up_reraStatus: Completed
CASE ID: 0901126056722022

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Pooja Sharma

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

21 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126056722022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Pooja Sharma before up_rera.

2
Stage 120/03/2025

Hearing

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed Appeal-107/2023 due to a lack of plausible explanation for the 186-day delay.

3
Stage 221/11/2024

Delay condonation

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd. due to the non-appearance of the appellant (dismissed for want of prosecution).

4
Stage 317/10/2024

Delay condonation

The Tribunal adjourned the proceedings following a request from the appellant's counsel and scheduled the defective appeal for consideration of the application for condonation of delay on 21.11.2024.

5
Stage 411/09/2024

Hearing

The Tribunal granted the appellant a final 7-day extension to file a reply to the respondent's objections and scheduled the case for orders on 17.10.2024.

6
Stage 508/08/2024

For Order

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the appeal for hearing on 11.09.2024.

7
Stage 610/07/2024

For Order

The Tribunal granted the respondent seven days to file objections to the applicant's better affidavit and scheduled the matter for hearing on August 8, 2024.

8
Stage 713/05/2024

For Order

The Tribunal noted the absence of both parties and ordered the defective appeal to be listed for orders on 10.07.2024.

9
Stage 810/04/2024

Delay condonation

No text available.

10
Stage 906/03/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel on personal grounds and rescheduled the defective appeal for orders/hearing on 10.04.2024.

11
Stage 1001/02/2024

Delay condonation

The Tribunal granted the appellant one week to file an improved affidavit in support of their application for condonation of delay and scheduled the matter for hearing on 06.03.2024.

12
Stage 1102/11/2023

Delay condonation

No text available.

13
Stage 1220/09/2023

Delay condonation

The Tribunal granted the appellant one week to file an improved affidavit for condonation of delay and directed the respondent to file objections within a subsequent week.

14
Stage 1302/08/2023

Delay condonation

The proceedings were adjourned due to the unavailability of counsel for the appellant, and the matter is scheduled for hearing on 20.09.2023 regarding the application for condonation of delay.

15
Stage 1422/05/2023

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the defective appeal for hearing on 02.08.2023, directing parties to exchange pleadings in the interim.

16
Stage 1510/04/2023

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, scheduling the matter for hearing on 22.05.2023.

17
Stage 1627/02/2023

Delay condonation

The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and directed specific procedures for service of documents via email and speed-post.

18
Stage 17Final Ruling Order

Tribunal Order #0901126056722022-21-11-2024

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd. due to the non-appearance of the appellant (dismissed for want of prosecution).

19
Stage 18Final Ruling Order

Tribunal Order #0901126056722022-20-03-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed Appeal-107/2023 due to a lack of plausible explanation for the 186-day delay.

20
Stage 19Interim Order

Tribunal Order #0901126056722022-27-02-2023

The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and directed specific procedures for service of documents via email and speed-post.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd. due to the non-appearance of the appellant (dismissed for want of prosecution). The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed Appeal-107/2023 due to a lack of plausible explanation for the 186-day delay. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd. due to the non-appearance of the appellant (dismissed for want of prosecution). The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed Appeal-107/2023 due to a lack of plausible explanation for the 186-day delay.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav
  • Bal Kishor Verma

Respondent Advocate(s)

  • Abhinav Singh

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126056722022-21-11-2024

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd. due to the non-appearance of the appellant (dismissed for want of prosecution).

FINAL_ORDEROrder ID: 0901126056722022-20-03-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay and consequently dismissed Appeal-107/2023 due to a lack of plausible explanation for the 186-day delay.

INTERIM_ORDEROrder ID: 0901126056722022-27-02-2023

The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and directed specific procedures for service of documents via email and speed-post.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →