CASE ID: 0901126051812023

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Harvir Singh, Vikas Yadav

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

13 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126051812023 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Harvir Singh, Vikas Yadav before up_rera.

2
Stage 102/12/2024

for delivery of Judgment/Order

The Tribunal rejected the applicant's application for condonation of delay and consequently dismissed the appeal, finding that the 240-day delay in instituting the appeal was willful and lacked satisfactory explanation.

3
Stage 201/10/2024

Delay condonation

The Tribunal heard arguments regarding the application for condonation of delay and reserved its judgment on the matter.

4
Stage 302/09/2024

Delay condonation

The Tribunal granted the appellant a final three-day extension to file a reply to the respondent's objections and scheduled the matter for hearing on 01.10.2024.

5
Stage 431/07/2024

Delay condonation

No text available.

6
Stage 501/07/2024

Delay condonation

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and directed the respondent's counsel to register on the portal for cause list visibility. The matter is scheduled for orders on 31.07.2024.

7
Stage 601/05/2024

Delay condonation

No text available.

8
Stage 729/03/2024

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for hearing on May 1, 2024, regarding the application for condonation of delay.

9
Stage 823/02/2024

Delay condonation

The Tribunal deemed the service of notice to the respondent sufficient and granted a 10-day extension for filing objections, scheduling the next hearing for March 29, 2024.

10
Stage 916/01/2024

Delay condonation

The Tribunal provisionally accepted the appellant's compliance with Section 43(5) of the Act following a deposit of Rs. 15,02,886 and issued notice to the respondents to seek objections regarding the condonation of delay and the grounds of appeal.

11
Stage 10Final Ruling Order

Tribunal Order #0901126051812023-02-12-2024

The Tribunal rejected the applicant's application for condonation of delay and consequently dismissed the appeal, finding that the 240-day delay in instituting the appeal was willful and lacked satisfactory explanation.

12
Stage 11Interim Order

Tribunal Order #0901126051812023-16-01-2024

The Tribunal provisionally accepted the appellant's compliance with Section 43(5) of the Act following a deposit of Rs. 15,02,886 and issued notice to the respondents to seek objections regarding the condonation of delay and the grounds of appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the applicant's application for condonation of delay and consequently dismissed the appeal, finding that the 240-day delay in instituting the appeal was willful and lacked satisfactory explanation. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the applicant's application for condonation of delay and consequently dismissed the appeal, finding that the 240-day delay in instituting the appeal was willful and lacked satisfactory explanation.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Naveen Kumar Tiwari
  • Sunamika

Respondent Advocate(s)

  • Prasoon Kumar Anjor

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126051812023-02-12-2024

The Tribunal rejected the applicant's application for condonation of delay and consequently dismissed the appeal, finding that the 240-day delay in instituting the appeal was willful and lacked satisfactory explanation.

INTERIM_ORDEROrder ID: 0901126051812023-16-01-2024

The Tribunal provisionally accepted the appellant's compliance with Section 43(5) of the Act following a deposit of Rs. 15,02,886 and issued notice to the respondents to seek objections regarding the condonation of delay and the grounds of appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →