Appellant / Complainant
Arun Kumar Singh, Sheril Singh
Respondent
U.P. Real Estate Regulatory Authority, M/s. Urban Homes Realcon Pvt. Ltd
urban homes realcon pvt. ltd.
₹12,68,505
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126049852022 by Arun Kumar Singh, Sheril Singh against U.P. Real Estate Regulatory Authority, M/s. Urban Homes Realcon Pvt. Ltd before up_rera.
Delay condonation
The Tribunal dismissed the appeal filed by the appellant, ruling that the second complaint was not maintainable as it concealed facts regarding the promoter's timely offer of possession following the receipt of an occupancy certificate.
Delay condonation
The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 12.10.2023.
Delay condonation
The Tribunal noted the absence of the respondent's counsel and ordered the defective appeal to be listed for hearing on 04.09.2023.
Delay condonation
The Tribunal listed the defective appeal for consideration of the application for condonation of delay and a subsequent hearing on 09.08.2023.
Delay condonation
The Tribunal granted the appellant's counsel time to provide a soft copy of their reply to the respondent and rescheduled the hearing for 29.05.2023.
Delay condonation
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections regarding the condonation of delay and the grounds of appeal, scheduling the next hearing for April 21, 2023.
Delay condonation
The Tribunal granted respondent no. 2 a final 10-day extension to file objections and directed the service of these objections via email, scheduling the next hearing for February 2, 2023.
Notice
The Tribunal granted respondent no. 2 ten days to file objections to the grounds of appeal and the application for condonation of delay, and scheduled the matter for hearing on 30.11.2022.
Notice
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the appeal for hearing on 01.11.2022.
Delay condonation
The Tribunal issued notice to the respondent regarding an application for condonation of delay and scheduled the appeal for hearing on 26.09.2022.
Tribunal Order #0901126049852022-16-01-2024
The Tribunal dismissed the appeal filed by the appellant, ruling that the second complaint was not maintainable as it concealed facts regarding the promoter's timely offer of possession following the receipt of an occupancy certificate.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal filed by the appellant, ruling that the second complaint was not maintainable as it concealed facts regarding the promoter's timely offer of possession following the receipt of an occupancy certificate. Awarded in favor of Respondent. Awarded interest rate: 12% per annum.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal filed by the appellant, ruling that the second complaint was not maintainable as it concealed facts regarding the promoter's timely offer of possession following the receipt of an occupancy certificate.
Ruling Awarded To
Respondent
Awarded Interest Rate
12% per annum
Interest Period
w.e.f. 10.10.2018 till the date of actual payment
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Vineet K Singh Bisen
Respondent Advocate(s)
- Kshemendra Shukla
Official RERA Tribunal Orders (1)
The Tribunal dismissed the appeal filed by the appellant, ruling that the second complaint was not maintainable as it concealed facts regarding the promoter's timely offer of possession following the receipt of an occupancy certificate.