up_reraStatus: Completed
CASE ID: 0901126053282021

Appellant / Complainant

Eshan Singh

VS

Respondent

Ansal Properties & Infrastructure Limited

Developer Firm

ansal properties & infrastructure limited

Disputed Amount

25,90,811

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay Compensation / InterestMaintenance & Utility DisputesJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

26 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126053282021 by Eshan Singh against Ansal Properties & Infrastructure Limited before up_rera.

Delay Compensation / InterestMaintenance & Utility DisputesJurisdiction & Maintainability
2
Stage 103/01/2025

Hearing

The Tribunal dismissed the appeal, ruling that a project phase for which a partial Completion Certificate has been issued does not fall under the definition of an 'ongoing project' under the Real Estate (Regulation and Development) Act, 2016.

3
Stage 211/11/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for January 3, 2025.

4
Stage 330/09/2024

Further Hearing

The Tribunal has heard the counsel for both parties and ordered the appeal to be listed for hearing on 11.11.2024.

5
Stage 424/09/2024

Hearing

The Tribunal granted the respondent one week to submit judgments regarding partial OC/CC and ongoing projects, adjourning the hearing to 30.09.2024.

6
Stage 518/09/2024

Hearing

The Tribunal has adjourned the matter to 24.09.2024 for orders, following a request from the respondent's counsel.

7
Stage 627/08/2024

For Order

The Tribunal granted the respondent's request for time to prepare their brief and scheduled the appeal for a final hearing on 18.09.2024.

8
Stage 724/07/2024

For Order

The Tribunal granted the appellant one week's time to file a supplementary rejoinder affidavit and scheduled the next hearing for August 27, 2024.

9
Stage 810/07/2024

For Order

The Tribunal granted a request from the respondent's counsel to adjourn the matter and scheduled the appeal for orders/hearing on 24.07.2024.

10
Stage 913/05/2024

For Order

The Tribunal noted that the counsel for the appellant was out of station and adjourned the matter to 10.07.2024 for orders/hearing.

11
Stage 1010/04/2024

Hearing

No text available.

12
Stage 1111/03/2024

Hearing

The Tribunal granted the appellant's counsel 24 hours to file a reply to the supplementary rejoinder affidavit and scheduled the appeal for orders on April 10, 2024.

13
Stage 1201/02/2024

Hearing

The Tribunal granted the appellant one week's time to file a reply to the respondent's objections and scheduled the appeal for hearing on 11.03.2024.

14
Stage 1302/11/2023

Hearing

No text available.

15
Stage 1420/09/2023

Hearing

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for October 11, 2023.

16
Stage 1511/08/2022

Hearing

The appeal was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.

17
Stage 1620/07/2022

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and directed both parties to prepare for a final hearing on the next scheduled date of 11.08.2022.

18
Stage 1713/07/2022

Further Order

The Tribunal directed both parties to file a list of dates and events within three days and scheduled the appeal for hearing on 20.07.2022.

19
Stage 1804/05/2022

Further Order

The Tribunal directed the parties to exchange written arguments along with relied-upon judgments and scheduled the appeal for hearing on 13.07.2022.

20
Stage 1925/03/2022

For Order

The Tribunal directed the appellant to file a replication/rejoinder to the respondent's reply and scheduled the next hearing for May 4, 2022.

21
Stage 2003/03/2022

Delay condonation

The Tribunal granted the respondent one week to file objections to the grounds of appeal and directed the parties to exchange replies and upload documents on the e-portal before the next hearing on 25.03.2022.

22
Stage 2123/12/2021

Delay condonation

The Tribunal condoned the delay in filing the appeal by applying the Supreme Court's COVID-19 limitation guidelines and directed the Registry to register the defective appeal as a regular appeal.

23
Stage 2226/11/2021

Delay condonation

The Tribunal noted that the appeal was filed out of time and ordered notice to be issued to the respondent via registered post and email, scheduling the matter for December 23, 2021, to address the limitation application.

24
Stage 23Final Ruling Order

Tribunal Order #0901126053282021-03-01-2025

The Tribunal dismissed the appeal, ruling that a project phase for which a partial Completion Certificate has been issued does not fall under the definition of an 'ongoing project' under the Real Estate (Regulation and Development) Act, 2016.

25
Stage 24Interim Order

Tribunal Order #0901126053282021-23-12-2021

The Tribunal condoned the delay in filing the appeal by applying the Supreme Court's COVID-19 limitation guidelines and directed the Registry to register the defective appeal as a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal, ruling that a project phase for which a partial Completion Certificate has been issued does not fall under the definition of an 'ongoing project' under the Real Estate (Regulation and Development) Act, 2016. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal, ruling that a project phase for which a partial Completion Certificate has been issued does not fall under the definition of an 'ongoing project' under the Real Estate (Regulation and Development) Act, 2016.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(d)Section 19(6)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Praveen Tripathi

Respondent Advocate(s)

  • Saurabh Misra
  • Krishna Kumar Singh
  • Gautam Johri

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126053282021-03-01-2025

The Tribunal dismissed the appeal, ruling that a project phase for which a partial Completion Certificate has been issued does not fall under the definition of an 'ongoing project' under the Real Estate (Regulation and Development) Act, 2016.

INTERIM_ORDEROrder ID: 0901126053282021-23-12-2021

The Tribunal condoned the delay in filing the appeal by applying the Supreme Court's COVID-19 limitation guidelines and directed the Registry to register the defective appeal as a regular appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for ansal properties & infrastructure limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →