Appellant / Complainant
Sudha Realtors Pvt. Ltd.
Respondent
Pradeep Kumar Gupta, Uttar Pradesh Real Estate Regulatory Authority
sudha realtors pvt. ltd.
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126048692023 by Sudha Realtors Pvt. Ltd. against Pradeep Kumar Gupta, Uttar Pradesh Real Estate Regulatory Authority before up_rera.
Admission
The Tribunal granted an adjournment requested by the appellant's counsel due to a bereavement in the family and rescheduled the appeal for hearing on 03.07.2026.
Admission
The Tribunal granted the appellant ten days to file a rejoinder affidavit and scheduled the case for orders on May 11, 2026.
Admission
The Tribunal granted a request for adjournment on behalf of the appellant's counsel and rescheduled the appeal for hearing on 08.04.2026.
Admission
The Tribunal granted the appellant 10 days to file a rejoinder and scheduled the matter for hearing on the application for condonation of delay on 18.03.2026.
Admission
The appellant requested that the decretal amount recovered during execution proceedings by the Regulatory Authority not be released until further orders. The court granted time for both parties to file additional affidavits and scheduled the next hearing for 12.02.2026.
Final Hearing
The Tribunal granted the respondent one week to upload signed objections and allowed a subsequent week for the filing of a rejoinder affidavit, adjourning the matter to 21.01.2026.
Final Hearing
The Tribunal granted the respondent 10 days to file objections and directed that a rejoinder be filed within one week thereafter, scheduling the next hearing for December 15, 2025.
For Order
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Sudha Realtors Pvt. Ltd. due to non-compliance with the mandatory pre-deposit requirements under Section 43(5) of the RERA Act, 2016.
Defect Removal
The Tribunal adjourned the appeal due to the respondent's absence but issued a final warning that the appeal will be dismissed if the appellant fails to comply with Section 43 (5) of the Act by the next hearing on 01.04.2024.
Defect Removal
The Tribunal granted a final 3-day extension to the appellant to comply with Section 43(5) of the Act, warning that failure to do so will result in the dismissal of the defective appeal on the next listing date.
Defect Removal
The Tribunal granted a final one-week extension to the appellant to comply with Section 43(5) of the Act, warning that failure to do so will result in the dismissal of the defective appeal.
Defect Removal
The Tribunal rejected the appellant's request for a month-long adjournment and directed them to comply with Section 43(5) of the Act by depositing the required amount within one week, failing which the appeal may be dismissed.
Tribunal Order #0901126048692023-21-01-2026
The appellant requested that the decretal amount recovered during execution proceedings by the Regulatory Authority not be released until further orders. The court granted time for both parties to file additional affidavits and scheduled the next hearing for 12.02.2026.
Tribunal Order #0901126048692023-01-04-2024
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Sudha Realtors Pvt. Ltd. due to non-compliance with the mandatory pre-deposit requirements under Section 43(5) of the RERA Act, 2016.
Tribunal Order #0901126048692023-19-03-2024
The Tribunal granted a final 3-day extension to the appellant to comply with Section 43(5) of the Act, warning that failure to do so will result in the dismissal of the defective appeal on the next listing date.
Tribunal Order #0901126048692023-28-03-2024
The Tribunal adjourned the appeal due to the respondent's absence but issued a final warning that the appeal will be dismissed if the appellant fails to comply with Section 43 (5) of the Act by the next hearing on 01.04.2024.
Tribunal Order #0901126048692023-04-03-2024
The Tribunal granted a final one-week extension to the appellant to comply with Section 43(5) of the Act, warning that failure to do so will result in the dismissal of the defective appeal.
Tribunal Order #0901126048692023-23-02-2024
The Tribunal rejected the appellant's request for a month-long adjournment and directed them to comply with Section 43(5) of the Act by depositing the required amount within one week, failing which the appeal may be dismissed.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Sudha Realtors Pvt. Ltd. due to non-compliance with the mandatory pre-deposit requirements under Section 43(5) of the RERA Act, 2016. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Sudha Realtors Pvt. Ltd. due to non-compliance with the mandatory pre-deposit requirements under Section 43(5) of the RERA Act, 2016.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
36 months from the date of agreement till giving actual possession of the Unit
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Azhar Ikram
Respondent Advocate(s)
- Fuhar Gupta
Official RERA Tribunal Orders (6)
The appellant requested that the decretal amount recovered during execution proceedings by the Regulatory Authority not be released until further orders. The court granted time for both parties to file additional affidavits and scheduled the next hearing for 12.02.2026.
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by Sudha Realtors Pvt. Ltd. due to non-compliance with the mandatory pre-deposit requirements under Section 43(5) of the RERA Act, 2016.
The Tribunal granted a final 3-day extension to the appellant to comply with Section 43(5) of the Act, warning that failure to do so will result in the dismissal of the defective appeal on the next listing date.
The Tribunal adjourned the appeal due to the respondent's absence but issued a final warning that the appeal will be dismissed if the appellant fails to comply with Section 43 (5) of the Act by the next hearing on 01.04.2024.
The Tribunal granted a final one-week extension to the appellant to comply with Section 43(5) of the Act, warning that failure to do so will result in the dismissal of the defective appeal.
The Tribunal rejected the appellant's request for a month-long adjournment and directed them to comply with Section 43(5) of the Act by depositing the required amount within one week, failing which the appeal may be dismissed.