up_reraStatus: Completed
CASE ID: 0901126049182023

Appellant / Complainant

U.P. State Industrial Development Authority

VS

Respondent

Abhishek Kumar

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

35 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126049182023 by U.P. State Industrial Development Authority against Abhishek Kumar before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 109/12/2025

Part Heard

The Tribunal dismissed the appeals filed by U.P. State Industrial Development Authority and affirmed the RERA order directing the promoter to pay delay interest to allottees from April 1, 2017, until the receipt of completion certificate or handing over of possession.

3
Stage 227/11/2025

Part Heard

No text available.

4
Stage 306/11/2025

Part Heard

The Tribunal granted an adjournment application filed by the appellant and scheduled the matter for further hearing on 27.11.2025.

5
Stage 416/10/2025

Hearing

The Tribunal has scheduled the appeal for a final hearing as part heard on November 6, 2025.

6
Stage 517/09/2025

Hearing

The Tribunal granted the appellant's counsel additional time to prepare his brief and adjourned the matter to 16.10.2025.

7
Stage 611/09/2025

Hearing

The Tribunal heard partial arguments from both counsels and adjourned the matter to 17.09.2025 for further hearing or rest of arguments.

8
Stage 727/08/2025

Hearing

The Tribunal ordered the appeal to be listed on 11.09.2025 along with other similar appeals in the same bunch.

9
Stage 813/08/2025

Hearing

The Tribunal scheduled the appeal for a subsequent hearing on 27.08.2025, alongside Appeal No. 51/2024 and Appeal No. 664/2023, noting that no further adjournments will be granted.

10
Stage 928/07/2025

Hearing

The Tribunal granted the appellant's counsel time to study a referred judgment and adjourned the matter to 13.08.2025 for final hearing.

11
Stage 1008/07/2025

Hearing

The Tribunal adjourned the matter to 28.07.2025 for final hearing and explicitly clarified that no further adjournments will be granted to either party.

12
Stage 1108/05/2025

Hearing

The Tribunal has granted a request from the parties to list the appeal for orders or hearing on July 8, 2025.

13
Stage 1224/04/2025

Hearing

The Tribunal granted adjournment applications filed by both parties and rescheduled the appeal for hearing on 08.05.2025.

14
Stage 1326/03/2025

Hearing

Upon the joint request of both parties, the Tribunal has adjourned the appeal for orders/hearing to 24.04.2025.

15
Stage 1421/02/2025

Delay condonation

The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.

16
Stage 1529/01/2025

Delay condonation

The Tribunal allowed the recall application and set aside the order dated 11.12.2024 which had imposed a cost of Rs. 5,000/- on the appellant due to counsel's non-appearance.

17
Stage 1622/01/2025

Delay condonation

No text available.

18
Stage 1715/01/2025

Delay condonation

No text available.

19
Stage 1811/12/2024

Delay condonation

The Tribunal adjourned the appeal due to the appellant's counsel seeking an adjournment despite a stop order, imposing a cost of Rs. 5,000/- payable by the appellant to the respondent.

20
Stage 1913/11/2024

Delay condonation

The Tribunal refers the parties to a previous order passed on a different appeal number (D 662/2023) for the relevant directions.

21
Stage 2016/10/2024

Delay condonation

The Tribunal granted a request by the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 13.11.2024.

22
Stage 2105/09/2024

Delay condonation

The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the case for hearing on 16.10.2024.

23
Stage 2229/07/2024

Delay condonation

The Tribunal granted the appellant a final opportunity to file a reply to the respondent's objections and scheduled the defective appeal for orders on 05.09.2024.

24
Stage 2301/07/2024

Delay condonation

The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objection and scheduled the matter for orders on 29.07.2024.

25
Stage 2401/05/2024

Delay condonation

No text available.

26
Stage 2529/03/2024

Delay condonation

The Tribunal refers the parties to a previously passed order dated 29.03.2024 in appeal No. D 660/2023 for the relevant orders.

27
Stage 2623/02/2024

Delay condonation

The Tribunal granted the respondent one week to file objections to the grounds of appeal and directed the exchange of soft copies between counsel, scheduling the matter for hearing on March 29, 2024.

28
Stage 2716/01/2024

Delay condonation

The Tribunal granted the respondent 10 days to file a reply to objections and scheduled the defective appeal for consideration of the condonation of delay application on 23.02.2024.

29
Stage 2818/12/2023

Delay condonation

The Tribunal noted the appellant's compliance with Section 43(5) regarding the deposit of Rs.11,57,840/- and issued notice to the respondent on the application for condonation of a 90-day delay in filing the appeal.

30
Stage 29Interim Order

Tribunal Order #0901126049182023-11-12-2024

The Tribunal adjourned the appeal due to the appellant's counsel seeking an adjournment despite a stop order, imposing a cost of Rs. 5,000/- payable by the appellant to the respondent.

31
Stage 30Final Ruling Order

Tribunal Order #0901126049182023-09-12-2025

The Tribunal dismissed the appeals filed by U.P. State Industrial Development Authority and affirmed the RERA order directing the promoter to pay delay interest to allottees from April 1, 2017, until the receipt of completion certificate or handing over of possession.

32
Stage 31Interim Order

Tribunal Order #0901126049182023-21-02-2025

The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.

33
Stage 32Interim Order

Tribunal Order #0901126049182023-29-01-2025

The Tribunal allowed the recall application and set aside the order dated 11.12.2024 which had imposed a cost of Rs. 5,000/- on the appellant due to counsel's non-appearance.

34
Stage 33Interim Order

Tribunal Order #0901126049182023-18-12-2023

The Tribunal noted the appellant's compliance with Section 43(5) regarding the deposit of Rs.11,57,840/- and issued notice to the respondent on the application for condonation of a 90-day delay in filing the appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeals filed by U.P. State Industrial Development Authority and affirmed the RERA order directing the promoter to pay delay interest to allottees from April 1, 2017, until the receipt of completion certificate or handing over of possession. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.

Disposal Winner: RespondentInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeals filed by U.P. State Industrial Development Authority and affirmed the RERA order directing the promoter to pay delay interest to allottees from April 1, 2017, until the receipt of completion certificate or handing over of possession.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR + 1%

Interest Period

with effect from 01.04.2017 till receipt of development certificate/completion certificate or till handing over the possession, whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shuchita Singh
  • Sanjeev Singh

Respondent Advocate(s)

  • Deepak Dwivedi

Official RERA Tribunal Orders (5)

INTERIM_ORDEROrder ID: 0901126049182023-11-12-2024

The Tribunal adjourned the appeal due to the appellant's counsel seeking an adjournment despite a stop order, imposing a cost of Rs. 5,000/- payable by the appellant to the respondent.

FINAL_ORDEROrder ID: 0901126049182023-09-12-2025

The Tribunal dismissed the appeals filed by U.P. State Industrial Development Authority and affirmed the RERA order directing the promoter to pay delay interest to allottees from April 1, 2017, until the receipt of completion certificate or handing over of possession.

INTERIM_ORDEROrder ID: 0901126049182023-21-02-2025

The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.

INTERIM_ORDEROrder ID: 0901126049182023-29-01-2025

The Tribunal allowed the recall application and set aside the order dated 11.12.2024 which had imposed a cost of Rs. 5,000/- on the appellant due to counsel's non-appearance.

INTERIM_ORDEROrder ID: 0901126049182023-18-12-2023

The Tribunal noted the appellant's compliance with Section 43(5) regarding the deposit of Rs.11,57,840/- and issued notice to the respondent on the application for condonation of a 90-day delay in filing the appeal.