Appellant / Complainant
U.P. State Industrial Development Authority
Respondent
Annapurna Pal
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126048872023 by U.P. State Industrial Development Authority against Annapurna Pal before up_rera.
Hearing
The Tribunal dismissed the appeal filed by UPSIDA, affirming the Regulatory Authority's order that the promoter must hand over possession of the plot and pay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession, whichever is later.
Hearing
The Tribunal granted an adjournment application filed by the appellant's counsel and rescheduled the hearing for April 27, 2026.
Hearing
The Tribunal granted the appellant seven days to upload a relevant Supreme Court order and adjourned the matter to 31.03.2026.
Hearing
The appeal is adjourned to 24.02.2026 due to a technical glitch with the NIC server.
Hearing
The Tribunal granted an adjournment application filed by the appellant and rescheduled the appeal for hearing on 02.02.2026.
Hearing
The Tribunal granted the respondent a final ten-day extension to file objections and scheduled the case for orders on 19.12.2025.
Hearing
The court granted an adjournment application filed by the appellant and rescheduled the hearing for November 25, 2025.
Hearing
The Tribunal has scheduled the case, along with cross appeal no. 51 of 2024, for further orders on November 6, 2025.
Hearing
The Tribunal has scheduled the appeal for a hearing on 13.10.2025, to be heard alongside the records of Appeal No. D 51/2024.
Hearing
The Tribunal has ordered the appeal to be listed for a hearing on 11.09.2025, along with Appeal No. D 51/20243.
Hearing
The Tribunal directed the Registry to list the appeal on 27.08.2025 before Bench no. 2 along with related bunch matters.
Hearing
The Tribunal granted the appellant's counsel time to study a cited judgment and adjourned the appeal to 13.08.2025 for final hearing.
Hearing
The Tribunal granted a request for adjournment and scheduled the case for final hearing on 28.07.2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal has granted a request from the parties to list the appeal for orders or hearing on 08.07.2025.
Hearing
The court granted adjournment applications filed by both parties and rescheduled the appeal for hearing on 08.05.2025.
Hearing
Upon the joint request of both parties, the appeal has been scheduled for orders or hearing on 24.04.2025.
Delay condonation
The Tribunal allowed the appellant's application to condone a 96-day delay in filing the appeal, subject to a cost of Rs. 1,000, and directed the registry to convert the defective appeal into a regular appeal.
Delay condonation
The Tribunal allowed the recall application and set aside the cost of Rs. 5,000 imposed on the appellant's counsel due to non-appearance caused by health issues.
Delay condonation
The Tribunal adjourned the appeal due to the appellant's counsel seeking an adjournment despite a stop order, imposing a cost of Rs. 5,000 to be paid by the appellant to the respondent.
Delay condonation
This is a procedural order referring the matter to a previous order passed in Appeal No. D 662/2023.
Delay condonation
The Tribunal granted a request by the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 13.11.2024.
Delay condonation
The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the matter for hearing on 16.10.2024.
Delay condonation
The Tribunal granted the appellant a final opportunity to file a reply to the respondent's objections and scheduled the defective appeal for orders on September 5, 2024.
Delay condonation
The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objection and scheduled the matter for orders on 29.07.2024.
Delay condonation
This is a procedural order directing the parties to refer to a previously passed order in appeal No. D 660/2023.
Delay condonation
The Tribunal granted the respondent an additional week to file objections to the grounds of appeal and directed the exchange of soft copies between counsel, scheduling the matter for March 29, 2024.
Delay condonation
The Tribunal granted the respondent 10 days to file a reply to the objections and scheduled the matter for hearing on 23.02.2024 to consider the application for condonation of delay.
Delay condonation
The Tribunal issued notice to the respondent regarding the appellant's application for condonation of a 90-day delay in filing the appeal and scheduled the matter for hearing on 16.01.2024.
Tribunal Order #0901126048872023-27-04-2026
The Tribunal dismissed the appeal filed by UPSIDA, affirming the Regulatory Authority's order that the promoter must hand over possession of the plot and pay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession, whichever is later.
Tribunal Order #0901126048872023-21-02-2025
The Tribunal allowed the appellant's application to condone a 96-day delay in filing the appeal, subject to a cost of Rs. 1,000, and directed the registry to convert the defective appeal into a regular appeal.
Tribunal Order #0901126048872023-29-01-2025
The Tribunal allowed the recall application and set aside the cost of Rs. 5,000 imposed on the appellant's counsel due to non-appearance caused by health issues.
Tribunal Order #0901126048872023-11-12-2024
The Tribunal adjourned the appeal due to the appellant's counsel seeking an adjournment despite a stop order, imposing a cost of Rs. 5,000 to be paid by the appellant to the respondent.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal filed by UPSIDA, affirming the Regulatory Authority's order that the promoter must hand over possession of the plot and pay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession, whichever is later. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal filed by UPSIDA, affirming the Regulatory Authority's order that the promoter must hand over possession of the plot and pay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession, whichever is later.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
with effect from 01.01.2017 till development certificate/ completion certificate or till handing over the possession whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Shuchita Singh
- Sanjeev Singh
Respondent Advocate(s)
- Deepak Dwivedi
Official RERA Tribunal Orders (4)
The Tribunal dismissed the appeal filed by UPSIDA, affirming the Regulatory Authority's order that the promoter must hand over possession of the plot and pay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession, whichever is later.
The Tribunal allowed the appellant's application to condone a 96-day delay in filing the appeal, subject to a cost of Rs. 1,000, and directed the registry to convert the defective appeal into a regular appeal.
The Tribunal allowed the recall application and set aside the cost of Rs. 5,000 imposed on the appellant's counsel due to non-appearance caused by health issues.
The Tribunal adjourned the appeal due to the appellant's counsel seeking an adjournment despite a stop order, imposing a cost of Rs. 5,000 to be paid by the appellant to the respondent.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.