up_reraStatus: Completed
CASE ID: 0901126064922022

Appellant / Complainant

Naresh Chandra Shastri

VS

Respondent

Awadh Infraland Ltd., Sanfran Developer Pvt Ltd, Allahbad Construction and Developers Associates

Developer Firm

awadh infraland ltd.

Disputed Amount

10,00,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

43 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126064922022 by Naresh Chandra Shastri against Awadh Infraland Ltd., Sanfran Developer Pvt Ltd, Allahbad Construction and Developers Associates before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 112/05/2026

Final Hearing

The Tribunal modified the previous order to grant the appellant a refund of Rs. 10,00,000/- along with interest at MCLR+1% per annum under Section 18(1) of the RERA Act, 2016, due to the project's failure to complete and deliver possession.

3
Stage 207/05/2026

For Order

The Tribunal noted the absence of the respondent/promoter and proceeded ex-parte, subsequently adjourning the matter to 12.05.2026 for final disposal.

4
Stage 308/04/2026

Hearing

The Tribunal granted the respondent a final 10-day extension to file objections, noting that the matter will proceed ex-parte if they fail to do so, and scheduled the next hearing for 07.05.2026.

5
Stage 418/03/2026

Hearing

At the request of the appellant's counsel, the matter has been adjourned and scheduled for orders on April 8, 2026.

6
Stage 513/02/2026

Hearing

The Tribunal noted the absence of the appellant's counsel and adjourned the appeal to 18.03.2026 for orders or hearing.

7
Stage 621/01/2026

Hearing

The Tribunal has granted a request to list the case for orders on 13.02.2026.

8
Stage 707/01/2026

Hearing

The Tribunal granted a request from the appellant's counsel to list the appeal for orders/hearing on 21.01.2026, noting that no further adjournments will be permitted.

9
Stage 809/12/2025

Hearing on Amendment Application

The Tribunal allowed the appellant's amendment application (IA No. 1383 of 2025) and directed the incorporation of necessary amendments to the memo of appeal within specified timelines.

10
Stage 914/11/2025

Hearing on Amendment Application

The Tribunal granted the respondent 10 days to file objections to an amendment application and scheduled the matter for hearing on 09.12.2025.

11
Stage 1031/10/2025

Hearing on Amendment Application

At the request of the appellant's counsel, the tribunal has adjourned the appeal and scheduled it for a new hearing date on 14.11.2025.

12
Stage 1126/09/2025

Hearing on Amendment Application

The Tribunal granted the appellant additional time to file an amendment application and scheduled the case for orders on 31.10.2025.

13
Stage 1203/09/2025

Hearing on Amendment Application

The Tribunal noted sufficient service of notice upon respondents 2 and 3, granted them 10 days to file objections, and scheduled the matter for hearing on 26.09.2025.

14
Stage 1319/08/2025

Hearing on Amendment Application

The Tribunal granted a request for adjournment on behalf of the appellant's counsel and rescheduled the appeal for hearing on 03.09.2025.

15
Stage 1428/07/2025

Hearing

The Tribunal allowed the application for impleadment, directing that the new parties be added to the array of opposite parties and issuing notices to them, with the matter listed for hearing on 19.08.2025.

16
Stage 1507/07/2025

Hearing

The Tribunal granted the appellant one week to file an impleadment application and scheduled the appeal for hearing on 28.07.2025.

17
Stage 1612/05/2025

Hearing

The appeal was adjourned due to the absence of both parties and is scheduled to be listed again on 07.07.2025.

18
Stage 1718/04/2025

Hearing

The Tribunal granted a request to list the appeal for order or hearing on 12.05.2025.

19
Stage 1821/03/2025

Hearing

The Tribunal granted an adjournment requested by the Appellant's counsel and rescheduled the appeal for hearing/orders on 18.04.2025.

20
Stage 1927/02/2025

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 21.03.2025.

21
Stage 2004/02/2025

Hearing

The Tribunal allowed the appellant's application for amendment to include the consideration amount paid and scheduled the matter for a hearing on 27.02.2025.

22
Stage 2107/01/2025

Hearing

The Tribunal granted the respondent 10 days to file objections to the appellant's amendment application dated 05.12.2024, with the matter scheduled for orders on 04.02.2025.

23
Stage 2209/12/2024

Hearing

The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the appeal for hearing on 07.01.2025.

24
Stage 2306/11/2024

Hearing

The Tribunal granted the appellant's counsel time to file an amendment application to the memo of appeal and scheduled the next hearing for December 9, 2024.

25
Stage 2416/10/2024

Hearing

The respondent developer has undertaken to refund the appellant the principal amount plus interest admissible under the Act, 2016, and is directed to make the payment via RTGS or produce a banker's cheque by the next hearing on 06.11.2024.

26
Stage 2512/09/2024

Hearing

The Tribunal granted the respondent a final opportunity to seek instructions and reply regarding the refund of the booking amount with interest, adjourning the matter to 16.10.2024.

27
Stage 2608/08/2024

Hearing

The appellant is seeking interest on the refund of their booking amount, and the respondent's counsel has been granted seven days to seek instructions regarding a potential settlement involving the refund plus interest (MCLR+1%).

28
Stage 2723/07/2024

Hearing

The Tribunal granted a request from the appellant's counsel for a short adjournment and scheduled the appeal for a final hearing on 08.08.2024.

29
Stage 2823/05/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the matter for consideration of the application for condonation of delay on 23.07.2024.

30
Stage 2908/05/2024

For Order

The Tribunal condoned a 3-day delay in filing the appeal due to technical server issues and scheduled the matter for hearing on 23.05.2024.

31
Stage 3005/04/2024

For Order

The Tribunal granted an adjournment due to the appellant's counsel's health and rescheduled the hearing for the application for condonation of delay to 08.05.2024.

32
Stage 3101/03/2024

For Order

The Tribunal has ordered the appeal to be listed for a hearing on 05.04.2024.

33
Stage 3219/01/2024

For Order

The Tribunal directed the respondent to file objections to the grounds of appeal within a week and granted the applicant one week to file a reply to the objections on the condonation of delay application. The matter is scheduled for hearing on 01.03.2024.

34
Stage 3317/10/2023

For Order

No text available.

35
Stage 3411/09/2023

For Order

The Tribunal adjourned the proceedings and rescheduled the appeal for orders to 17.10.2023 due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh.

36
Stage 3508/08/2023

For Order

The Tribunal allowed the appellant's application to serve notice to the respondent via Dasti and email, scheduling the matter for hearing on the application for condonation of delay on 11.09.2023.

37
Stage 3626/05/2023

For Order

No text available.

38
Stage 3717/04/2023

Defect Removal

The Tribunal issued notice to the respondent regarding the appellant's application for condonation of delay and outlined the procedural steps for service of notice and filing of objections.

39
Stage 38Final Ruling Order

Tribunal Order #0901126064922022-12-05-2026

The Tribunal modified the previous order to grant the appellant a refund of Rs. 10,00,000/- along with interest at MCLR+1% per annum under Section 18(1) of the RERA Act, 2016, due to the project's failure to complete and deliver possession.

40
Stage 39Interim Order

Tribunal Order #0901126064922022-09-12-2025

The Tribunal allowed the appellant's amendment application (IA No. 1383 of 2025) and directed the incorporation of necessary amendments to the memo of appeal within specified timelines.

41
Stage 40Interim Order

Tribunal Order #0901126064922022-16-10-2024

The respondent developer has undertaken to refund the appellant the principal amount plus interest admissible under the Act, 2016, and is directed to make the payment via RTGS or produce a banker's cheque by the next hearing on 06.11.2024.

42
Stage 41Interim Order

Tribunal Order #0901126064922022-08-08-2024

The appellant is seeking interest on the refund of their booking amount, and the respondent's counsel has been granted seven days to seek instructions regarding a potential settlement involving the refund plus interest (MCLR+1%).

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal modified the previous order to grant the appellant a refund of Rs. 10,00,000/- along with interest at MCLR+1% per annum under Section 18(1) of the RERA Act, 2016, due to the project's failure to complete and deliver possession. Awarded in favor of Appellant. Awarded interest rate: MCLR+1 percent.

Disposal Winner: AppellantInterest Rate: MCLR+1 percentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal modified the previous order to grant the appellant a refund of Rs. 10,00,000/- along with interest at MCLR+1% per annum under Section 18(1) of the RERA Act, 2016, due to the project's failure to complete and deliver possession.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1 percent

Interest Period

till the date of payment to be made by the respondent within 45 days from the date this order is uploaded on the portal of the Tribunal

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shailendra Kumar Singh

Respondent Advocate(s)

  • Virendra Vikram Singh

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126064922022-12-05-2026

The Tribunal modified the previous order to grant the appellant a refund of Rs. 10,00,000/- along with interest at MCLR+1% per annum under Section 18(1) of the RERA Act, 2016, due to the project's failure to complete and deliver possession.

INTERIM_ORDEROrder ID: 0901126064922022-09-12-2025

The Tribunal allowed the appellant's amendment application (IA No. 1383 of 2025) and directed the incorporation of necessary amendments to the memo of appeal within specified timelines.

INTERIM_ORDEROrder ID: 0901126064922022-16-10-2024

The respondent developer has undertaken to refund the appellant the principal amount plus interest admissible under the Act, 2016, and is directed to make the payment via RTGS or produce a banker's cheque by the next hearing on 06.11.2024.

INTERIM_ORDEROrder ID: 0901126064922022-08-08-2024

The appellant is seeking interest on the refund of their booking amount, and the respondent's counsel has been granted seven days to seek instructions regarding a potential settlement involving the refund plus interest (MCLR+1%).

TathyaGrid RERA Intelligence AI

Need to research all rulings for awadh infraland ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →