up_reraStatus: Completed
CASE ID: 0901126053852022

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Snehlat Tomar

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126053852022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Snehlat Tomar before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 127/05/2024

Hearing

The Tribunal rejected the applications for condonation of delay in seven appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all appeals; consequently, the Tribunal directed that the pre-deposited amounts be transferred to U.P. RERA for distribution to the allottees during execution proceedings.

3
Stage 224/05/2024

Hearing

The Tribunal has listed the defective appeal for consideration of a condonation of delay application and hearing on 27.05.2024.

4
Stage 325/04/2024

Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the defective appeal for orders or hearing on 24.05.2024.

5
Stage 420/03/2024

Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the defective appeal for consideration of the application for condonation of delay on 25.04.2024.

6
Stage 516/02/2024

Hearing

The Tribunal granted the applicant one week to file a reply to the respondent's objections and scheduled the defective appeal for consideration of the condonation of delay application on 20.03.2024.

7
Stage 609/01/2024

Hearing

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for hearing on the application for condonation of delay on 16.02.2024.

8
Stage 703/10/2023

Hearing

No text available.

9
Stage 823/08/2023

Hearing

The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections and scheduled the next hearing for 03.10.2023, explicitly stating that no further adjournments will be granted.

10
Stage 905/07/2023

Hearing

The Tribunal granted a 10-day extension to the respondent for filing objections to the application for condonation of delay and grounds of appeal, scheduling the next hearing for August 23, 2023.

11
Stage 1026/04/2023

Defect Removal

The Tribunal verified the appellant's compliance with Section 43(5) regarding the mandatory deposit of Rs.15,18,721/- and issued notice to the respondent, scheduling the matter for hearing on the application for condonation of delay on 05.07.2023.

12
Stage 1117/04/2023

Defect Removal

The Tribunal noted the appellant's deposit of Rs. 15,18,721/- for compliance with Section 43(5) and adjourned the defective appeal to 26.04.2023 upon request.

13
Stage 12Final Ruling Order

Tribunal Order #0901126053852022-27-05-2024

The Tribunal rejected the applications for condonation of delay in seven appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all appeals; consequently, the Tribunal directed that the pre-deposited amounts be transferred to U.P. RERA for distribution to the allottees during execution proceedings.

14
Stage 13Interim Order

Tribunal Order #0901126053852022-26-04-2023

The Tribunal verified the appellant's compliance with Section 43(5) regarding the mandatory deposit of Rs.15,18,721/- and issued notice to the respondent, scheduling the matter for hearing on the application for condonation of delay on 05.07.2023.

15
Stage 14Interim Order

Tribunal Order #0901126053852022-23-08-2023

The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections and scheduled the next hearing for 03.10.2023, explicitly stating that no further adjournments will be granted.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the applications for condonation of delay in seven appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all appeals; consequently, the Tribunal directed that the pre-deposited amounts be transferred to U.P. RERA for distribution to the allottees during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the applications for condonation of delay in seven appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all appeals; consequently, the Tribunal directed that the pre-deposited amounts be transferred to U.P. RERA for distribution to the allottees during execution proceedings.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 09.10.2016 to date of getting OC/CC or to the date when possession of plot was offered whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Bal Kishor Verma
  • Amit Yadav

Respondent Advocate(s)

  • Prasoon Kumar Anjor

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126053852022-27-05-2024

The Tribunal rejected the applications for condonation of delay in seven appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all appeals; consequently, the Tribunal directed that the pre-deposited amounts be transferred to U.P. RERA for distribution to the allottees during execution proceedings.

INTERIM_ORDEROrder ID: 0901126053852022-26-04-2023

The Tribunal verified the appellant's compliance with Section 43(5) regarding the mandatory deposit of Rs.15,18,721/- and issued notice to the respondent, scheduling the matter for hearing on the application for condonation of delay on 05.07.2023.

INTERIM_ORDEROrder ID: 0901126053852022-23-08-2023

The Tribunal closed the appellant's opportunity to file a reply to the respondent's objections and scheduled the next hearing for 03.10.2023, explicitly stating that no further adjournments will be granted.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →