Appellant / Complainant
Sanjeev Aggarwal
Respondent
Greater Noida Industrial Development Authority
₹12,31,351
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126053562022 by Sanjeev Aggarwal against Greater Noida Industrial Development Authority before up_rera.
Hearing
The Tribunal ruled that the allottee is entitled to delay interest until the date of issuance of the completion certificate (29.05.2023), rejecting the promoter's attempt to use a retrospective completion date to avoid liability under Section 18(1) of the Act.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to him being out of station and scheduled the case for orders on April 1, 2025.
Hearing
The Tribunal directed the respondent to upload documents regarding the OC/CC application and NOCs, while requiring an explanation for the discrepancy between the project's alleged completion date in 2018 and the issuance of the completion certificate in 2023.
Hearing
The Tribunal allowed the application for condonation of delay, citing COVID-19 pandemic extensions and settlement attempts as sufficient cause, and directed the Registry to convert the defective appeal into a regular appeal.
Hearing
The appeal has been adjourned at the request of the appellant's counsel and is scheduled for a hearing on 17.01.2025.
Hearing
The Tribunal has granted a request by the appellant's counsel to list the defective appeal for orders or hearing on 28.10.2024.
Hearing
The Tribunal granted the appellant one week to file a better affidavit for condonation of delay and ordered that this appeal be listed alongside Appeal No. 875/2021 on 20.09.2024.
Hearing
The Tribunal granted a request to list this defective appeal for orders or hearing on July 31, 2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to his absence from the station and rescheduled the hearing for July 2, 2024.
Hearing
The Tribunal granted an adjournment request from the respondent's counsel due to personal difficulty and scheduled the defective appeal for hearing on May 8, 2024, alongside a related appeal.
Hearing
The Tribunal granted a request for adjournment and scheduled the defective appeal, along with the application for condonation of delay, for hearing on 06.05.2024.
Hearing
The Tribunal noted the absence of the appellant's counsel and scheduled the defective appeal for consideration of the condonation of delay application on 04.04.2024.
Hearing
The Tribunal noted that counsel for the respondent filed an OC/CC on 03.07.2023 and scheduled the appeal for a hearing on 01.03.2024.
Hearing
The Tribunal granted a request from the respondent's counsel to adjourn today's hearing and rescheduled the matter for 24.07.2023.
Hearing
The court granted a joint request from both parties to reschedule the hearing for the defective appeal and the application for condonation of delay to 18.07.2023.
Delay condonation
The Tribunal adjourned the matter to 05.07.2023 to consider the application for condonation of delay and hear arguments regarding the respondent's opportunity to file objections.
Delay condonation
The Tribunal granted an adjournment request from the respondent's counsel due to him being out of station and rescheduled the defective appeal for hearing on 04.07.2023.
Delay condonation
The Tribunal closed the respondent's opportunity to file objections to the application for condonation of delay and the grounds of appeal due to failure to comply with previous orders. The matter is listed for April 25, 2023, for consideration of the condonation application.
Delay condonation
The Tribunal granted the respondent a final 10-day extension to file objections to the application for condonation of delay and the grounds of appeal, with the case scheduled for hearing on 08.02.2023.
Delay condonation
The Tribunal issued a fresh notice to the respondent regarding the application for condonation of delay and directed the applicant to serve the notice via speed-post and email, with the matter listed for hearing on 04.01.2023.
Delay condonation
The Tribunal issued notice to the respondent regarding the appeal and the application for condonation of delay, scheduling the matter for hearing on 03.11.2022.
Tribunal Order #0901126053562022-17-03-2023
The Tribunal closed the respondent's opportunity to file objections to the application for condonation of delay and the grounds of appeal due to failure to comply with previous orders. The matter is listed for April 25, 2023, for consideration of the condonation application.
Tribunal Order #0901126053562022-01-04-2025
The Tribunal ruled that the allottee is entitled to delay interest until the date of issuance of the completion certificate (29.05.2023), rejecting the promoter's attempt to use a retrospective completion date to avoid liability under Section 18(1) of the Act.
Tribunal Order #0901126053562022-17-01-2025
The Tribunal allowed the application for condonation of delay, citing COVID-19 pandemic extensions and settlement attempts as sufficient cause, and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Order #0901126053562022-12-02-2025
The Tribunal directed the respondent to upload documents regarding the OC/CC application and NOCs, while requiring an explanation for the discrepancy between the project's alleged completion date in 2018 and the issuance of the completion certificate in 2023.
Tribunal Disposal & Final Award Ruling
The Tribunal ruled that the allottee is entitled to delay interest until the date of issuance of the completion certificate (29.05.2023), rejecting the promoter's attempt to use a retrospective completion date to avoid liability under Section 18(1) of the Act. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal ruled that the allottee is entitled to delay interest until the date of issuance of the completion certificate (29.05.2023), rejecting the promoter's attempt to use a retrospective completion date to avoid liability under Section 18(1) of the Act.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1%
Interest Period
w.e.f 19.09.2017 to 20.05.2023
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Nirmit Srivastav
Respondent Advocate(s)
- Ajai Kumar Gupta
- Rishindra Vikram Singh
Official RERA Tribunal Orders (4)
The Tribunal closed the respondent's opportunity to file objections to the application for condonation of delay and the grounds of appeal due to failure to comply with previous orders. The matter is listed for April 25, 2023, for consideration of the condonation application.
The Tribunal ruled that the allottee is entitled to delay interest until the date of issuance of the completion certificate (29.05.2023), rejecting the promoter's attempt to use a retrospective completion date to avoid liability under Section 18(1) of the Act.
The Tribunal allowed the application for condonation of delay, citing COVID-19 pandemic extensions and settlement attempts as sufficient cause, and directed the Registry to convert the defective appeal into a regular appeal.
The Tribunal directed the respondent to upload documents regarding the OC/CC application and NOCs, while requiring an explanation for the discrepancy between the project's alleged completion date in 2018 and the issuance of the completion certificate in 2023.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.