Appellant / Complainant
Uppal Chadha Hi-Tech Developers Pvt. Ltd.
Respondent
Suman Vir Singh
uppal chadha hi-tech developers pvt. ltd.
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126056822022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Suman Vir Singh before up_rera.
Delay condonation
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act 2016 and upholding the Regulatory Authority's order to pay delay interest.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the hearing for the application for condonation of delay on 20.02.2025.
Delay condonation
Upon the joint request of the counsel for both parties, the tribunal has rescheduled the appeal to 29.01.2025 for consideration of the application for condonation of delay and hearing.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for orders/hearing on 17.01.2025.
Delay condonation
The Tribunal directed the appellant to file a fresh certificate from a Chartered Accountant to comply with the mandate of Section 43(5) of the Act, 2016, and scheduled the next hearing for 29.11.2024.
Delay condonation
The Tribunal granted the appellant seven days to rectify defects regarding non-compliance with Section 43(5) of the Act and scheduled the matter for orders on October 23, 2024.
Delay condonation
The Tribunal granted the appellant seven days to file a reply to the respondent's objections regarding compliance with Section 43(5) of the Act and scheduled the matter for orders on September 25, 2024.
Delay condonation
The Tribunal granted the respondent one week to file written objections regarding alleged non-compliance with Section 43(5) of the Act and objections to the applicant's supplementary affidavit, scheduling the matter for hearing on 28.08.2024.
Delay condonation
The Tribunal granted the respondent one week's time to file a supplementary objection to the application for condonation of delay and scheduled the matter for hearing on 25.07.2024.
Delay condonation
The Tribunal noted the absence of the respondent and the unavailability of the appellant's counsel, subsequently listing the defective appeal for consideration of a delay condonation application on 27.05.2024.
Delay condonation
The Tribunal noted that pleadings have been exchanged and scheduled the defective appeal for consideration of the application for condonation of delay on 25.04.2024.
Delay condonation
The Tribunal adjourned the proceedings due to the personal difficulty of the appellant's counsel and rescheduled the hearing for 08.04.2024 to consider the application for condonation of delay.
Delay condonation
The Tribunal granted the appellant one week to file a reply to the respondent's objections and adjourned the matter to 05.03.2024 for consideration of the condonation of delay application.
Delay condonation
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections, subject to the payment of Rs 5,000 in costs for library and legal welfare purposes.
Delay condonation
The Tribunal granted the appellant one week to file a reply to the respondent's objections regarding the application for condonation of delay and scheduled the next hearing for 29.09.2023.
Delay condonation
The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and scheduled the matter for hearing on 21.08.2023 regarding the application for condonation of delay.
Delay condonation
The Tribunal granted a 10-day extension for the respondent to file objections to the application for condonation of delay and the grounds of appeal, scheduling the next hearing for July 3, 2023.
Delay condonation
The Tribunal issued notice to the respondent following the appellant's compliance with Section 43(5) of the Act and set a returnable date for April 20, 2023.
Tribunal Order #0901126056822022-20-02-2025
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act 2016 and upholding the Regulatory Authority's order to pay delay interest.
Tribunal Order #0901126056822022-23-10-2024
The Tribunal directed the appellant to file a fresh certificate from a Chartered Accountant to comply with the mandate of Section 43(5) of the Act, 2016, and scheduled the next hearing for 29.11.2024.
Tribunal Order #0901126056822022-08-01-2024
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections, subject to the payment of Rs 5,000 in costs for library and legal welfare purposes.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act 2016 and upholding the Regulatory Authority's order to pay delay interest. Awarded in favor of Respondent. Awarded interest rate: MCLR+1 percent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act 2016 and upholding the Regulatory Authority's order to pay delay interest.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1 percent
Interest Period
from 18.07.2016 till date of offer of possession or date of O.C./C.C., whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Amit Yadav
- Bal Kishor Verma
Respondent Advocate(s)
- Respondent In-Person
- Prasoon Kumar Anjor
Official RERA Tribunal Orders (3)
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act 2016 and upholding the Regulatory Authority's order to pay delay interest.
The Tribunal directed the appellant to file a fresh certificate from a Chartered Accountant to comply with the mandate of Section 43(5) of the Act, 2016, and scheduled the next hearing for 29.11.2024.
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections, subject to the payment of Rs 5,000 in costs for library and legal welfare purposes.