Appellant / Complainant
Vaibhav
Respondent
Agrani Homes Pvt Ltd
agrani homes pvt ltd
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126053572021 by Vaibhav against Agrani Homes Pvt Ltd before up_rera.
Defect Removal
The Tribunal dismissed the appeal and the underlying RERA complaint because the respondent's project was not registered under Section 3 of the Act 2016, rendering the proceedings non-maintainable per Supreme Court precedent.
Further Order
The Tribunal noted that the respondent's project is unregistered and directed the appellant to explain the maintainability of the complaint and appeal under the Act.
Further Order
The Tribunal granted a request for adjournment made by the appellant's counsel and rescheduled the hearing to 11.01.2022.
Defect Removal
The Tribunal granted a short adjournment to allow the respondent's counsel to file a Vakalatnama and noted that the parties are likely to settle the matter.
Defect Removal
The Tribunal noted that all registry defects were removed and adjourned the matter to 06.12.2021, directing the respondent to file their Vakalatnama and required documents by that date.
Tribunal Order #0901126053572021-21-02-2022
The Tribunal noted that the respondent's project is unregistered and directed the appellant to explain the maintainability of the complaint and appeal under the Act.
Tribunal Order #0901126053572021-03-03-2022
The Tribunal dismissed the appeal and the underlying RERA complaint because the respondent's project was not registered under Section 3 of the Act 2016, rendering the proceedings non-maintainable per Supreme Court precedent.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal and the underlying RERA complaint because the respondent's project was not registered under Section 3 of the Act 2016, rendering the proceedings non-maintainable per Supreme Court precedent. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal and the underlying RERA complaint because the respondent's project was not registered under Section 3 of the Act 2016, rendering the proceedings non-maintainable per Supreme Court precedent.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Rajesh Kumar Misra
Official RERA Tribunal Orders (2)
The Tribunal noted that the respondent's project is unregistered and directed the appellant to explain the maintainability of the complaint and appeal under the Act.
The Tribunal dismissed the appeal and the underlying RERA complaint because the respondent's project was not registered under Section 3 of the Act 2016, rendering the proceedings non-maintainable per Supreme Court precedent.
Need to research all rulings for agrani homes pvt ltd?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.