Appellant / Complainant
Rinzing Lama
Respondent
Jkg Constructions Pvt Ltd, Anarock Property Consultants Private Limited
jkg constructions pvt ltd
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126063412022 by Rinzing Lama against Jkg Constructions Pvt Ltd, Anarock Property Consultants Private Limited before up_rera.
Delay condonation
The appeal was dismissed as withdrawn following an amicable settlement reached between the appellant, Rinzing Lama, and the respondent, JKG Constructions Pvt Ltd.
Delay condonation
The Tribunal granted a request for adjournment made by the respondent's counsel and rescheduled the appeal for hearing on 16.04.2025.
Delay condonation
The Tribunal granted a request for an adjournment to allow the parties time to pursue an amicable settlement and scheduled the next hearing for March 19, 2025.
Delay condonation
The matter is adjourned to 27.02.2025 as the appellant's counsel informed the court that efforts are being made to settle the dispute out of court.
Delay condonation
The Tribunal granted a request by the appellant's counsel to adjourn the matter as settlement negotiations are underway, rescheduling the hearing for 04.02.2025.
Hearing
Upon the joint request of the counsels for both parties, the appeal has been adjourned and listed for orders/hearing on 19.12.2024.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the hearing for 22.11.2024.
Hearing
Upon the joint request of both parties, the tribunal has adjourned the appeal for orders or hearing to 16.10.2024.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the hearing for the application for condonation of delay on 02.08.2024.
Hearing
The Tribunal adjourned the proceedings due to the absence of counsel for both parties and scheduled the defective appeal for a hearing on 03.07.2024.
Hearing
The Tribunal has scheduled the appeal for hearing on May 3, 2024, to consider an application for condonation of delay.
Hearing
The Tribunal has scheduled the appeal for a subsequent hearing on 01.04.2024.
Hearing
The Tribunal noted the absence of counsel for both parties during the rounds of hearing and rescheduled the matter to 29.02.2024 for consideration of the delay condonation application and further hearing.
For Order
The Tribunal adjourned the proceedings due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh and rescheduled the hearing for 26.10.2023.
For Order
The Tribunal granted the applicant 10 days to file a reply to the objections raised by the respondent and scheduled the matter for further hearing on 26.07.2023.
For Order
The Tribunal granted the respondent one week to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent reply period for the applicant, and scheduled the matter for hearing on 15.05.2023.
For Order
The Tribunal granted the respondent 10 days to file objections and a Vakalatnama, with the appellant permitted to file a reply within one week thereafter. The matter is scheduled for hearing on 03.04.2023.
Delay condonation
The Tribunal issued a notice to the respondent regarding an application for condonation of delay and directed the appellant's counsel to serve the necessary documents via speed post and email.
Tribunal Disposal & Final Award Ruling
Dismissed as withdrawn Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed as withdrawn
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Kushagra Dikshit
- Fuhar Gupta
Respondent Advocate(s)
- Saurabh Misra
- Gautam Johri