up_reraStatus: Completed
CASE ID: 0901126049772023

Appellant / Complainant

U.P. State Industrial Development Authority

VS

Respondent

Pragya Mehrotra

Disputed Amount

36,77,500

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

22 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126049772023 by U.P. State Industrial Development Authority against Pragya Mehrotra before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 126/03/2025

Hearing

The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession.

3
Stage 221/02/2025

Delay condonation

The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.

4
Stage 329/01/2025

Delay condonation

The Tribunal allowed a recall application to set aside an order imposing costs of Rs. 5000/- on the appellant's counsel due to health issues and rescheduled the appeal for hearing on 21.02.2024.

5
Stage 422/01/2025

Delay condonation

No text available.

6
Stage 515/01/2025

Delay condonation

No text available.

7
Stage 611/12/2024

Delay condonation

The Tribunal adjourned the appeal due to the appellant's counsel seeking an adjournment despite a stop order, imposing a cost of Rs. 5,000/- to be paid by the appellant to the respondent.

8
Stage 713/11/2024

Delay condonation

The Tribunal refers the parties to a previously passed order dated in Appeal No. D 662/2023 for the current orders.

9
Stage 816/10/2024

Delay condonation

The Tribunal granted a request by the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 13.11.2024.

10
Stage 905/09/2024

Delay condonation

The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the case for hearing on 16.10.2024.

11
Stage 1029/07/2024

Delay condonation

The Tribunal granted the appellant a final opportunity to file a reply to the respondent's objections and scheduled the defective appeal for orders on 05.09.2024.

12
Stage 1101/07/2024

Delay condonation

The Tribunal granted the appellant one week's time to file a reply to the respondent's objection and scheduled the matter for orders on 29.07.2024.

13
Stage 1201/05/2024

Delay condonation

No text available.

14
Stage 1329/03/2024

Delay condonation

The Tribunal refers the parties to a previous order passed in appeal No. D 660/2023 for the relevant directions.

15
Stage 1423/02/2024

Delay condonation

The Tribunal granted the respondent an additional week to file objections to the grounds of appeal and directed the exchange of soft copies between counsel. The matter is scheduled for hearing on the application for condonation of delay on 29.03.2024.

16
Stage 1516/01/2024

Delay condonation

The Tribunal granted 10 days to the respondent for filing a reply and scheduled the defective appeal for consideration of condonation of delay on 23.02.2024.

17
Stage 1618/12/2023

Delay condonation

The Tribunal issued notice to the respondent regarding an application for condonation of delay in filing the appeal and scheduled the matter for hearing on 16.01.2024.

18
Stage 17Final Ruling Order

Tribunal Order #0901126049772023-26-03-2025

The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession.

19
Stage 18Interim Order

Tribunal Order #0901126049772023-21-02-2025

The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.

20
Stage 19Interim Order

Tribunal Order #0901126049772023-11-12-2024

The Tribunal adjourned the appeal due to the appellant's counsel seeking an adjournment despite a stop order, imposing a cost of Rs. 5,000/- to be paid by the appellant to the respondent.

21
Stage 20Interim Order

Tribunal Order #0901126049772023-29-01-2025

The Tribunal allowed a recall application to set aside an order imposing costs of Rs. 5000/- on the appellant's counsel due to health issues and rescheduled the appeal for hearing on 21.02.2024.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.01.2017 till development certificate/ completion certificate or till handing over the possession whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shuchita Singh
  • Sanjeev Singh

Respondent Advocate(s)

  • Deepak Dwivedi
  • Prasoon Kumar Anjor

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126049772023-26-03-2025

The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession.

INTERIM_ORDEROrder ID: 0901126049772023-21-02-2025

The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.

INTERIM_ORDEROrder ID: 0901126049772023-11-12-2024

The Tribunal adjourned the appeal due to the appellant's counsel seeking an adjournment despite a stop order, imposing a cost of Rs. 5,000/- to be paid by the appellant to the respondent.

INTERIM_ORDEROrder ID: 0901126049772023-29-01-2025

The Tribunal allowed a recall application to set aside an order imposing costs of Rs. 5000/- on the appellant's counsel due to health issues and rescheduled the appeal for hearing on 21.02.2024.