Appellant / Complainant
Naresh Chandra Shastri
Respondent
Awadh Infraland Ltd., Sanfran Developer Pvt Ltd, Allahbad Construction and Developers Associates
awadh infraland ltd.
₹10,00,000
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126064922022 by Naresh Chandra Shastri against Awadh Infraland Ltd., Sanfran Developer Pvt Ltd, Allahbad Construction and Developers Associates before up_rera.
Final Hearing
The Tribunal modified the previous order to grant the appellant a refund of Rs. 10,00,000/- along with interest at MCLR+1% per annum under Section 18(1) of the RERA Act, 2016, due to the project's failure to complete and deliver possession.
For Order
The Tribunal noted the absence of the respondent/promoter and proceeded ex-parte, subsequently adjourning the matter to 12.05.2026 for final disposal.
Hearing
The Tribunal granted the respondent a final 10-day extension to file objections, noting that the matter will proceed ex-parte if they fail to do so, and scheduled the next hearing for 07.05.2026.
Hearing
At the request of the appellant's counsel, the matter has been adjourned and scheduled for orders on April 8, 2026.
Hearing
The Tribunal noted the absence of the appellant's counsel and adjourned the appeal to 18.03.2026 for orders or hearing.
Hearing
The Tribunal has granted a request to list the case for orders on 13.02.2026.
Hearing
The Tribunal granted a request from the appellant's counsel to list the appeal for orders/hearing on 21.01.2026, noting that no further adjournments will be permitted.
Hearing on Amendment Application
The Tribunal allowed the appellant's amendment application (IA No. 1383 of 2025) and directed the incorporation of necessary amendments to the memo of appeal within specified timelines.
Hearing on Amendment Application
The Tribunal granted the respondent 10 days to file objections to an amendment application and scheduled the matter for hearing on 09.12.2025.
Hearing on Amendment Application
At the request of the appellant's counsel, the tribunal has adjourned the appeal and scheduled it for a new hearing date on 14.11.2025.
Hearing on Amendment Application
The Tribunal granted the appellant additional time to file an amendment application and scheduled the case for orders on 31.10.2025.
Hearing on Amendment Application
The Tribunal noted sufficient service of notice upon respondents 2 and 3, granted them 10 days to file objections, and scheduled the matter for hearing on 26.09.2025.
Hearing on Amendment Application
The Tribunal granted a request for adjournment on behalf of the appellant's counsel and rescheduled the appeal for hearing on 03.09.2025.
Hearing
The Tribunal allowed the application for impleadment, directing that the new parties be added to the array of opposite parties and issuing notices to them, with the matter listed for hearing on 19.08.2025.
Hearing
The Tribunal granted the appellant one week to file an impleadment application and scheduled the appeal for hearing on 28.07.2025.
Hearing
The appeal was adjourned due to the absence of both parties and is scheduled to be listed again on 07.07.2025.
Hearing
The Tribunal granted a request to list the appeal for order or hearing on 12.05.2025.
Hearing
The Tribunal granted an adjournment requested by the Appellant's counsel and rescheduled the appeal for hearing/orders on 18.04.2025.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 21.03.2025.
Hearing
The Tribunal allowed the appellant's application for amendment to include the consideration amount paid and scheduled the matter for a hearing on 27.02.2025.
Hearing
The Tribunal granted the respondent 10 days to file objections to the appellant's amendment application dated 05.12.2024, with the matter scheduled for orders on 04.02.2025.
Hearing
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the appeal for hearing on 07.01.2025.
Hearing
The Tribunal granted the appellant's counsel time to file an amendment application to the memo of appeal and scheduled the next hearing for December 9, 2024.
Hearing
The respondent developer has undertaken to refund the appellant the principal amount plus interest admissible under the Act, 2016, and is directed to make the payment via RTGS or produce a banker's cheque by the next hearing on 06.11.2024.
Hearing
The Tribunal granted the respondent a final opportunity to seek instructions and reply regarding the refund of the booking amount with interest, adjourning the matter to 16.10.2024.
