up_reraStatus: Completed
CASE ID: 0901126059122021

Appellant / Complainant

Bhagwan Sarup Agarwal

VS

Respondent

UP RERA Gautambudhnagar, Uppal Chaddha Hi Tech Developers Pvt Ltd

Developer Firm

uppal chaddha hi tech developers pvt ltd

Disputed Amount

19,86,750

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

26 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126059122021 by Bhagwan Sarup Agarwal against UP RERA Gautambudhnagar, Uppal Chaddha Hi Tech Developers Pvt Ltd before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferNon-Compliance & Execution
2
Stage 119/02/2024

Hearing

The Tribunal declined to set aside the recovery certificate but granted the appellant liberty to approach the Secretary of the Regulatory Authority for a rectification of the interest calculation date to align with the original order.

3
Stage 218/01/2024

Hearing

The Tribunal directed the respondent's counsel to register his name in the case records and scheduled the appeal for a hearing on 19.02.2024.

4
Stage 316/10/2023

Hearing

No text available.

5
Stage 406/09/2023

Hearing

The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the matter for hearing on 16.10.2023.

6
Stage 516/08/2023

Admission

The Tribunal noted that the case was wrongly listed for today's date and directed the matter to be listed for hearing on 06.09.2023.

7
Stage 611/08/2023

Delay condonation

The Tribunal condoned the delay in filing the appeal by invoking the Supreme Court's Suo Moto order dated 10.01.2022 and directed the Registry to convert the defective appeal into a regular appeal.

8
Stage 714/07/2023

Delay condonation

The Tribunal has scheduled the defective appeal for a hearing on September 5, 2023, to consider the application for condonation of delay.

9
Stage 802/05/2023

Delay condonation

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 14.07.2023.

10
Stage 921/03/2023

Delay condonation

No text available.

11
Stage 1010/02/2023

Delay condonation

No text available.

12
Stage 1106/01/2023

Delay condonation

No text available.

13
Stage 1206/12/2022

Delay condonation

No text available.

14
Stage 1310/11/2022

For Order

The Tribunal noted a clerical error in the respondent's address on the notice and directed the issuance of fresh notices to be served via speed post and email.

15
Stage 1401/11/2022

Notice

The Tribunal granted the appellant's counsel one week to file an affidavit of service and scheduled the defective appeal for a hearing on November 10, 2022.

16
Stage 1527/09/2022

Notice

The Tribunal issued fresh notice to the respondent and directed the applicant to serve the appeal documents via speed-post and email, scheduling the matter for 01.11.2022 to address the application for condonation of delay.

17
Stage 1629/08/2022

Notice

No text available.

18
Stage 1701/08/2022

Delay condonation

The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and directed specific procedures for service of notice and filing of objections.

19
Stage 1821/07/2022

Delay condonation

The Tribunal granted the appellant one week to comply with a previous order dated 19.05.2022 and scheduled the case for hearing on 01.08.2022 regarding the application for condonation of delay.

20
Stage 1930/05/2022

Delay condonation

No text available.

21
Stage 2019/05/2022

Defect Removal

The Tribunal granted the appellant one week to file an application for condonation of delay and directed that a soft copy be sent to the respondent and uploaded to the e-portal before the next hearing on 30.05.2022.

22
Stage 2110/05/2022

Defect Removal

The Tribunal directed the appellant's counsel to rectify procedural defects, including missing document uploads and improper annexure ordering, within one week.

23
Stage 2202/05/2022

Defect Removal

The Tribunal directed the appellant's counsel to rectify registry-identified defects within three days and scheduled the matter for further orders on 10.05.2022.

24
Stage 23Final Ruling Order

Tribunal Order #0901126059122021-19-02-2024

The Tribunal declined to set aside the recovery certificate but granted the appellant liberty to approach the Secretary of the Regulatory Authority for a rectification of the interest calculation date to align with the original order.

25
Stage 24Interim Order

Tribunal Order #0901126059122021-11-08-2023

The Tribunal condoned the delay in filing the appeal by invoking the Supreme Court's Suo Moto order dated 10.01.2022 and directed the Registry to convert the defective appeal into a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal declined to set aside the recovery certificate but granted the appellant liberty to approach the Secretary of the Regulatory Authority for a rectification of the interest calculation date to align with the original order. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal declined to set aside the recovery certificate but granted the appellant liberty to approach the Secretary of the Regulatory Authority for a rectification of the interest calculation date to align with the original order.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 23.09.2015 till receipt of OC/CC or offer of possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ashutosh Mishra
  • Shivam Gupta

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126059122021-19-02-2024

The Tribunal declined to set aside the recovery certificate but granted the appellant liberty to approach the Secretary of the Regulatory Authority for a rectification of the interest calculation date to align with the original order.

INTERIM_ORDEROrder ID: 0901126059122021-11-08-2023

The Tribunal condoned the delay in filing the appeal by invoking the Supreme Court's Suo Moto order dated 10.01.2022 and directed the Registry to convert the defective appeal into a regular appeal.

TathyaGrid RERA Intelligence AI