Appellant / Complainant
Pradeep Bansal
Respondent
Eminent Planners & Developers Pvt. Ltd.
eminent planners & developers pvt. ltd.
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126060892021 by Pradeep Bansal against Eminent Planners & Developers Pvt. Ltd. before up_rera.
Hearing
The Tribunal dismissed the appeal, ruling that U.P. RERA lacks jurisdiction to adjudicate complaints regarding unregistered projects, while upholding the Regulatory Authority's direction to take action against the respondent for statutory violations.
Ex-Parte
The Tribunal heard arguments from the appellant's counsel and reserved the judgment for a later date.
Ex-Parte
The Tribunal noted the respondent's absence and scheduled the case for the delivery of judgment on November 11, 2022.
Ex-Parte
The Tribunal directed the appellant's counsel to file a list of dates and relied-upon judgments and scheduled the matter for an ex-parte hearing on 19.10.2022.
Hearing
Due to the respondent's failure to appear despite being served, the Tribunal ordered the case to proceed ex-parte and scheduled it for an ex-parte hearing on 21.09.2022.
Hearing
The Tribunal accepted the appellant's argument that publication in 'Amar Ujala' constitutes sufficient notice based on Supreme Court precedent, and scheduled the matter for further orders on 23.08.2022.
Hearing
The Tribunal permitted the appellant to serve notice to the respondent via their registered e-mail ID and speed post instead of newspaper publication, and scheduled the matter for 13.07.2022.
Hearing on Appeal
The Tribunal directed the appellant to justify the publication of notice in 'Amar Ujala' instead of the specified newspapers or take alternative steps to serve the respondent.
Hearing on Appeal
The Tribunal directed the appellant to publish a notice in newspapers circulating in Agra (such as Dainik Jagran, Hindustan Times, or Times of India) within 15 days and scheduled the next hearing for February 10, 2022.
Hearing on Appeal
The Tribunal issued notice to the respondent and established a procedural timeline for the service of appeal documents, filing of objections, and subsequent replies before the next hearing on 10.01.2022.
Tribunal Order #0901126060892021-02-05-2023
The Tribunal dismissed the appeal, ruling that U.P. RERA lacks jurisdiction to adjudicate complaints regarding unregistered projects, while upholding the Regulatory Authority's direction to take action against the respondent for statutory violations.
Tribunal Order #0901126060892021-13-07-2022
The Tribunal accepted the appellant's argument that publication in 'Amar Ujala' constitutes sufficient notice based on Supreme Court precedent, and scheduled the matter for further orders on 23.08.2022.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal, ruling that U.P. RERA lacks jurisdiction to adjudicate complaints regarding unregistered projects, while upholding the Regulatory Authority's direction to take action against the respondent for statutory violations. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal, ruling that U.P. RERA lacks jurisdiction to adjudicate complaints regarding unregistered projects, while upholding the Regulatory Authority's direction to take action against the respondent for statutory violations.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Fuhar Gupta
- Prashant Kumar
Official RERA Tribunal Orders (2)
The Tribunal dismissed the appeal, ruling that U.P. RERA lacks jurisdiction to adjudicate complaints regarding unregistered projects, while upholding the Regulatory Authority's direction to take action against the respondent for statutory violations.
The Tribunal accepted the appellant's argument that publication in 'Amar Ujala' constitutes sufficient notice based on Supreme Court precedent, and scheduled the matter for further orders on 23.08.2022.