Hearing
The appellant is seeking interest on the refund of their booking amount, and the respondent's counsel has been granted seven days to seek instructions regarding a potential settlement involving the refund plus interest (MCLR+1%).
Hearing
The Tribunal granted a request from the appellant's counsel for a short adjournment and scheduled the appeal for a final hearing on 08.08.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the matter for consideration of the application for condonation of delay on 23.07.2024.
For Order
The Tribunal condoned a 3-day delay in filing the appeal due to technical server issues and scheduled the matter for hearing on 23.05.2024.
For Order
The Tribunal granted an adjournment due to the appellant's counsel's health and rescheduled the hearing for the application for condonation of delay to 08.05.2024.
For Order
The Tribunal has ordered the appeal to be listed for a hearing on 05.04.2024.
For Order
The Tribunal directed the respondent to file objections to the grounds of appeal within a week and granted the applicant one week to file a reply to the objections on the condonation of delay application. The matter is scheduled for hearing on 01.03.2024.
For Order
The Tribunal adjourned the proceedings and rescheduled the appeal for orders to 17.10.2023 due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh.
For Order
The Tribunal allowed the appellant's application to serve notice to the respondent via Dasti and email, scheduling the matter for hearing on the application for condonation of delay on 11.09.2023.
Defect Removal
The Tribunal issued notice to the respondent regarding the appellant's application for condonation of delay and outlined the procedural steps for service of notice and filing of objections.
Tribunal Order #0901126064922022-12-05-2026
The Tribunal modified the previous order to grant the appellant a refund of Rs. 10,00,000/- along with interest at MCLR+1% per annum under Section 18(1) of the RERA Act, 2016, due to the project's failure to complete and deliver possession.
Tribunal Order #0901126064922022-09-12-2025
The Tribunal allowed the appellant's amendment application (IA No. 1383 of 2025) and directed the incorporation of necessary amendments to the memo of appeal within specified timelines.
Tribunal Order #0901126064922022-16-10-2024
The respondent developer has undertaken to refund the appellant the principal amount plus interest admissible under the Act, 2016, and is directed to make the payment via RTGS or produce a banker's cheque by the next hearing on 06.11.2024.
Tribunal Order #0901126064922022-08-08-2024
The appellant is seeking interest on the refund of their booking amount, and the respondent's counsel has been granted seven days to seek instructions regarding a potential settlement involving the refund plus interest (MCLR+1%).
Tribunal Disposal & Final Award Ruling
The Tribunal modified the previous order to grant the appellant a refund of Rs. 10,00,000/- along with interest at MCLR+1% per annum under Section 18(1) of the RERA Act, 2016, due to the project's failure to complete and deliver possession. Awarded in favor of Appellant. Awarded interest rate: MCLR+1 percent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal modified the previous order to grant the appellant a refund of Rs. 10,00,000/- along with interest at MCLR+1% per annum under Section 18(1) of the RERA Act, 2016, due to the project's failure to complete and deliver possession.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1 percent
Interest Period
till the date of payment to be made by the respondent within 45 days from the date this order is uploaded on the portal of the Tribunal
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Shailendra Kumar Singh
Respondent Advocate(s)
- Virendra Vikram Singh
Official RERA Tribunal Orders (4)
The Tribunal modified the previous order to grant the appellant a refund of Rs. 10,00,000/- along with interest at MCLR+1% per annum under Section 18(1) of the RERA Act, 2016, due to the project's failure to complete and deliver possession.
The Tribunal allowed the appellant's amendment application (IA No. 1383 of 2025) and directed the incorporation of necessary amendments to the memo of appeal within specified timelines.
The respondent developer has undertaken to refund the appellant the principal amount plus interest admissible under the Act, 2016, and is directed to make the payment via RTGS or produce a banker's cheque by the next hearing on 06.11.2024.
The appellant is seeking interest on the refund of their booking amount, and the respondent's counsel has been granted seven days to seek instructions regarding a potential settlement involving the refund plus interest (MCLR+1%).
Need to research all rulings for awadh infraland ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.