Appellant / Complainant
U.P. State Industrial Development Authority
Respondent
Ranjeet Kumar Tiwari
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126048942023 by U.P. State Industrial Development Authority against Ranjeet Kumar Tiwari before up_rera.
Part Heard
The Tribunal dismissed the appeals filed by the U.P. State Industrial Development Authority, affirming that the promoter is liable to pay delay interest to allottees from the originally declared possession date of January 1, 2017, until the receipt of a completion certificate or handing over of possession.
Part Heard
The Tribunal granted an adjournment application filed by the appellant's counsel and scheduled the matter for further hearing on 27.11.2025.
Hearing
The Tribunal has scheduled the appeal for a final hearing as part-heard on November 6, 2025.
Hearing
The Tribunal granted the appellant's counsel additional time to prepare their brief and adjourned the matter to 16.10.2025.
Hearing
The Tribunal heard arguments from both counsels and adjourned the matter to 17.09.2025 for further hearing or arguments.
Hearing
The Tribunal has ordered the appeal to be listed on 11.09.2025 along with other similar cases.
Hearing
The Tribunal listed the appeal for a subsequent hearing on 27.08.2025, along with two other connected appeals, and clarified that no further adjournments will be granted.
Hearing
The Tribunal granted the appellant's counsel time to study a cited judgment and adjourned the matter to 13.08.2025 for final hearing.
Hearing
The Tribunal granted a request for adjournment and scheduled the case for final hearing on 28.07.2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal has granted a request from the parties to list the appeal for orders or hearing on July 8, 2025.
Hearing
The Tribunal granted adjournment applications filed by both parties and rescheduled the appeal for hearing on 08.05.2025.
Hearing
Upon the joint request of both parties, the appeal has been adjourned for orders or hearing to be listed on 24.04.2025.
Delay condonation
The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.
Delay condonation
The Tribunal allowed the recall application to set aside a previous order imposing a cost of Rs. 5000/- on the appellant's counsel due to health issues and scheduled the appeal for hearing on 21.02.2024.
Delay condonation
The Tribunal adjourned the appeal due to the absence of the appellant's counsel and imposed a cost of Rs. 5,000/- to be paid by the appellant to the respondent.
Delay condonation
This is a procedural order directing the parties to refer to a previous order passed in Appeal No. D 662/2023.
Delay condonation
The court granted a request by the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 13.11.2024.
Delay condonation
The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the matter for hearing on 16.10.2024.
Delay condonation
The Tribunal granted the appellant a final opportunity to file a reply to the respondent's objections and scheduled the defective appeal for orders on September 5, 2024.
Delay condonation
The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objection and scheduled the matter for orders on 29.07.2024.
Delay condonation
The Tribunal refers the parties to a previously passed order dated 29.03.2024 in appeal No. D 660/2023 for directions.
Delay condonation
The Tribunal granted the respondent an additional week to file objections to the grounds of appeal and directed the exchange of soft copies between counsel before the next hearing on 29.03.2024.
Delay condonation
The Tribunal granted 10 days to the respondent for filing a reply to objections and scheduled the matter for hearing on February 23, 2024, regarding an application for condonation of delay.
Delay condonation
The Tribunal issued notice to the respondent regarding the appellant's application for condonation of a 90-day delay in filing the appeal, following the mandatory deposit required under Section 43(5) of the Act.
Tribunal Order #0901126048942023-09-12-2025
The Tribunal dismissed the appeals filed by the U.P. State Industrial Development Authority, affirming that the promoter is liable to pay delay interest to allottees from the originally declared possession date of January 1, 2017, until the receipt of a completion certificate or handing over of possession.
Tribunal Order #0901126048942023-21-02-2025
The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Order #0901126048942023-29-01-2025
The Tribunal allowed the recall application to set aside a previous order imposing a cost of Rs. 5000/- on the appellant's counsel due to health issues and scheduled the appeal for hearing on 21.02.2024.
Tribunal Order #0901126048942023-11-12-2024
The Tribunal adjourned the appeal due to the absence of the appellant's counsel and imposed a cost of Rs. 5,000/- to be paid by the appellant to the respondent.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeals filed by the U.P. State Industrial Development Authority, affirming that the promoter is liable to pay delay interest to allottees from the originally declared possession date of January 1, 2017, until the receipt of a completion certificate or handing over of possession. Awarded in favor of Respondent. Awarded interest rate: MCLR + 1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeals filed by the U.P. State Industrial Development Authority, affirming that the promoter is liable to pay delay interest to allottees from the originally declared possession date of January 1, 2017, until the receipt of a completion certificate or handing over of possession.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR + 1%
Interest Period
from 01.01.2017 till receipt of development certificate/completion certificate or till handing over the possession, whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Shuchita Singh
- Sanjeev Singh
Respondent Advocate(s)
- Deepak Dwivedi
Official RERA Tribunal Orders (4)
The Tribunal dismissed the appeals filed by the U.P. State Industrial Development Authority, affirming that the promoter is liable to pay delay interest to allottees from the originally declared possession date of January 1, 2017, until the receipt of a completion certificate or handing over of possession.
The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.
The Tribunal allowed the recall application to set aside a previous order imposing a cost of Rs. 5000/- on the appellant's counsel due to health issues and scheduled the appeal for hearing on 21.02.2024.
The Tribunal adjourned the appeal due to the absence of the appellant's counsel and imposed a cost of Rs. 5,000/- to be paid by the appellant to the respondent.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.