Appellant / Complainant
Eshan Singh
Respondent
Ansal Properties & Infrastructure Limited
ansal properties & infrastructure limited
₹25,90,811
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126053282021 by Eshan Singh against Ansal Properties & Infrastructure Limited before up_rera.
Hearing
The Tribunal dismissed the appeal, ruling that a project phase for which a partial Completion Certificate has been issued does not fall under the definition of an 'ongoing project' under the Real Estate (Regulation and Development) Act, 2016.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for January 3, 2025.
Further Hearing
The Tribunal has heard the counsel for both parties and ordered the appeal to be listed for hearing on 11.11.2024.
Hearing
The Tribunal granted the respondent one week to submit judgments regarding partial OC/CC and ongoing projects, adjourning the hearing to 30.09.2024.
Hearing
The Tribunal has adjourned the matter to 24.09.2024 for orders, following a request from the respondent's counsel.
For Order
The Tribunal granted the respondent's request for time to prepare their brief and scheduled the appeal for a final hearing on 18.09.2024.
For Order
The Tribunal granted the appellant one week's time to file a supplementary rejoinder affidavit and scheduled the next hearing for August 27, 2024.
For Order
The Tribunal granted a request from the respondent's counsel to adjourn the matter and scheduled the appeal for orders/hearing on 24.07.2024.
For Order
The Tribunal noted that the counsel for the appellant was out of station and adjourned the matter to 10.07.2024 for orders/hearing.
Hearing
The Tribunal granted the appellant's counsel 24 hours to file a reply to the supplementary rejoinder affidavit and scheduled the appeal for orders on April 10, 2024.
Hearing
The Tribunal granted the appellant one week's time to file a reply to the respondent's objections and scheduled the appeal for hearing on 11.03.2024.
Hearing
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for October 11, 2023.
Hearing
The appeal was dismissed for want of prosecution due to the non-appearance of the appellant's counsel.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and directed both parties to prepare for a final hearing on the next scheduled date of 11.08.2022.
Further Order
The Tribunal directed both parties to file a list of dates and events within three days and scheduled the appeal for hearing on 20.07.2022.
Further Order
The Tribunal directed the parties to exchange written arguments along with relied-upon judgments and scheduled the appeal for hearing on 13.07.2022.
For Order
The Tribunal directed the appellant to file a replication/rejoinder to the respondent's reply and scheduled the next hearing for May 4, 2022.
Delay condonation
The Tribunal granted the respondent one week to file objections to the grounds of appeal and directed the parties to exchange replies and upload documents on the e-portal before the next hearing on 25.03.2022.
Delay condonation
The Tribunal condoned the delay in filing the appeal by applying the Supreme Court's COVID-19 limitation guidelines and directed the Registry to register the defective appeal as a regular appeal.
Delay condonation
The Tribunal noted that the appeal was filed out of time and ordered notice to be issued to the respondent via registered post and email, scheduling the matter for December 23, 2021, to address the limitation application.
Tribunal Order #0901126053282021-03-01-2025
The Tribunal dismissed the appeal, ruling that a project phase for which a partial Completion Certificate has been issued does not fall under the definition of an 'ongoing project' under the Real Estate (Regulation and Development) Act, 2016.
Tribunal Order #0901126053282021-23-12-2021
The Tribunal condoned the delay in filing the appeal by applying the Supreme Court's COVID-19 limitation guidelines and directed the Registry to register the defective appeal as a regular appeal.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal, ruling that a project phase for which a partial Completion Certificate has been issued does not fall under the definition of an 'ongoing project' under the Real Estate (Regulation and Development) Act, 2016. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal, ruling that a project phase for which a partial Completion Certificate has been issued does not fall under the definition of an 'ongoing project' under the Real Estate (Regulation and Development) Act, 2016.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Praveen Tripathi
Respondent Advocate(s)
- Saurabh Misra
- Krishna Kumar Singh
- Gautam Johri
Official RERA Tribunal Orders (2)
The Tribunal dismissed the appeal, ruling that a project phase for which a partial Completion Certificate has been issued does not fall under the definition of an 'ongoing project' under the Real Estate (Regulation and Development) Act, 2016.
The Tribunal condoned the delay in filing the appeal by applying the Supreme Court's COVID-19 limitation guidelines and directed the Registry to register the defective appeal as a regular appeal.