Appellant / Complainant
Yamuna Expressway Industrial Development Authority
Respondent
Vijay Kumar Grover
₹9,43,172
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126050552021 by Yamuna Expressway Industrial Development Authority against Vijay Kumar Grover before up_rera.
Hearing
The Tribunal dismissed the appellant's appeal, ruling that farmer's agitation does not qualify as a force majeure event to waive interest for project delays, and directed the respondent to take possession of the unit within four weeks of a demand notice.
Hearing
The Tribunal scheduled the appeal for its next hearing on January 7, 2026, and explicitly noted that no further adjournments will be granted.
Hearing
The Tribunal granted the appellant time to seek instructions regarding possession and conveyance deed execution and adjourned the appeal to 08.12.2025.
Hearing
The Tribunal adjourned the appeal to 06.11.2025 and directed the Registry to notify the respondent to appear virtually at 11:30 a.m. on that date.
Hearing
The appeal has been restored to its original number and is scheduled for the next hearing on 14.10.2025.
Hearing
The appeal filed by Yamuna Expressway Industrial Development Authority was dismissed due to the appellant's failure to appear for the hearing.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and directed the appellant to upload the required affidavit regarding OC/CC, listing the matter for hearing on 08.05.2025.
Hearing
The Tribunal has scheduled the case for orders on April 16, 2025.
Hearing
The Tribunal granted the appellant 10 days to upload an affidavit regarding the issuance of OC/CC and scheduled the next hearing for March 20, 2025.
Hearing
The Tribunal granted the appellant further time to produce the OC/CC for the project, subject to a cost of Rs. 5,000 to be paid by the appellant for the library of legal representatives.
Hearing
The Tribunal granted the appellant 15 days to file a reply to a query raised in a previous order and scheduled the next hearing for February 4, 2025.
Hearing
The Tribunal granted an adjournment due to the illness of the appellant's counsel and rescheduled the hearing for January 6, 2025.
Hearing
The Tribunal granted a request to reschedule the hearing of Appeal-997/2021 to 10.12.2024, noting that no further adjournments will be permitted.
Hearing
The Tribunal has granted a request by the appellant's counsel to reschedule the hearing of the appeal to 18.11.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the matter for a hearing on 03.10.2024.
Hearing
The Tribunal granted a request from the appellant's counsel to reschedule the hearing of the appeal to 01.08.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to a personal bereavement and rescheduled the matter for hearing on 29.04.2024.
Hearing
The Tribunal granted the appellant's counsel additional time to produce relevant provisions regarding YEIDA's exemption from seeking OC/CC and adjourned the hearing to 22.03.2024.
Hearing
The Tribunal granted an adjournment due to the appellant's counsel's illness and rescheduled the hearing for 20.02.2024, noting that no further adjournments will be permitted.
Hearing
The Tribunal adjourned the proceedings and rescheduled the hearing for 17.10.2023 due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh.
Hearing
The Tribunal directed the appellant to place on record the Occupancy Certificate (OC/CC) and any offer of possession provided to the respondent to determine compliance with previous directions. The appeal, which challenges the interest rate calculation for delayed possession, is listed for further hearing on 11.09.2023.
Hearing
The Tribunal rescheduled the appeal for hearing on 02.08.2023 and noted the respondent's absence, stipulating that no further adjournments will be granted on the next date.
Hearing
The Tribunal directed the appellant to place the status of the Occupancy Certificate (OC) or Completion Certificate (CC) on record by the next hearing date of 22.05.2023.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the matter for hearing on 05.12.2022.
Hearing
The Tribunal has scheduled the case for a hearing on December 1, 2022.
Hearing
The Tribunal adjourned the proceedings due to the respondent's inability to join the virtual hearing because of poor connectivity, rescheduling the matter for 02.11.2022.
Hearing
The Tribunal directed the appellant to approach the respondent with a formal offer to settle the dispute amicably regarding possession and the execution of the conveyance deed before the next hearing date.
Hearing
The Tribunal adjourned the proceedings to 21.09.2022 and directed that the order be sent to the respondent via email, noting that the matter will proceed based on available records if the respondent fails to appear.
Hearing
The Tribunal scheduled the appeal for a hearing on 12.09.2022 and directed that the matter may proceed ex parte if the respondent fails to appear.
Hearing
The Tribunal noted the absence of the appellant and scheduled the appeal for a hearing on 22.08.2022, noting that pleadings have been exchanged.
Delay condonation
The Tribunal condoned the delay in filing the appeal, citing the Supreme Court's exclusion of the COVID-19 period for limitation purposes, and directed the Registry to convert the defective appeal into a regular appeal.
Delay condonation
The Tribunal adjourned the matter to 12.07.2022 for consideration of a condonation of delay application and directed the parties to exchange pleadings in the interim.
Delay condonation
The Tribunal granted the appellant three days to file a reply to the respondent's objections and scheduled the matter for May 23, 2022, to consider the application for condonation of delay.
Delay condonation
The Tribunal granted the applicant 10 days to file a reply to the respondent's objections and scheduled the defective appeal for hearing on May 9, 2022.
Delay condonation
The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objections and scheduled the case for hearing on 20.04.2022 regarding the application for condonation of delay.
Delay condonation
The Tribunal issued notice to the respondent regarding the appeal and directed the applicant to serve the notice and relevant documents via speed-post and email, with the matter listed for 30.03.2022.
Defect Removal
The matter is adjourned to 07.03.2022 following a request by the counsel for the applicant.
Defect Removal
The Tribunal directed the appellant to rectify registry defects and deposit the required amount under Section 43(5) of the Act within 15 days.
Tribunal Order #0901126050552021-12-07-2022
The Tribunal condoned the delay in filing the appeal, citing the Supreme Court's exclusion of the COVID-19 period for limitation purposes, and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Order #0901126050552021-07-01-2026
The Tribunal dismissed the appellant's appeal, ruling that farmer's agitation does not qualify as a force majeure event to waive interest for project delays, and directed the respondent to take possession of the unit within four weeks of a demand notice.
Tribunal Order #0901126050552021-08-05-2025
The appeal filed by Yamuna Expressway Industrial Development Authority was dismissed due to the appellant's failure to appear for the hearing.
Tribunal Order #0901126050552021-02-08-2023
The Tribunal directed the appellant to place on record the Occupancy Certificate (OC/CC) and any offer of possession provided to the respondent to determine compliance with previous directions. The appeal, which challenges the interest rate calculation for delayed possession, is listed for further hearing on 11.09.2023.
Tribunal Order #0901126050552021-21-09-2022
The Tribunal directed the appellant to approach the respondent with a formal offer to settle the dispute amicably regarding possession and the execution of the conveyance deed before the next hearing date.
Tribunal Order #0901126050552021-04-02-2025
The Tribunal granted the appellant further time to produce the OC/CC for the project, subject to a cost of Rs. 5,000 to be paid by the appellant for the library of legal representatives.
Tribunal Order #0901126050552021-24-12-2021
The Tribunal directed the appellant to rectify registry defects and deposit the required amount under Section 43(5) of the Act within 15 days.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appellant's appeal, ruling that farmer's agitation does not qualify as a force majeure event to waive interest for project delays, and directed the respondent to take possession of the unit within four weeks of a demand notice. The appeal filed by Yamuna Expressway Industrial Development Authority was dismissed due to the appellant's failure to appear for the hearing. Awarded in favor of Respondent. Awarded interest rate: MCLR+1 percent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appellant's appeal, ruling that farmer's agitation does not qualify as a force majeure event to waive interest for project delays, and directed the respondent to take possession of the unit within four weeks of a demand notice. The appeal filed by Yamuna Expressway Industrial Development Authority was dismissed due to the appellant's failure to appear for the hearing.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1 percent
Interest Period
with effect from 16.08.2018 till the date of Occupation/Completion certificate (OC/CC)
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Prashant Kumar
- Fuhar Gupta
Respondent Advocate(s)
- Respondent In-Person
Official RERA Tribunal Orders (7)
The Tribunal condoned the delay in filing the appeal, citing the Supreme Court's exclusion of the COVID-19 period for limitation purposes, and directed the Registry to convert the defective appeal into a regular appeal.
The Tribunal dismissed the appellant's appeal, ruling that farmer's agitation does not qualify as a force majeure event to waive interest for project delays, and directed the respondent to take possession of the unit within four weeks of a demand notice.
The appeal filed by Yamuna Expressway Industrial Development Authority was dismissed due to the appellant's failure to appear for the hearing.
The Tribunal directed the appellant to place on record the Occupancy Certificate (OC/CC) and any offer of possession provided to the respondent to determine compliance with previous directions. The appeal, which challenges the interest rate calculation for delayed possession, is listed for further hearing on 11.09.2023.
The Tribunal directed the appellant to approach the respondent with a formal offer to settle the dispute amicably regarding possession and the execution of the conveyance deed before the next hearing date.
The Tribunal granted the appellant further time to produce the OC/CC for the project, subject to a cost of Rs. 5,000 to be paid by the appellant for the library of legal representatives.
The Tribunal directed the appellant to rectify registry defects and deposit the required amount under Section 43(5) of the Act within 15 days.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.