up_reraStatus: Active
CASE ID: 0901126052672023

Appellant / Complainant

Sulalita Sharma

VS

Respondent

Assotech Realty Private Limited, Assotech Realty Pvt Ltd

Developer Firm

assotech realty private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

13 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126052672023 by Sulalita Sharma against Assotech Realty Private Limited, Assotech Realty Pvt Ltd before up_rera.

2
Stage 118/09/2024

Delay condonation

The U.P. Real Estate Appellate Tribunal allowed the appellant's application to withdraw the appeal, resulting in the dismissal of the case as withdrawn.

3
Stage 230/08/2024

Delay condonation

The Tribunal noted the appellant's failure to deposit a previously imposed cost of Rs. 5,000 and scheduled the matter for hearing on 18.09.2024, explicitly stating that no further adjournments will be granted.

4
Stage 308/08/2024

Delay condonation

The Tribunal closed the applicant's opportunity to file a reply due to repeated failure to do so and noted that the previously imposed cost of Rs. 5,000/- remains unpaid.

5
Stage 422/07/2024

Delay condonation

The Tribunal granted a 7-day extension to the appellant to file a reply to the respondent's objections due to counsel's illness and rescheduled the matter for August 8, 2024.

6
Stage 522/05/2024

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objection and scheduled the matter for hearing on July 22, 2024.

7
Stage 622/04/2024

Delay condonation

The Tribunal imposed a cost of Rs. 5,000 on the applicant for failing to comply with previous directions regarding the service of records and directed them to provide soft copies of all records to the respondent within one week.

8
Stage 714/03/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and directed the applicant to provide soft copies of the case records to the respondent to facilitate filing objections to the condonation of delay application.

9
Stage 820/02/2024

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to absence and issued notice to the respondent regarding the appeal, scheduling the next hearing for 14.03.2024.

10
Stage 9Interim Order

Tribunal Order #0901126052672023-08-08-2024

The Tribunal closed the applicant's opportunity to file a reply due to repeated failure to do so and noted that the previously imposed cost of Rs. 5,000/- remains unpaid.

11
Stage 10Interim Order

Tribunal Order #0901126052672023-30-08-2024

The Tribunal noted the appellant's failure to deposit a previously imposed cost of Rs. 5,000 and scheduled the matter for hearing on 18.09.2024, explicitly stating that no further adjournments will be granted.

12
Stage 11Interim Order

Tribunal Order #0901126052672023-22-04-2024

The Tribunal imposed a cost of Rs. 5,000 on the applicant for failing to comply with previous directions regarding the service of records and directed them to provide soft copies of all records to the respondent within one week.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Active

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rishabh Singh
  • Kanish Bangia

Respondent Advocate(s)

  • Siddharth Nandwani

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126052672023-08-08-2024

The Tribunal closed the applicant's opportunity to file a reply due to repeated failure to do so and noted that the previously imposed cost of Rs. 5,000/- remains unpaid.

INTERIM_ORDEROrder ID: 0901126052672023-30-08-2024

The Tribunal noted the appellant's failure to deposit a previously imposed cost of Rs. 5,000 and scheduled the matter for hearing on 18.09.2024, explicitly stating that no further adjournments will be granted.

INTERIM_ORDEROrder ID: 0901126052672023-22-04-2024

The Tribunal imposed a cost of Rs. 5,000 on the applicant for failing to comply with previous directions regarding the service of records and directed them to provide soft copies of all records to the respondent within one week.

TathyaGrid RERA Intelligence AI

Need to research all rulings for assotech realty private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →