Appellant / Complainant
Vineeta Jain
Respondent
Patel Advance JV
patel advance jv
₹9,80,027
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126048482022 by Vineeta Jain against Patel Advance JV before up_rera.
Hearing
The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order for the promoter to hand over possession and pay delay interest (MCLR+1%) while allowing a six-month deduction for COVID-19 force majeure and permitting the promoter to levy interest on any default installments by the appellant.
Hearing
The Tribunal adjourned the appeal to 20.02.2025 and directed the respondent to produce documents regarding the project's RERA registration extension, proposed completion date, and status of the Occupancy Certificate/Completion Certificate (OC/CC).
Hearing
The Tribunal condoned an 8-day delay in filing the appeal and directed the respondent to provide instructions and documents regarding the project's OC/CC status and possession readiness by the next hearing on 30.01.2025.
Hearing
The Tribunal allowed the appellant's application to amend the prayer clause in the appeal and directed the applicant to upload an amended memo of appeal with changes marked in red ink.
Hearing
The Tribunal granted the appellant 10 days to file an amendment application to the memo of appeal and scheduled the next hearing for 26.11.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the defective appeal for orders or hearing on 21.10.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to their unavailability in the High Court and rescheduled the hearing for 10.09.2024.
Hearing
The Tribunal granted a request for adjournment following a counsel's unavailability and rescheduled the appeal hearing to August 7, 2024.
Hearing
The Tribunal granted an adjournment requested by the counsel for the respondent due to his presence at the High Court and rescheduled the hearing for 08.07.2024.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to an eye infection and rescheduled the hearing for May 9, 2024.
Hearing
The Tribunal noted that pleadings have been exchanged and adjourned the matter to 08.04.2024 for consideration of the application for condonation of delay.
Hearing
The Tribunal granted a request to fix the matter for hearing on 05.03.2024 to allow for the filing of an amendment application and consideration of condonation of delay.
Hearing
The Tribunal granted the appellant 10 days to file an amendment application regarding specific clauses of the challenged order and scheduled the matter for hearing on February 28, 2024.
Delay condonation
The Tribunal adjourned the proceedings due to a strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 26.10.2023.
Delay condonation
The Tribunal granted a request to list the defective appeal for consideration of the application for condonation of delay on 26.07.2023.
For Order
The Tribunal granted an adjournment following a request from the respondent's counsel and rescheduled the case for hearing/orders on 18.07.2023.
For Order
The Tribunal adjourned the proceedings due to the absence of counsel on sanctioned leave and rescheduled the hearing for May 5, 2023.
Delay condonation
The Tribunal granted an adjournment request from the appellant's counsel due to them being out of station and rescheduled the case for hearing on 24.03.2023.
Delay condonation
The Tribunal granted the appellant one week to file a reply to the respondent's objections regarding the application for condonation of delay and scheduled the matter for hearing on 13.01.2023.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent deadline for the applicant's reply. The matter is scheduled for hearing on 15.11.2022.
Delay condonation
The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the applicant to serve the notice via speed-post and email, scheduling the matter for hearing on 10.10.2022.
Tribunal Order #0901126048482022-09-01-2025
The Tribunal condoned an 8-day delay in filing the appeal and directed the respondent to provide instructions and documents regarding the project's OC/CC status and possession readiness by the next hearing on 30.01.2025.
Tribunal Order #0901126048482022-20-02-2025
The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order for the promoter to hand over possession and pay delay interest (MCLR+1%) while allowing a six-month deduction for COVID-19 force majeure and permitting the promoter to levy interest on any default installments by the appellant.
Tribunal Order #0901126048482022-26-11-2024
The Tribunal allowed the appellant's application to amend the prayer clause in the appeal and directed the applicant to upload an amended memo of appeal with changes marked in red ink.
Tribunal Order #0901126048482022-30-01-2025
The Tribunal adjourned the appeal to 20.02.2025 and directed the respondent to produce documents regarding the project's RERA registration extension, proposed completion date, and status of the Occupancy Certificate/Completion Certificate (OC/CC).
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order for the promoter to hand over possession and pay delay interest (MCLR+1%) while allowing a six-month deduction for COVID-19 force majeure and permitting the promoter to levy interest on any default installments by the appellant. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order for the promoter to hand over possession and pay delay interest (MCLR+1%) while allowing a six-month deduction for COVID-19 force majeure and permitting the promoter to levy interest on any default installments by the appellant.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
w.e.f. 27.11.2017 till handing over possession of the unit after obtaining Occupancy/Completion Certificate (subject to deduction of six months for COVID-19 pandemic)
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Azhar Ikram
- Manish Singh
Respondent Advocate(s)
- Mandeep Singh
- Jayant Gupta
Official RERA Tribunal Orders (4)
The Tribunal condoned an 8-day delay in filing the appeal and directed the respondent to provide instructions and documents regarding the project's OC/CC status and possession readiness by the next hearing on 30.01.2025.
The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order for the promoter to hand over possession and pay delay interest (MCLR+1%) while allowing a six-month deduction for COVID-19 force majeure and permitting the promoter to levy interest on any default installments by the appellant.
The Tribunal allowed the appellant's application to amend the prayer clause in the appeal and directed the applicant to upload an amended memo of appeal with changes marked in red ink.
The Tribunal adjourned the appeal to 20.02.2025 and directed the respondent to produce documents regarding the project's RERA registration extension, proposed completion date, and status of the Occupancy Certificate/Completion Certificate (OC/CC).
Need to research all rulings for patel advance jv?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.