Appellant / Complainant
Gaursons Realtech Private Limited
Respondent
Shailendra Kumar, Pratibha
gaursons realtech private limited
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126053972023 by Gaursons Realtech Private Limited against Shailendra Kumar, Pratibha before up_rera.
Delay condonation
The appeal was dismissed as infructuous because the cause of action no longer survives, and any interim orders were vacated.
Delay condonation
Upon the joint request of the counsels for both parties, the tribunal has adjourned the appeal for hearing/orders to 04.07.2025.
Delay condonation
Upon the joint request of the counsel for both parties, the Tribunal has adjourned the appeal and scheduled the next hearing for May 7, 2025.
Delay condonation
The Tribunal granted a request for adjournment filed by the appellant's counsel and rescheduled the appeal for hearing on 16.04.2025.
Delay condonation
The Tribunal granted the appellant 10 days to file a rejoinder affidavit and scheduled the case for hearing/orders on 19.03.2025.
Delay condonation
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the hearing for the application for delay and the defective appeal on 24.02.2025.
Delay condonation
The Tribunal granted the appellant 10 days to file a rejoinder to the respondent's objections and scheduled the appeal for consideration of the condonation of delay application on 31.01.2025.
Delay condonation
The Tribunal granted the respondent a two-week extension to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent timeline set for the appellant to file a reply.
Delay condonation
The Tribunal adjourned the matter to 04.12.2024 for orders, noting that advocates were abstaining from judicial work due to a Bar Council resolution and no litigants appeared in person.
Delay condonation
The Tribunal granted the respondent 10 days to file objections against the application for condonation of delay and the grounds of appeal, with the matter scheduled for hearing on 04.11.2024.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with the matter scheduled for hearing on 24.09.2024.
Delay condonation
The Tribunal granted the appellant's application for waiver of the mandatory pre-deposit required under Section 43(5) of the Act and issued notice to the respondents for the next hearing.
Delay condonation
The order refers the parties to a previously passed order dated in Appeal No. D 132/2024 for the relevant directions.
Defect Removal
The Tribunal has scheduled the defective appeal for consideration regarding the application for condonation of delay on 16.05.2024.
Defect Removal
The Tribunal granted the appellant one week to seek instructions regarding the removal of defects in the respondent's unit and scheduled the matter for hearing on 03.05.2024.
Tribunal Order #0901126053972023-18-07-2024
The Tribunal granted the appellant's application for waiver of the mandatory pre-deposit required under Section 43(5) of the Act and issued notice to the respondents for the next hearing.
Tribunal Disposal & Final Award Ruling
Dismissed Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Samrat Vaish
- Mohit Yadav
- Sangya Negi
Respondent Advocate(s)
- Amit Yadav
Official RERA Tribunal Orders (1)
The Tribunal granted the appellant's application for waiver of the mandatory pre-deposit required under Section 43(5) of the Act and issued notice to the respondents for the next hearing.