up_reraStatus: Completed
CASE ID: 0901126056762022

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Vikas Agarwal

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disputed Amount

38,54,715

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126056762022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Vikas Agarwal before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 102/12/2024

for delivery of Judgment/Order

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations for project delays under Section 18 of the RERA Act.

3
Stage 201/10/2024

Delay condonation

The Tribunal condoned the delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal. After hearing arguments, the Bench reserved judgment, noting that the matter is covered by a previous precedent.

4
Stage 311/09/2024

Delay condonation

The Tribunal granted a request by both counsels to club this appeal with similar matters already scheduled for 01.10.2024, directing the case to be listed on that date for orders or hearing.

5
Stage 408/08/2024

For Order

The Tribunal has adjourned the appeal to 11.09.2024 for orders following a joint request from the counsel for both parties.

6
Stage 509/07/2024

For Order

The Tribunal adjourned the appeal to 08.08.2024 following a request from counsel due to the respondent's representative being delayed by heavy rains and traffic.

7
Stage 610/05/2024

For Order

Due to the illness of the appellant's counsel, the court has scheduled a defective appeal for orders on 09.07.2024.

8
Stage 709/04/2024

For Order

The Tribunal adjourned the matter to 10.05.2024 for consideration of the application for condonation of delay and hearing, noting the absence of the appellant's counsel due to illness.

9
Stage 805/03/2024

For Order

The Tribunal granted the applicant one week's additional time to file a reply to the respondent's objection and scheduled the appeal for hearing on 09.04.2024.

10
Stage 925/01/2024

For Order

The Tribunal noted the absence of counsel due to illness and the respondent's non-appearance, subsequently adjourning the matter to 05.03.2024 for consideration of the condonation of delay application.

11
Stage 1005/01/2024

For Order

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections regarding the application for condonation of delay and grounds of appeal, scheduling the matter for orders on 25.01.2024.

12
Stage 1128/09/2023

For Order

No text available.

13
Stage 1217/08/2023

Notice

The Tribunal granted the respondent one week to file objections to the grounds of appeal and directed the applicant to respond to delay condonation objections within a week, scheduling the matter for 28.09.2023.

14
Stage 1321/06/2023

Delay condonation

The Tribunal accepted the appellant's deposit of Rs. 11,42,762/- under Section 43(5) of the RERA Act and issued notice to the respondent regarding the application for condonation of delay, scheduling the next hearing for 17.08.2023.

15
Stage 14Final Ruling Order

Tribunal Order #0901126056762022-02-12-2024

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations for project delays under Section 18 of the RERA Act.

16
Stage 15Interim Order

Tribunal Order #0901126056762022-21-06-2023

The Tribunal accepted the appellant's deposit of Rs. 11,42,762/- under Section 43(5) of the RERA Act and issued notice to the respondent regarding the application for condonation of delay, scheduling the next hearing for 17.08.2023.

17
Stage 16Interim Order

Tribunal Order #0901126056762022-01-10-2024

The Tribunal condoned the delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal. After hearing arguments, the Bench reserved judgment, noting that the matter is covered by a previous precedent.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations for project delays under Section 18 of the RERA Act. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations for project delays under Section 18 of the RERA Act.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 27.10.2014 till the date of obtaining Occupancy/Completion certificate (OC/CC) or till the date of offer of possession whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav
  • Bal Kishor Verma

Respondent Advocate(s)

  • Prasoon Kumar Anjor

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126056762022-02-12-2024

The Tribunal dismissed the appellant's appeal, ruling that farmer agitation does not constitute 'force majeure' to waive interest obligations for project delays under Section 18 of the RERA Act.

INTERIM_ORDEROrder ID: 0901126056762022-21-06-2023

The Tribunal accepted the appellant's deposit of Rs. 11,42,762/- under Section 43(5) of the RERA Act and issued notice to the respondent regarding the application for condonation of delay, scheduling the next hearing for 17.08.2023.

INTERIM_ORDEROrder ID: 0901126056762022-01-10-2024

The Tribunal condoned the delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal. After hearing arguments, the Bench reserved judgment, noting that the matter is covered by a previous precedent.

TathyaGrid RERA Intelligence AI