave Phase-1 Yojna' project must be computed from the initially declared completion date of 13.04.2017, while excluding the period of the NGT injunction (17.12.2018 to 12.01.2021) as a force majeure event.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.