Appellant / Complainant
Uppal Chadha Hi-Tech Developers Pvt. Ltd.
Respondent
Renu Dahiya
uppal chadha hi-tech developers pvt. ltd.
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126056712022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Renu Dahiya before up_rera.
Re-Hearing
The Tribunal dismissed the appeal filed by the promoter, ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act, thereby upholding the requirement to pay interest for project delays.
Re-Hearing
The Tribunal has ordered the appeal to be listed for a subsequent hearing on 28.05.2025.
Delay condonation
The Tribunal condoned a 24-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal, subsequently reserving judgment.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel due to illness and scheduled the appeal for hearing on 16.09.2024.
Delay condonation
Upon the joint request of the counsels for both parties, the court has scheduled the defective appeal for a hearing on 20.08.2024.
Delay condonation
The Tribunal noted the request for adjournment from the appellant's counsel and scheduled the appeal for orders/hearing on 20.05.2024.
Delay condonation
The Tribunal noted that pleadings have been exchanged and scheduled the defective appeal for consideration of a delay condonation application on 19.04.2024.
Delay condonation
The Tribunal granted the appellant one week to file a reply and scheduled the matter for consideration of a condonation of delay application on 14.03.2024.
Delay condonation
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the matter for orders on 09.11.2023.
Delay condonation
The Tribunal granted the appellant one week's time to file a reply to the respondent's objections and scheduled the next hearing for 25.09.2023.
Delay condonation
The Tribunal acknowledges the appellant's deposit of Rs. 7,73,159/- in compliance with Section 43(5) of the Act and grants the respondent 10 days to file objections against the condonation of delay application and the appeal grounds.
Tribunal Order #0901126056712022-28-05-2025
The Tribunal dismissed the appeal filed by the promoter, ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act, thereby upholding the requirement to pay interest for project delays.
Tribunal Order #0901126056712022-17-04-2023
The Tribunal acknowledges the appellant's deposit of Rs. 7,73,159/- in compliance with Section 43(5) of the Act and grants the respondent 10 days to file objections against the condonation of delay application and the appeal grounds.
Tribunal Order #0901126056712022-23-10-2024
The Tribunal condoned a 24-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal, subsequently reserving judgment.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal filed by the promoter, ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act, thereby upholding the requirement to pay interest for project delays. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal filed by the promoter, ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act, thereby upholding the requirement to pay interest for project delays.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Surangama Sharma
Respondent Advocate(s)
- Harish Pandey
Official RERA Tribunal Orders (3)
The Tribunal dismissed the appeal filed by the promoter, ruling that 'farmers' agitation' does not constitute a 'force majeure' event under the RERA Act, thereby upholding the requirement to pay interest for project delays.
The Tribunal acknowledges the appellant's deposit of Rs. 7,73,159/- in compliance with Section 43(5) of the Act and grants the respondent 10 days to file objections against the condonation of delay application and the appeal grounds.
The Tribunal condoned a 24-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal, subsequently reserving judgment.
Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.