Appellant / Complainant
U.P. State Industrial Development Authority
Respondent
Rahul Kamal
₹36,77,500
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126049142023 by U.P. State Industrial Development Authority against Rahul Kamal before up_rera.
Hearing
The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession.
Delay condonation
The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.
Delay condonation
The Tribunal allowed the recall application and set aside the order dated 11.12.2024 which had imposed a cost of Rs. 5,000 due to the counsel's non-appearance.
Delay condonation
The Tribunal adjourned the appeal due to the appellant's counsel seeking adjournment despite a stop order, imposing a cost of Rs. 5,000/- payable by the appellant to the respondent.
Delay condonation
The order refers to a previous order passed in Appeal No. D 662/2023 for further directions.
Delay condonation
The Tribunal granted a request by the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 13.11.2024.
Delay condonation
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the case for orders/hearing on 16.10.2024.
Delay condonation
The Tribunal granted a final opportunity to the appellant's counsel to file a reply to the respondent's objections and listed the defective appeal for orders on 05.09.2024.
Delay condonation
The Tribunal granted the appellant one week to file a reply to the respondent's objections and listed the appeal for orders on July 29, 2024.
Delay condonation
This is a procedural order directing the parties to refer to a previously passed order dated in appeal No. D 660/2023.
Delay condonation
The Tribunal granted a one-week extension to the respondent for filing objections to the grounds of appeal and directed the exchange of soft copies between counsel. The matter is scheduled for hearing on March 29, 2024.
Delay condonation
The Tribunal granted 10 days to the respondent for filing a reply to objections and scheduled the hearing for February 23, 2024, to consider the application for condonation of delay.
Delay condonation
The Tribunal issued notice to the respondent regarding an application for condonation of a 90-day delay in filing the appeal and set the matter for hearing on 16.01.2024.
Tribunal Order #0901126049142023-26-03-2025
The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession.
Tribunal Order #0901126049142023-29-01-2025
The Tribunal allowed the recall application and set aside the order dated 11.12.2024 which had imposed a cost of Rs. 5,000 due to the counsel's non-appearance.
Tribunal Order #0901126049142023-21-02-2025
The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Order #0901126049142023-11-12-2024
The Tribunal adjourned the appeal due to the appellant's counsel seeking adjournment despite a stop order, imposing a cost of Rs. 5,000/- payable by the appellant to the respondent.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 01.01.2017 till development certificate/ completion certificate or till handing over the possession whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Shuchita Singh
- Sanjeev Singh
Respondent Advocate(s)
- Deepak Dwivedi
Official RERA Tribunal Orders (4)
The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession.
The Tribunal allowed the recall application and set aside the order dated 11.12.2024 which had imposed a cost of Rs. 5,000 due to the counsel's non-appearance.
The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.
The Tribunal adjourned the appeal due to the appellant's counsel seeking adjournment despite a stop order, imposing a cost of Rs. 5,000/- payable by the appellant to the respondent.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.