up_reraStatus: Completed
CASE ID: 0901126049272023

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Neha Jain

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

8 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126049272023 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Neha Jain before up_rera.

2
Stage 113/02/2024

Delay condonation

The appeal was dismissed as withdrawn following a settlement between the parties, with the Tribunal noting that the release of funds deposited under Section 43(5) will be addressed upon receipt of a formal application.

3
Stage 223/01/2024

Delay condonation

The Tribunal granted the appellant one week to file an affidavit of service regarding notices issued to the respondent and scheduled the matter for orders on 13.02.2024.

4
Stage 302/01/2024

Delay condonation

The Tribunal allowed the appellant's application to amend the prayer clause of the appeal and directed the issuance of notice to the respondent regarding the application for condonation of delay.

5
Stage 421/12/2023

Delay condonation

The Tribunal granted the appellant one week's time to file an amendment application regarding the prayer clause of the appeal and scheduled the matter for orders on January 2, 2024.

6
Stage 5Final Ruling Order

Tribunal Order #0901126049272023-13-02-2024

The appeal was dismissed as withdrawn following a settlement between the parties, with the Tribunal noting that the release of funds deposited under Section 43(5) will be addressed upon receipt of a formal application.

7
Stage 6Interim Order

Tribunal Order #0901126049272023-02-01-2024

The Tribunal allowed the appellant's application to amend the prayer clause of the appeal and directed the issuance of notice to the respondent regarding the application for condonation of delay.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The appeal was dismissed as withdrawn following a settlement between the parties, with the Tribunal noting that the release of funds deposited under Section 43(5) will be addressed upon receipt of a formal application. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The appeal was dismissed as withdrawn following a settlement between the parties, with the Tribunal noting that the release of funds deposited under Section 43(5) will be addressed upon receipt of a formal application.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Naveen Kumar Tiwari

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126049272023-13-02-2024

The appeal was dismissed as withdrawn following a settlement between the parties, with the Tribunal noting that the release of funds deposited under Section 43(5) will be addressed upon receipt of a formal application.

INTERIM_ORDEROrder ID: 0901126049272023-02-01-2024

The Tribunal allowed the appellant's application to amend the prayer clause of the appeal and directed the issuance of notice to the respondent regarding the application for condonation of delay.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →