Appellant / Complainant
Uppal Chadha Hi-Tech Developers Pvt. Ltd.
Respondent
Naveen Goel
uppal chadha hi-tech developers pvt. ltd.
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126048752023 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Naveen Goel before up_rera.
Delay condonation
The Tribunal rejected the applications for condonation of delay in nine appeals due to lack of sufficient cause and dismissed the appeals; consequently, it directed that the pre-deposited amounts under Section 43(5) be transferred to the U.P. RERA for execution/distribution.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and rescheduled the hearing for the application for condonation of delay to 24.05.2024.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel due to personal difficulty and unpreparedness, rescheduling the hearing for the consideration of the condonation of delay application to 23.05.2024.
Delay condonation
The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the hearing for the application for condonation of delay on 22.05.2024.
Delay condonation
The Tribunal granted an adjournment due to the respondent's counsel's health and scheduled the matter for April 23, 2024, to consider the application for condonation of delay.
Delay condonation
The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for hearing on 18.03.2024 regarding the application for condonation of delay.
Delay condonation
The Tribunal granted the appellant a one-week extension to file an affidavit of service and scheduled the matter for orders on 13.02.2024.
Delay condonation
The Tribunal allowed the appellant's application to amend the prayer clause of the appeal and directed the issuance of notice to the respondent regarding the application for condonation of delay.
Delay condonation
The Tribunal granted the appellant one week to file an amendment application regarding the prayer clause of the appeal and scheduled the matter for orders on January 2, 2024.
Tribunal Order #0901126048752023-24-05-2024
The Tribunal rejected the applications for condonation of delay in nine appeals due to lack of sufficient cause and dismissed the appeals; consequently, it directed that the pre-deposited amounts under Section 43(5) be transferred to the U.P. RERA for execution/distribution.
Tribunal Order #0901126048752023-02-01-2024
The Tribunal allowed the appellant's application to amend the prayer clause of the appeal and directed the issuance of notice to the respondent regarding the application for condonation of delay.
Tribunal Disposal & Final Award Ruling
The Tribunal rejected the applications for condonation of delay in nine appeals due to lack of sufficient cause and dismissed the appeals; consequently, it directed that the pre-deposited amounts under Section 43(5) be transferred to the U.P. RERA for execution/distribution. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal rejected the applications for condonation of delay in nine appeals due to lack of sufficient cause and dismissed the appeals; consequently, it directed that the pre-deposited amounts under Section 43(5) be transferred to the U.P. RERA for execution/distribution.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 08.12.2016 to date of getting OC/CC or to the date when possession of plot was offered whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Naveen Kumar Tiwari
Respondent Advocate(s)
- Prasoon Kumar Anjor
Official RERA Tribunal Orders (2)
The Tribunal rejected the applications for condonation of delay in nine appeals due to lack of sufficient cause and dismissed the appeals; consequently, it directed that the pre-deposited amounts under Section 43(5) be transferred to the U.P. RERA for execution/distribution.
The Tribunal allowed the appellant's application to amend the prayer clause of the appeal and directed the issuance of notice to the respondent regarding the application for condonation of delay.
Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.