up_reraStatus: Completed
CASE ID: 0901126057582022

Appellant / Complainant

Neeraj Kumar Srivastava

VS

Respondent

Dhanya Promoters Private Limited (Mahagun Group)

Developer Firm

dhanya promoters private limited

Disputed Amount

33,46,175

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

31 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126057582022 by Neeraj Kumar Srivastava against Dhanya Promoters Private Limited (Mahagun Group) before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 116/05/2025

Hearing

The Tribunal allowed the appeals, modifying the previous order to grant the appellants delay interest from 08.06.2018 until the receipt of the Occupancy Certificate/Completion Certificate (OC/CC) or a valid offer of possession, whichever is later.

3
Stage 222/04/2025

For Order

The Tribunal allowed the appellant's application for condonation of delay due to technical issues with the portal and directed the conversion of the defective appeal into a regular appeal.

4
Stage 324/03/2025

For Order

The Tribunal granted the respondent 10 days to file objections and directed the appellant to reply within one week thereafter, scheduling the hearing for the application for condonation of delay on 22.04.2025.

5
Stage 427/02/2025

For Order

The Tribunal allowed the appellant's amendment application to correct the respondent's address and delete a relief, and directed the issuance of fresh notice to the respondent for the next hearing on 24.03.2025.

6
Stage 507/02/2025

For Order

The Tribunal granted the appellant time to file an amendment application and provide a new address for the respondent after the initial notice was returned undelivered.

7
Stage 615/01/2025

For Order

The Tribunal issued notice to the respondents and directed the appellant to serve the application for condonation of delay and memo of appeal via speed-post and email, scheduling the next hearing for February 7, 2025.

8
Stage 708/01/2025

For Order

The Tribunal granted the appellant time to file an amendment application for the prayer clause and rescheduled the hearing for January 15, 2025, to consider the application for condonation of delay.

9
Stage 829/08/2024

Delay condonation

The Tribunal heard arguments regarding the lack of Occupancy Certificate (OC) or Completion Certificate (CC) for the project and reserved judgment, noting that the matter is covered by a previous precedent.

10
Stage 905/08/2024

Delay condonation

The Tribunal noted the appellant's submission of an RTI response regarding the project's completion certificate and scheduled the next hearing for 29.08.2024.

11
Stage 1005/07/2024

Delay condonation

No text available.

12
Stage 1107/05/2024

Delay condonation

The Tribunal granted the appellant one week to file information regarding the respondent's efforts to secure OC/CC and scheduled the hearing for the application for condonation of delay on 05.07.2024.

13
Stage 1208/04/2024

Delay condonation

The Tribunal granted the appellant one week to obtain information from the Greater Noida Industrial Development Authority regarding the project's OC/CC status and scheduled the matter for hearing on 07.05.2024.

14
Stage 1304/03/2024

Delay condonation

The Tribunal closed the respondent's opportunity to file objections and ordered the matter to proceed ex-parte due to their failure to appear or file responses. The case is scheduled for an ex-parte hearing on the application for condonation of delay on 08.04.2024.

15
Stage 1423/01/2024

Delay condonation

The Tribunal deemed service of notice to the respondent sufficient and granted the respondent 10 days to file objections to the condonation of delay application and grounds of appeal.

16
Stage 1519/10/2023

Delay condonation

No text available.

17
Stage 1613/09/2023

Delay condonation

No text available.

18
Stage 1725/07/2023

Delay condonation

No text available.

19
Stage 1812/05/2023

Delay condonation

No text available.

20
Stage 1929/03/2023

Delay condonation

The Tribunal issued fresh notice to the respondent due to the applicant's failure to comply with previous service directions, imposing a cost of Rs. 1,000/- on the applicant for their lackadaisical attitude.

21
Stage 2003/03/2023

Notice

The appeal was dismissed for want of prosecution due to the non-appearance of the applicant and their counsel.

22
Stage 2101/02/2023

Notice

No text available.

23
Stage 2223/12/2022

Notice

The Tribunal issued fresh notices regarding the application for condonation of delay and directed the applicant to serve the respondent via speed post and email before the next hearing on 01.02.2023.

24
Stage 2301/12/2022

Defect Removal

The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the applicant to serve the notice via speed-post and email, scheduling the next hearing for 23.12.2022.

25
Stage 24Final Ruling Order

Tribunal Order #0901126057582022-16-05-2025

The Tribunal allowed the appeals, modifying the previous order to grant the appellants delay interest from 08.06.2018 until the receipt of the Occupancy Certificate/Completion Certificate (OC/CC) or a valid offer of possession, whichever is later.

26
Stage 25Interim Order

Tribunal Order #0901126057582022-27-02-2025

The Tribunal allowed the appellant's amendment application to correct the respondent's address and delete a relief, and directed the issuance of fresh notice to the respondent for the next hearing on 24.03.2025.

27
Stage 26Interim Order

Tribunal Order #0901126057582022-04-03-2024

The Tribunal closed the respondent's opportunity to file objections and ordered the matter to proceed ex-parte due to their failure to appear or file responses. The case is scheduled for an ex-parte hearing on the application for condonation of delay on 08.04.2024.

28
Stage 27Interim Order

Tribunal Order #0901126057582022-29-03-2023

The Tribunal issued fresh notice to the respondent due to the applicant's failure to comply with previous service directions, imposing a cost of Rs. 1,000/- on the applicant for their lackadaisical attitude.

29
Stage 28Interim Order

Tribunal Order #0901126057582022-22-04-2025

The Tribunal allowed the appellant's application for condonation of delay due to technical issues with the portal and directed the conversion of the defective appeal into a regular appeal.

30
Stage 29Interim Order

Tribunal Order #0901126057582022-29-08-2024

The Tribunal heard arguments regarding the lack of Occupancy Certificate (OC) or Completion Certificate (CC) for the project and reserved judgment, noting that the matter is covered by a previous precedent.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appeals, modifying the previous order to grant the appellants delay interest from 08.06.2018 until the receipt of the Occupancy Certificate/Completion Certificate (OC/CC) or a valid offer of possession, whichever is later. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appeals, modifying the previous order to grant the appellants delay interest from 08.06.2018 until the receipt of the Occupancy Certificate/Completion Certificate (OC/CC) or a valid offer of possession, whichever is later.

Ruling Awarded To

Appellant

Interest Period

w.e.f. 08.06.2018 till the OC/CC of the project or valid offer of possession of the Unit, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Nirmit Srivastava

Official RERA Tribunal Orders (6)

FINAL_ORDEROrder ID: 0901126057582022-16-05-2025

The Tribunal allowed the appeals, modifying the previous order to grant the appellants delay interest from 08.06.2018 until the receipt of the Occupancy Certificate/Completion Certificate (OC/CC) or a valid offer of possession, whichever is later.

INTERIM_ORDEROrder ID: 0901126057582022-27-02-2025

The Tribunal allowed the appellant's amendment application to correct the respondent's address and delete a relief, and directed the issuance of fresh notice to the respondent for the next hearing on 24.03.2025.

INTERIM_ORDEROrder ID: 0901126057582022-04-03-2024

The Tribunal closed the respondent's opportunity to file objections and ordered the matter to proceed ex-parte due to their failure to appear or file responses. The case is scheduled for an ex-parte hearing on the application for condonation of delay on 08.04.2024.

INTERIM_ORDEROrder ID: 0901126057582022-29-03-2023

The Tribunal issued fresh notice to the respondent due to the applicant's failure to comply with previous service directions, imposing a cost of Rs. 1,000/- on the applicant for their lackadaisical attitude.

INTERIM_ORDEROrder ID: 0901126057582022-22-04-2025

The Tribunal allowed the appellant's application for condonation of delay due to technical issues with the portal and directed the conversion of the defective appeal into a regular appeal.

INTERIM_ORDEROrder ID: 0901126057582022-29-08-2024

The Tribunal heard arguments regarding the lack of Occupancy Certificate (OC) or Completion Certificate (CC) for the project and reserved judgment, noting that the matter is covered by a previous precedent.

TathyaGrid RERA Intelligence AI

Need to research all rulings for dhanya promoters private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →