up_reraStatus: Completed
CASE ID: 0901126048852023

Appellant / Complainant

U.P. State Industrial Development Authority

VS

Respondent

Mohit Kumar Pal

Disputed Amount

36,77,500

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

23 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126048852023 by U.P. State Industrial Development Authority against Mohit Kumar Pal before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 126/03/2025

Hearing

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDC, affirming that the promoter is liable to pay delay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession, based on the initial completion date declared in the application form.

3
Stage 221/02/2025

Delay condonation

The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.

4
Stage 329/01/2025

Delay condonation

The Tribunal allowed a recall application to set aside an order imposing a cost of Rs. 5000/- on the appellant's counsel due to health issues and scheduled the appeal for hearing on 21.02.2024.

5
Stage 422/01/2025

Delay condonation

No text available.

6
Stage 515/01/2025

Delay condonation

No text available.

7
Stage 611/12/2024

Delay condonation

The Tribunal adjourned the appeal due to the absence of the appellant's counsel and imposed a cost of Rs. 5,000/- to be paid by the appellant to the respondent.

8
Stage 713/11/2024

Hearing

The Tribunal adjourned the proceedings at the request of the appellant's counsel and scheduled the hearing for November 12, 2024, noting that no further adjournments will be granted.

9
Stage 816/10/2024

Delay condonation

The Tribunal granted a request by the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 13.11.2024.

10
Stage 905/09/2024

Delay condonation

The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the case for hearing on 16.10.2024.

11
Stage 1029/07/2024

Delay condonation

The Tribunal granted the appellant a final opportunity to file a reply to the respondent's objections and scheduled the defective appeal for orders on September 5, 2024.

12
Stage 1101/07/2024

Delay condonation

The Tribunal granted the appellant's counsel one week to file a reply to the respondent's objection and scheduled the matter for orders on 29.07.2024.

13
Stage 1201/05/2024

Delay condonation

No text available.

14
Stage 1329/03/2024

Delay condonation

The order refers to a previous order passed in appeal No. D 660/2023 and contains no new substantive directives or rulings.

15
Stage 1423/02/2024

Delay condonation

The Tribunal granted the respondent a one-week extension to file objections to the grounds of appeal and directed the exchange of soft copies between counsel. The matter is scheduled for hearing on the application for condonation of delay on 29.03.2024.

16
Stage 1516/01/2024

Delay condonation

The Tribunal granted 10 days to the respondent to file a reply to objections and directed the appellant to send a reply within 10 days, scheduling the matter for hearing on 23.02.2024.

17
Stage 1618/12/2023

Delay condonation

The Tribunal issued notice to the respondent regarding an application for condonation of delay in filing the appeal, noting a 90-day delay and directing specific service protocols via speed-post and e-mail.

18
Stage 17Interim Order

Tribunal Order #0901126048852023-29-01-2025

The Tribunal allowed a recall application to set aside an order imposing a cost of Rs. 5000/- on the appellant's counsel due to health issues and scheduled the appeal for hearing on 21.02.2024.

19
Stage 18Final Ruling Order

Tribunal Order #0901126048852023-26-03-2025

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDC, affirming that the promoter is liable to pay delay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession, based on the initial completion date declared in the application form.

20
Stage 19Interim Order

Tribunal Order #0901126048852023-21-02-2025

The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.

21
Stage 20Interim Order

Tribunal Order #0901126048852023-11-12-2024

The Tribunal adjourned the appeal due to the absence of the appellant's counsel and imposed a cost of Rs. 5,000/- to be paid by the appellant to the respondent.

22
Stage 21Interim Order

Tribunal Order #0901126048852023-18-12-2023

The Tribunal issued notice to the respondent regarding an application for condonation of delay in filing the appeal, noting a 90-day delay and directing specific service protocols via speed-post and e-mail.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDC, affirming that the promoter is liable to pay delay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession, based on the initial completion date declared in the application form. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDC, affirming that the promoter is liable to pay delay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession, based on the initial completion date declared in the application form.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.01.2017 till development certificate/ completion certificate or till handing over the possession whichever is later

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Shuchita Singh
  • Sanjeev Singh

Respondent Advocate(s)

  • Deepak Dwivedi

Official RERA Tribunal Orders (5)

INTERIM_ORDEROrder ID: 0901126048852023-29-01-2025

The Tribunal allowed a recall application to set aside an order imposing a cost of Rs. 5000/- on the appellant's counsel due to health issues and scheduled the appeal for hearing on 21.02.2024.

FINAL_ORDEROrder ID: 0901126048852023-26-03-2025

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by UPSIDC, affirming that the promoter is liable to pay delay interest at MCLR+1% from January 1, 2017, until the issuance of a completion certificate or handing over possession, based on the initial completion date declared in the application form.

INTERIM_ORDEROrder ID: 0901126048852023-21-02-2025

The Tribunal allowed the appellant's application for condonation of delay in filing the appeal, subject to a cost of Rs. 1000/-, and directed the Registry to convert the defective appeal into a regular appeal.

INTERIM_ORDEROrder ID: 0901126048852023-11-12-2024

The Tribunal adjourned the appeal due to the absence of the appellant's counsel and imposed a cost of Rs. 5,000/- to be paid by the appellant to the respondent.

INTERIM_ORDEROrder ID: 0901126048852023-18-12-2023

The Tribunal issued notice to the respondent regarding an application for condonation of delay in filing the appeal, noting a 90-day delay and directing specific service protocols via speed-post and e-mail.