up_reraStatus: Completed
CASE ID: 0901126060462021

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Madhvendra Kumar Pandey

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

32 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126060462021 by Lucknow Development Authority against Madhvendra Kumar Pandey before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 103/01/2025

For Order

The Tribunal quashed the Adjudicating Officer's order for lack of jurisdiction but directed the appellant to pay delay interest at MCLR+1% per annum for the period from 30.08.2015 to 07.08.2019.

3
Stage 207/08/2024

Hearing

The Tribunal decided to proceed with an ex-parte hearing due to the respondent's repeated failure to appear and reserved its judgment following arguments from the appellant.

4
Stage 319/07/2024

Hearing

The Tribunal granted a request by the appellant's counsel to list this appeal alongside connected matters on 07.08.2024.

5
Stage 404/07/2024

Hearing

The Tribunal granted a final opportunity to the respondent to appear and scheduled the appeal for hearing on 19.07.2024.

6
Stage 506/05/2024

Hearing

The Tribunal noted the absence of both parties and rescheduled the appeal for orders/hearing on 04.07.2024.

7
Stage 616/04/2024

Hearing

The Tribunal noted the absence of the respondent and, upon being informed by the appellant's counsel that the matter is ripe for hearing, rescheduled the appeal for hearing on 06.05.2024.

8
Stage 714/03/2024

Hearing

The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections due to repeated failure to do so and scheduled the appeal for hearing on 16.04.2024.

9
Stage 807/02/2024

Hearing

The Tribunal granted the appellant one week to file a reply to the respondent's objection and scheduled the appeal for hearing on 14.03.2024.

10
Stage 908/11/2023

Hearing

No text available.

11
Stage 1025/09/2023

Hearing

The Tribunal granted a 10-day extension to the appellant for filing a reply to the respondent's objections and scheduled the next hearing for November 8, 2023.

12
Stage 1116/08/2023

Hearing

The Tribunal granted a 10-day extension for filing an affidavit and Vakalatnama, and scheduled the appeal for hearing on September 25, 2023.

13
Stage 1231/05/2023

Hearing

The Tribunal granted the appellant, Lucknow Development Authority, 10 days to file a reply to the respondent's objections and to submit the Vakalatnama for Sri Abhishek Khare.

14
Stage 1317/03/2023

Hearing

The Tribunal dismissed the appeal for want of prosecution because the Lucknow Development Authority failed to nominate a new counsel following the resignation of their previous lawyer and failed to inform the court of any difficulties.

15
Stage 1408/02/2023

Hearing

No text available.

16
Stage 1509/01/2023

Notice

The Tribunal granted the appellant one week's time to file a reply to the respondent's objections and scheduled the next hearing for February 8, 2023.

17
Stage 1614/12/2022

Notice

The Tribunal has scheduled the appeal for a hearing on January 9, 2023.

18
Stage 1718/11/2022

Notice

The U.P. Real Estate Appellate Tribunal adjourned the appeal to 14.12.2022 due to the absence of the respondent.

19
Stage 1821/10/2022

Notice

The Tribunal adjourned the appeal to 18.11.2022 for further orders after noting that no one appeared in court despite a Vakalatnama being filed on behalf of the respondent.

20
Stage 1921/09/2022

Exchange of pleadings

The Tribunal issued a notice to the respondent for 21.10.2022 and directed the appellant to serve the memo of appeal via speed-post and email, with instructions for subsequent filing of replies.

21
Stage 2024/08/2022

Exchange of pleadings

The Tribunal directed the respondent's counsel to file a Vakalatnama and a reply to the grounds of appeal before the next hearing date.

22
Stage 2112/07/2022

Further Order

The Tribunal granted the respondent a final opportunity to file a reply to the grounds of appeal and scheduled the matter for further orders on 24.08.2022.

23
Stage 2202/05/2022

Further Order

The Tribunal issued a notice to the respondent and directed the appellant to serve the memo of appeal via speed-post and email, with the matter listed for further orders on 12.07.2022.

24
Stage 2325/03/2022

Hearing

The Tribunal allowed the application for condonation of delay, condoning a 55-day delay in filing the appeal due to the COVID-19 pandemic extension period, and directed the defective appeal to be registered as a Regular Appeal.

25
Stage 2425/02/2022

Compliance of section 43(5)

The Tribunal directed the parties to file objections and pleadings on the e-portal within specified timelines and scheduled the matter for hearing on the application for condonation of delay on 25.03.2022.

26
Stage 2517/01/2022

Compliance of section 43(5)

No text available.

27
Stage 2615/12/2021

Defect Removal

The Tribunal directed the appellant to remove registry defects before the next hearing and ordered that notice be issued to the respondent via registered post and email.

28
Stage 27Final Ruling Order

Tribunal Order #0901126060462021-03-01-2025

The Tribunal quashed the Adjudicating Officer's order for lack of jurisdiction but directed the appellant to pay delay interest at MCLR+1% per annum for the period from 30.08.2015 to 07.08.2019.

29
Stage 28Interim Order

Tribunal Order #0901126060462021-17-03-2023

The Tribunal dismissed the appeal for want of prosecution because the Lucknow Development Authority failed to nominate a new counsel following the resignation of their previous lawyer and failed to inform the court of any difficulties.

30
Stage 29Interim Order

Tribunal Order #0901126060462021-25-03-2022

The Tribunal allowed the application for condonation of delay, condoning a 55-day delay in filing the appeal due to the COVID-19 pandemic extension period, and directed the defective appeal to be registered as a Regular Appeal.

31
Stage 30Interim Order

Tribunal Order #0901126060462021-07-08-2024

The Tribunal decided to proceed with an ex-parte hearing due to the respondent's repeated failure to appear and reserved its judgment following arguments from the appellant.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal quashed the Adjudicating Officer's order for lack of jurisdiction but directed the appellant to pay delay interest at MCLR+1% per annum for the period from 30.08.2015 to 07.08.2019. Awarded in favor of Partial. Awarded interest rate: MCLR+1% per annum.

Disposal Winner: PartialInterest Rate: MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal quashed the Adjudicating Officer's order for lack of jurisdiction but directed the appellant to pay delay interest at MCLR+1% per annum for the period from 30.08.2015 to 07.08.2019.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1% per annum

Interest Period

30.08.2015 to 07.08.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhinav Mani Tripathi

Respondent Advocate(s)

  • Suyash Gupta

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126060462021-03-01-2025

The Tribunal quashed the Adjudicating Officer's order for lack of jurisdiction but directed the appellant to pay delay interest at MCLR+1% per annum for the period from 30.08.2015 to 07.08.2019.

INTERIM_ORDEROrder ID: 0901126060462021-17-03-2023

The Tribunal dismissed the appeal for want of prosecution because the Lucknow Development Authority failed to nominate a new counsel following the resignation of their previous lawyer and failed to inform the court of any difficulties.

INTERIM_ORDEROrder ID: 0901126060462021-25-03-2022

The Tribunal allowed the application for condonation of delay, condoning a 55-day delay in filing the appeal due to the COVID-19 pandemic extension period, and directed the defective appeal to be registered as a Regular Appeal.

INTERIM_ORDEROrder ID: 0901126060462021-07-08-2024

The Tribunal decided to proceed with an ex-parte hearing due to the respondent's repeated failure to appear and reserved its judgment following arguments from the appellant.