up_reraStatus: Completed
CASE ID: 0901126048862023

Appellant / Complainant

U.P. State Industrial Development Authority

VS

Respondent

Rajkiran Chaurasia

Disputed Amount

36,77,500

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

23 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126048862023 by U.P. State Industrial Development Authority against Rajkiran Chaurasia before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 126/03/2025

Hearing

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDC, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession.

3
Stage 221/02/2025

Delay condonation

The Tribunal allowed the appellant's application for condonation of delay subject to a cost of Rs. 1000/- and directed the Registry to convert the defective appeal into a regular appeal.

4
Stage 329/01/2025

Delay condonation

The Tribunal allowed the recall application to set aside a previous order imposing a cost of Rs. 5000/- on the appellant's counsel due to health issues and scheduled the matter for hearing on 21.02.2024.

5
Stage 422/01/2025

Delay condonation

No text available.

6
Stage 515/01/2025

Delay condonation

No text available.

7
Stage 611/12/2024

Delay condonation

The Tribunal adjourned the batch of appeals due to the absence of the appellant's counsel and imposed a cost of Rs. 5,000/- to be paid by the appellant to the respondent.

8
Stage 713/11/2024

Delay condonation

The order refers to a previous order passed in Appeal No. D 662/2023 regarding the matter of U.P. State Industrial Development Authority vs. Rajkiran Chaurasia.

9
Stage 816/10/2024

Delay condonation

The Tribunal granted a request by the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 13.11.2024.

10
Stage 905/09/2024

Delay condonation

The Tribunal granted the appellant a final 10-day extension to file a reply to the respondent's objections and scheduled the matter for hearing on 16.10.2024.

11
Stage 1029/07/2024

Delay condonation

The Tribunal granted the appellant's counsel a final opportunity to file a reply to the respondent's objections and scheduled the defective appeal for orders on September 5, 2024.

12
Stage 1101/07/2024

Delay condonation

The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objection and scheduled the matter for orders on 29.07.2024.

13
Stage 1201/05/2024

Delay condonation

No text available.

14
Stage 1329/03/2024

Delay condonation

This is a procedural order directing the parties to refer to a previously passed order dated in appeal No. D 660/2023.

15
Stage 1423/02/2024

Delay condonation

The Tribunal granted the respondent an additional week to file objections to the grounds of appeal and directed the exchange of soft copies between counsel. The matter is scheduled for a hearing on the application for condonation of delay on 29.03.2024.

16
Stage 1516/01/2024

Delay condonation

The Tribunal granted the respondent 10 days to file a reply to objections and scheduled the matter for February 23, 2024, to consider an application for condonation of delay.

17
Stage 1618/12/2023

Delay condonation

The Tribunal issued notice to the respondent regarding an application for condonation of a 90-day delay in filing the appeal, noting that the appellant has complied with the mandatory deposit requirement under Section 43(5) of the Act.

18
Stage 17Interim Order

Tribunal Order #0901126048862023-29-01-2025

The Tribunal allowed the recall application to set aside a previous order imposing a cost of Rs. 5000/- on the appellant's counsel due to health issues and scheduled the matter for hearing on 21.02.2024.

19
Stage 18Interim Order

Tribunal Order #0901126048862023-18-12-2023

The Tribunal issued notice to the respondent regarding an application for condonation of a 90-day delay in filing the appeal, noting that the appellant has complied with the mandatory deposit requirement under Section 43(5) of the Act.

20
Stage 19Final Ruling Order

Tribunal Order #0901126048862023-26-03-2025

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDC, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession.

21
Stage 20Interim Order

Tribunal Order #0901126048862023-21-02-2025

The Tribunal allowed the appellant's application for condonation of delay subject to a cost of Rs. 1000/- and directed the Registry to convert the defective appeal into a regular appeal.

22
Stage 21Interim Order

Tribunal Order #0901126048862023-11-12-2024

The Tribunal adjourned the batch of appeals due to the absence of the appellant's counsel and imposed a cost of Rs. 5,000/- to be paid by the appellant to the respondent.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDC, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDC, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

with effect from 01.01.2017 till development certificate/ completion certificate or till handing over the possession whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shuchita Singh
  • Sanjeev Singh

Respondent Advocate(s)

  • Deepak Dwivedi

Official RERA Tribunal Orders (5)

INTERIM_ORDEROrder ID: 0901126048862023-29-01-2025

The Tribunal allowed the recall application to set aside a previous order imposing a cost of Rs. 5000/- on the appellant's counsel due to health issues and scheduled the matter for hearing on 21.02.2024.

INTERIM_ORDEROrder ID: 0901126048862023-18-12-2023

The Tribunal issued notice to the respondent regarding an application for condonation of a 90-day delay in filing the appeal, noting that the appellant has complied with the mandatory deposit requirement under Section 43(5) of the Act.

FINAL_ORDEROrder ID: 0901126048862023-26-03-2025

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDC, affirming the Regulatory Authority's order that the promoter must pay interest at MCLR+1% to the allottee from January 1, 2017, until the issuance of a completion certificate or handing over possession.

INTERIM_ORDEROrder ID: 0901126048862023-21-02-2025

The Tribunal allowed the appellant's application for condonation of delay subject to a cost of Rs. 1000/- and directed the Registry to convert the defective appeal into a regular appeal.

INTERIM_ORDEROrder ID: 0901126048862023-11-12-2024

The Tribunal adjourned the batch of appeals due to the absence of the appellant's counsel and imposed a cost of Rs. 5,000/- to be paid by the appellant to the respondent.