up_reraStatus: Completed
CASE ID: 0901126056812022

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Aradhna Soni

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disputed Amount

25,15,001

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126056812022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Aradhna Soni before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 102/12/2024

for delivery of Judgment/Order

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations under Section 18 of the RERA Act for an ongoing project.

3
Stage 201/10/2024

Hearing

The Tribunal condoned the delay in filing the appeal, directed the registry to convert the defective appeal into a regular appeal, and reserved judgment after noting that the matter is covered by a previous precedent.

4
Stage 309/09/2024

Hearing

The Tribunal has granted a request by the counsels to list this defective appeal for consideration of the application for condonation of delay on 01.10.2024, noting that similar connected matters are scheduled for that date.

5
Stage 405/08/2024

Hearing

The Tribunal adjourned the matter and scheduled it for orders/hearing on 09.09.2024 due to the absence of the respondent.

6
Stage 505/07/2024

Hearing

No text available.

7
Stage 608/05/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and scheduled the defective appeal for orders/hearing on 05.07.2024.

8
Stage 705/04/2024

Hearing

The Tribunal noted that pleadings have been exchanged and listed the defective appeal for consideration of the application for condonation of delay on 08.05.2024.

9
Stage 801/03/2024

Hearing

The Tribunal has ordered the appeal to be listed for a hearing on 05.04.2024.

10
Stage 924/01/2024

Hearing

The Tribunal listed the defective appeal for consideration of a delay condonation application and subsequent hearing on March 1, 2024.

11
Stage 1026/10/2023

Hearing

No text available.

12
Stage 1114/09/2023

Delay condonation

The Tribunal adjourned the proceedings due to a call by the Bar Council of Uttar Pradesh for lawyers to abstain from judicial work and scheduled the matter for hearing on 26.10.2023.

13
Stage 1226/07/2023

Delay condonation

No text available.

14
Stage 1319/07/2023

Delay condonation

The Tribunal granted the appellant's counsel three days to file an affidavit of service and scheduled the defective appeal for orders on 26.07.2023.

15
Stage 1405/05/2023

Delay condonation

The Tribunal directed the issuance of fresh notice to the respondent via post and email due to insufficient address details and set a returnable date of 19.07.2023.

16
Stage 1520/04/2023

Delay condonation

The Tribunal granted a one-week extension for the appellant to file an affidavit of service and adjourned the matter to May 5, 2023.

17
Stage 1613/03/2023

Delay condonation

The Tribunal directs the Registry to verify the deposit of Rs. 14,08,381/- by the appellant and orders the issuance of notice to the respondent, subject to successful fund transfer, with a hearing scheduled for 20.04.2023.

18
Stage 17Final Ruling Order

Tribunal Order #0901126056812022-02-12-2024

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations under Section 18 of the RERA Act for an ongoing project.

19
Stage 18Interim Order

Tribunal Order #0901126056812022-13-03-2023

The Tribunal directs the Registry to verify the deposit of Rs. 14,08,381/- by the appellant and orders the issuance of notice to the respondent, subject to successful fund transfer, with a hearing scheduled for 20.04.2023.

20
Stage 19Interim Order

Tribunal Order #0901126056812022-01-10-2024

The Tribunal condoned the delay in filing the appeal, directed the registry to convert the defective appeal into a regular appeal, and reserved judgment after noting that the matter is covered by a previous precedent.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations under Section 18 of the RERA Act for an ongoing project. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations under Section 18 of the RERA Act for an ongoing project.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 18.07.2016 till the date of obtaining Occupancy/Completion certificate (OC/CC) or till the date of offer of possession whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Bal Kishor Verma
  • Amit Yadav

Respondent Advocate(s)

  • Vivek Singh
  • Shrey Uttam
  • Vatsala Singh

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126056812022-02-12-2024

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations under Section 18 of the RERA Act for an ongoing project.

INTERIM_ORDEROrder ID: 0901126056812022-13-03-2023

The Tribunal directs the Registry to verify the deposit of Rs. 14,08,381/- by the appellant and orders the issuance of notice to the respondent, subject to successful fund transfer, with a hearing scheduled for 20.04.2023.

INTERIM_ORDEROrder ID: 0901126056812022-01-10-2024

The Tribunal condoned the delay in filing the appeal, directed the registry to convert the defective appeal into a regular appeal, and reserved judgment after noting that the matter is covered by a previous precedent.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →