up_reraStatus: Completed
CASE ID: 0901126050552021

Appellant / Complainant

Yamuna Expressway Industrial Development Authority

VS

Respondent

Vijay Kumar Grover

Disputed Amount

9,43,172

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

54 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126050552021 by Yamuna Expressway Industrial Development Authority against Vijay Kumar Grover before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 107/01/2026

Hearing

The Tribunal dismissed the appellant's appeal, ruling that farmer's agitation does not qualify as a force majeure event to waive interest for project delays, and directed the respondent to take possession of the unit within four weeks of a demand notice.

3
Stage 208/12/2025

Hearing

The Tribunal scheduled the appeal for its next hearing on January 7, 2026, and explicitly noted that no further adjournments will be granted.

4
Stage 306/11/2025

Hearing

The Tribunal granted the appellant time to seek instructions regarding possession and conveyance deed execution and adjourned the appeal to 08.12.2025.

5
Stage 414/10/2025

Hearing

The Tribunal adjourned the appeal to 06.11.2025 and directed the Registry to notify the respondent to appear virtually at 11:30 a.m. on that date.

6
Stage 516/09/2025

Hearing

The appeal has been restored to its original number and is scheduled for the next hearing on 14.10.2025.

7
Stage 608/05/2025

Hearing

The appeal filed by Yamuna Expressway Industrial Development Authority was dismissed due to the appellant's failure to appear for the hearing.

8
Stage 716/04/2025

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and directed the appellant to upload the required affidavit regarding OC/CC, listing the matter for hearing on 08.05.2025.

9
Stage 820/03/2025

Hearing

The Tribunal has scheduled the case for orders on April 16, 2025.

10
Stage 927/02/2025

Hearing

The Tribunal granted the appellant 10 days to upload an affidavit regarding the issuance of OC/CC and scheduled the next hearing for March 20, 2025.

11
Stage 1004/02/2025

Hearing

The Tribunal granted the appellant further time to produce the OC/CC for the project, subject to a cost of Rs. 5,000 to be paid by the appellant for the library of legal representatives.

12
Stage 1106/01/2025

Hearing

The Tribunal granted the appellant 15 days to file a reply to a query raised in a previous order and scheduled the next hearing for February 4, 2025.

13
Stage 1210/12/2024

Hearing

The Tribunal granted an adjournment due to the illness of the appellant's counsel and rescheduled the hearing for January 6, 2025.

14
Stage 1318/11/2024

Hearing

The Tribunal granted a request to reschedule the hearing of Appeal-997/2021 to 10.12.2024, noting that no further adjournments will be permitted.

15
Stage 1403/10/2024

Hearing

The Tribunal has granted a request by the appellant's counsel to reschedule the hearing of the appeal to 18.11.2024.

16
Stage 1503/09/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the matter for a hearing on 03.10.2024.

17
Stage 1601/08/2024

Hearing

No text available.

18
Stage 1730/05/2024

Hearing

The Tribunal granted a request from the appellant's counsel to reschedule the hearing of the appeal to 01.08.2024.

19
Stage 1829/04/2024

Hearing

No text available.

20
Stage 1922/03/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to a personal bereavement and rescheduled the matter for hearing on 29.04.2024.

21
Stage 2020/02/2024

Hearing

The Tribunal granted the appellant's counsel additional time to produce relevant provisions regarding YEIDA's exemption from seeking OC/CC and adjourned the hearing to 22.03.2024.

22
Stage 2119/01/2024

Hearing

The Tribunal granted an adjournment due to the appellant's counsel's illness and rescheduled the hearing for 20.02.2024, noting that no further adjournments will be permitted.

23
Stage 2217/10/2023

Hearing

No text available.

24
Stage 2311/09/2023

Hearing

The Tribunal adjourned the proceedings and rescheduled the hearing for 17.10.2023 due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh.

25
Stage 2402/08/2023

Hearing

The Tribunal directed the appellant to place on record the Occupancy Certificate (OC/CC) and any offer of possession provided to the respondent to determine compliance with previous directions. The appeal, which challenges the interest rate calculation for delayed possession, is listed for further hearing on 11.09.2023.

26
Stage 2522/05/2023

Hearing

The Tribunal rescheduled the appeal for hearing on 02.08.2023 and noted the respondent's absence, stipulating that no further adjournments will be granted on the next date.

27
Stage 2627/04/2023

Hearing

The Tribunal directed the appellant to place the status of the Occupancy Certificate (OC) or Completion Certificate (CC) on record by the next hearing date of 22.05.2023.

28
Stage 2720/03/2023

Hearing

No text available.

29
Stage 2809/02/2023

Hearing

No text available.

30
Stage 2905/01/2023

Hearing

No text available.

31
Stage 3005/12/2022

Hearing

No text available.

32
Stage 3101/12/2022

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the matter for hearing on 05.12.2022.

33
Stage 3202/11/2022

Hearing

The Tribunal has scheduled the case for a hearing on December 1, 2022.

34
Stage 3319/10/2022

Hearing

The Tribunal adjourned the proceedings due to the respondent's inability to join the virtual hearing because of poor connectivity, rescheduling the matter for 02.11.2022.

35
Stage 3421/09/2022

Hearing

The Tribunal directed the appellant to approach the respondent with a formal offer to settle the dispute amicably regarding possession and the execution of the conveyance deed before the next hearing date.

36
Stage 3512/09/2022

Hearing

The Tribunal adjourned the proceedings to 21.09.2022 and directed that the order be sent to the respondent via email, noting that the matter will proceed based on available records if the respondent fails to appear.

37
Stage 3622/08/2022

Hearing

The Tribunal scheduled the appeal for a hearing on 12.09.2022 and directed that the matter may proceed ex parte if the respondent fails to appear.

38
Stage 3701/08/2022

Hearing

The Tribunal noted the absence of the appellant and scheduled the appeal for a hearing on 22.08.2022, noting that pleadings have been exchanged.

39
Stage 3812/07/2022

Delay condonation

The Tribunal condoned the delay in filing the appeal, citing the Supreme Court's exclusion of the COVID-19 period for limitation purposes, and directed the Registry to convert the defective appeal into a regular appeal.

40
Stage 3923/05/2022

Delay condonation

The Tribunal adjourned the matter to 12.07.2022 for consideration of a condonation of delay application and directed the parties to exchange pleadings in the interim.

41
Stage 4009/05/2022

Delay condonation

The Tribunal granted the appellant three days to file a reply to the respondent's objections and scheduled the matter for May 23, 2022, to consider the application for condonation of delay.

42
Stage 4120/04/2022

Delay condonation

The Tribunal granted the applicant 10 days to file a reply to the respondent's objections and scheduled the defective appeal for hearing on May 9, 2022.

43
Stage 4230/03/2022

Delay condonation

The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and scheduled the case for hearing on 20.04.2022 regarding the application for condonation of delay.

44
Stage 4307/03/2022

Delay condonation

The Tribunal issued notice to the respondent regarding the appeal and directed the applicant to serve the notice and relevant documents via speed-post and email, with the matter listed for 30.03.2022.

45
Stage 4403/03/2022

Defect Removal

The matter is adjourned to 07.03.2022 following a request by the counsel for the applicant.

46
Stage 4524/12/2021

Defect Removal

The Tribunal directed the appellant to rectify registry defects and deposit the required amount under Section 43(5) of the Act within 15 days.

47
Stage 46Interim Order

Tribunal Order #0901126050552021-12-07-2022

The Tribunal condoned the delay in filing the appeal, citing the Supreme Court's exclusion of the COVID-19 period for limitation purposes, and directed the Registry to convert the defective appeal into a regular appeal.

48
Stage 47Final Ruling Order

Tribunal Order #0901126050552021-07-01-2026

The Tribunal dismissed the appellant's appeal, ruling that farmer's agitation does not qualify as a force majeure event to waive interest for project delays, and directed the respondent to take possession of the unit within four weeks of a demand notice.

49
Stage 48Final Ruling Order

Tribunal Order #0901126050552021-08-05-2025

The appeal filed by Yamuna Expressway Industrial Development Authority was dismissed due to the appellant's failure to appear for the hearing.

50
Stage 49Interim Order

Tribunal Order #0901126050552021-02-08-2023

The Tribunal directed the appellant to place on record the Occupancy Certificate (OC/CC) and any offer of possession provided to the respondent to determine compliance with previous directions. The appeal, which challenges the interest rate calculation for delayed possession, is listed for further hearing on 11.09.2023.

51
Stage 50Interim Order

Tribunal Order #0901126050552021-21-09-2022

The Tribunal directed the appellant to approach the respondent with a formal offer to settle the dispute amicably regarding possession and the execution of the conveyance deed before the next hearing date.

52
Stage 51Interim Order

Tribunal Order #0901126050552021-04-02-2025

The Tribunal granted the appellant further time to produce the OC/CC for the project, subject to a cost of Rs. 5,000 to be paid by the appellant for the library of legal representatives.

53
Stage 52Interim Order

Tribunal Order #0901126050552021-24-12-2021

The Tribunal directed the appellant to rectify registry defects and deposit the required amount under Section 43(5) of the Act within 15 days.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appellant's appeal, ruling that farmer's agitation does not qualify as a force majeure event to waive interest for project delays, and directed the respondent to take possession of the unit within four weeks of a demand notice. The appeal filed by Yamuna Expressway Industrial Development Authority was dismissed due to the appellant's failure to appear for the hearing. Awarded in favor of Respondent. Awarded interest rate: MCLR+1 percent.

Disposal Winner: RespondentInterest Rate: MCLR+1 percentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appellant's appeal, ruling that farmer's agitation does not qualify as a force majeure event to waive interest for project delays, and directed the respondent to take possession of the unit within four weeks of a demand notice. The appeal filed by Yamuna Expressway Industrial Development Authority was dismissed due to the appellant's failure to appear for the hearing.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1 percent

Interest Period

with effect from 16.08.2018 till the date of Occupation/Completion certificate (OC/CC)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Prashant Kumar
  • Fuhar Gupta

Respondent Advocate(s)

  • Respondent In-Person

Official RERA Tribunal Orders (7)

INTERIM_ORDEROrder ID: 0901126050552021-12-07-2022

The Tribunal condoned the delay in filing the appeal, citing the Supreme Court's exclusion of the COVID-19 period for limitation purposes, and directed the Registry to convert the defective appeal into a regular appeal.

FINAL_ORDEROrder ID: 0901126050552021-07-01-2026

The Tribunal dismissed the appellant's appeal, ruling that farmer's agitation does not qualify as a force majeure event to waive interest for project delays, and directed the respondent to take possession of the unit within four weeks of a demand notice.

FINAL_ORDEROrder ID: 0901126050552021-08-05-2025

The appeal filed by Yamuna Expressway Industrial Development Authority was dismissed due to the appellant's failure to appear for the hearing.

INTERIM_ORDEROrder ID: 0901126050552021-02-08-2023

The Tribunal directed the appellant to place on record the Occupancy Certificate (OC/CC) and any offer of possession provided to the respondent to determine compliance with previous directions. The appeal, which challenges the interest rate calculation for delayed possession, is listed for further hearing on 11.09.2023.

INTERIM_ORDEROrder ID: 0901126050552021-21-09-2022

The Tribunal directed the appellant to approach the respondent with a formal offer to settle the dispute amicably regarding possession and the execution of the conveyance deed before the next hearing date.

INTERIM_ORDEROrder ID: 0901126050552021-04-02-2025

The Tribunal granted the appellant further time to produce the OC/CC for the project, subject to a cost of Rs. 5,000 to be paid by the appellant for the library of legal representatives.

INTERIM_ORDEROrder ID: 0901126050552021-24-12-2021

The Tribunal directed the appellant to rectify registry defects and deposit the required amount under Section 43(5) of the Act within 15 days.