Appellant / Complainant
U.P. State Industrial Development Authority
Respondent
Ankur Pal Singh
₹36,77,500
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126048932023 by U.P. State Industrial Development Authority against Ankur Pal Singh before up_rera.
Hearing
The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession, whichever is later.
Delay condonation
The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.
Delay condonation
The Tribunal allowed the recall application and set aside the order dated 11.12.2024 which had imposed a cost of Rs. 5,000/- on the appellant's counsel due to non-appearance.
Delay condonation
The Tribunal adjourned the appeal due to the absence of the appellant's counsel and imposed a cost of Rs. 5,000/- to be paid by the appellant to the respondent.
Delay condonation
This is a procedural order directing the parties to refer to a previously passed order dated in Appeal No. D 662/2023 for the relevant directions.
Delay condonation
Upon the request of the appellant's counsel, the tribunal has adjourned the matter and scheduled the appeal for a hearing on 13.11.2024.
Delay condonation
The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the matter for hearing on 16.10.2024.
Delay condonation
The Tribunal granted the appellant a final opportunity to file a reply to the respondent's objections and scheduled the matter for orders on September 5, 2024.
Delay condonation
The Tribunal granted the appellant's counsel a one-week extension to file a reply to the respondent's objection and scheduled the matter for orders on 29.07.2024.
Delay condonation
The Tribunal refers the parties to a previous order passed in appeal No. D 660/2023 regarding the current matter.
Delay condonation
The Tribunal granted the respondent one week to file objections to the grounds of appeal and directed the exchange of soft copies between counsel before listing the matter for hearing on 29.03.2024.
Delay condonation
The Tribunal granted 10 days to the respondent for filing a reply to objections and scheduled the matter for February 23, 2024, to consider an application for condonation of delay.
Delay condonation
The Tribunal issued notice to the respondent regarding an application for condonation of a 90-day delay in filing the appeal, after confirming compliance with Section 43(5) of the Act.
Tribunal Order #0901126048932023-26-03-2025
The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession, whichever is later.
Tribunal Order #0901126048932023-21-02-2025
The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Order #0901126048932023-11-12-2024
The Tribunal adjourned the appeal due to the absence of the appellant's counsel and imposed a cost of Rs. 5,000/- to be paid by the appellant to the respondent.
Tribunal Order #0901126048932023-29-01-2025
The Tribunal allowed the recall application and set aside the order dated 11.12.2024 which had imposed a cost of Rs. 5,000/- on the appellant's counsel due to non-appearance.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession, whichever is later. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession, whichever is later.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 01.01.2017 till development certificate/ completion certificate or till handing over the possession whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Shuchita Singh
- Sanjeev Singh
Respondent Advocate(s)
- Deepak Dwivedi
Official RERA Tribunal Orders (4)
The Tribunal dismissed the appeal filed by U.P. State Industrial Development Authority, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession, whichever is later.
The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.
The Tribunal adjourned the appeal due to the absence of the appellant's counsel and imposed a cost of Rs. 5,000/- to be paid by the appellant to the respondent.
The Tribunal allowed the recall application and set aside the order dated 11.12.2024 which had imposed a cost of Rs. 5,000/- on the appellant's counsel due to non-appearance.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.