Appellant / Complainant
Ashok Verma
Respondent
Abhisht Developers Builders Pvt. Ltd.
abhisht developers builders pvt. ltd.
₹24,46,967
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126057852022 by Ashok Verma against Abhisht Developers Builders Pvt. Ltd. before up_rera.
for delivery of Judgment/Order
The Tribunal set aside the Regulatory Authority's order, ruling that the promoter's cancellation of the allotment was invalid and directing the promoter to issue a fresh demand notice after adjusting delay interest at MCLR+1% from 04.02.2014.
Hearing
The Tribunal heard arguments from both parties regarding the appeal and has reserved its judgment for a later date.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the case for orders/hearing on 21.02.2025.
Hearing
The Tribunal granted the appellant 10 days to file a rejoinder to the respondent's objections and scheduled the next hearing for January 29, 2025.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on January 8, 2025.
Hearing
The Tribunal granted the appellant seven days to file a rejoinder affidavit regarding the respondent's objections and scheduled the matter for hearing on 28.10.2024.
Hearing
The Tribunal granted the respondent seven days to file objections to the amended memo of appeal and directed the appellant to reply within a week thereafter, scheduling the next hearing for 20.09.2024.
Hearing
The Tribunal granted the appellant a final 7-day extension to file a reply to the respondent's objections against the amended memo of appeal and scheduled the next hearing for 14.08.2024.
Hearing
The Tribunal granted a request for adjournment from the appellant's counsel and rescheduled the appeal for hearing on 16.05.2024.
Hearing
The Tribunal allowed the appellant's amendment application (IA No. 699 of 2024) to add new grounds and prayers regarding a unit cancellation, directing both parties to file amended pleadings and objections before the next hearing on 16.04.2024.
Hearing
The Tribunal granted the respondent one week to produce evidence regarding the communication of the appellant's unit cancellation and scheduled the matter for hearing on 12.03.2024.
Hearing
The Tribunal noted the absence of the respondent's counsel and adjourned the appeal to 21.02.2024 for hearing or orders.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel on health grounds and rescheduled the hearing for 11.10.2023.
Hearing
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the defective appeal for hearing on 25.08.2023.
Notice
The Tribunal granted the respondent 10 days to file objections against the application for condonation of delay and grounds of appeal, with a subsequent one-week window for the applicant to reply.
Admission
The Tribunal issued a notice to the respondent and outlined the procedural timeline for service of appeal documents and the filing of objections and replies.
Tribunal Order #0901126057852022-12-03-2024
The Tribunal allowed the appellant's amendment application (IA No. 699 of 2024) to add new grounds and prayers regarding a unit cancellation, directing both parties to file amended pleadings and objections before the next hearing on 16.04.2024.
Tribunal Order #0901126057852022-29-05-2025
The Tribunal set aside the Regulatory Authority's order, ruling that the promoter's cancellation of the allotment was invalid and directing the promoter to issue a fresh demand notice after adjusting delay interest at MCLR+1% from 04.02.2014.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside the Regulatory Authority's order, ruling that the promoter's cancellation of the allotment was invalid and directing the promoter to issue a fresh demand notice after adjusting delay interest at MCLR+1% from 04.02.2014. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1% p.a..
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside the Regulatory Authority's order, ruling that the promoter's cancellation of the allotment was invalid and directing the promoter to issue a fresh demand notice after adjusting delay interest at MCLR+1% from 04.02.2014.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR + 1% p.a.
Interest Period
from 04.02.2014 till the date of obtaining OC/CC or handing over the possession (after executing the conveyance deed) of the unit whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Shantanu Gupta
Respondent Advocate(s)
- Amit Yadav
- Swetank Sharma
Official RERA Tribunal Orders (2)
The Tribunal allowed the appellant's amendment application (IA No. 699 of 2024) to add new grounds and prayers regarding a unit cancellation, directing both parties to file amended pleadings and objections before the next hearing on 16.04.2024.
The Tribunal set aside the Regulatory Authority's order, ruling that the promoter's cancellation of the allotment was invalid and directing the promoter to issue a fresh demand notice after adjusting delay interest at MCLR+1% from 04.02.2014.
Need to research all rulings for abhisht developers builders pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.