up_reraStatus: Completed
CASE ID: 0901126048482022

Appellant / Complainant

Vineeta Jain

VS

Respondent

Patel Advance JV

Developer Firm

patel advance jv

Disputed Amount

9,80,027

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

31 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126048482022 by Vineeta Jain against Patel Advance JV before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 120/02/2025

Hearing

The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order for the promoter to hand over possession and pay delay interest (MCLR+1%) while allowing a six-month deduction for COVID-19 force majeure and permitting the promoter to levy interest on any default installments by the appellant.

3
Stage 230/01/2025

Hearing

The Tribunal adjourned the appeal to 20.02.2025 and directed the respondent to produce documents regarding the project's RERA registration extension, proposed completion date, and status of the Occupancy Certificate/Completion Certificate (OC/CC).

4
Stage 309/01/2025

Hearing

The Tribunal condoned an 8-day delay in filing the appeal and directed the respondent to provide instructions and documents regarding the project's OC/CC status and possession readiness by the next hearing on 30.01.2025.

5
Stage 426/11/2024

Hearing

The Tribunal allowed the appellant's application to amend the prayer clause in the appeal and directed the applicant to upload an amended memo of appeal with changes marked in red ink.

6
Stage 521/10/2024

Hearing

The Tribunal granted the appellant 10 days to file an amendment application to the memo of appeal and scheduled the next hearing for 26.11.2024.

7
Stage 610/09/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the defective appeal for orders or hearing on 21.10.2024.

8
Stage 707/08/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to their unavailability in the High Court and rescheduled the hearing for 10.09.2024.

9
Stage 808/07/2024

Hearing

The Tribunal granted a request for adjournment following a counsel's unavailability and rescheduled the appeal hearing to August 7, 2024.

10
Stage 909/05/2024

Hearing

The Tribunal granted an adjournment requested by the counsel for the respondent due to his presence at the High Court and rescheduled the hearing for 08.07.2024.

11
Stage 1008/04/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel due to an eye infection and rescheduled the hearing for May 9, 2024.

12
Stage 1105/03/2024

Hearing

The Tribunal noted that pleadings have been exchanged and adjourned the matter to 08.04.2024 for consideration of the application for condonation of delay.

13
Stage 1228/02/2024

Hearing

The Tribunal granted a request to fix the matter for hearing on 05.03.2024 to allow for the filing of an amendment application and consideration of condonation of delay.

14
Stage 1324/01/2024

Hearing

The Tribunal granted the appellant 10 days to file an amendment application regarding specific clauses of the challenged order and scheduled the matter for hearing on February 28, 2024.

15
Stage 1426/10/2023

Hearing

No text available.

16
Stage 1514/09/2023

Delay condonation

The Tribunal adjourned the proceedings due to a strike called by the Bar Council of Uttar Pradesh and rescheduled the hearing for 26.10.2023.

17
Stage 1626/07/2023

Delay condonation

No text available.

18
Stage 1718/07/2023

Delay condonation

The Tribunal granted a request to list the defective appeal for consideration of the application for condonation of delay on 26.07.2023.

19
Stage 1805/05/2023

For Order

The Tribunal granted an adjournment following a request from the respondent's counsel and rescheduled the case for hearing/orders on 18.07.2023.

20
Stage 1924/03/2023

For Order

The Tribunal adjourned the proceedings due to the absence of counsel on sanctioned leave and rescheduled the hearing for May 5, 2023.

21
Stage 2015/02/2023

Delay condonation

The Tribunal granted an adjournment request from the appellant's counsel due to them being out of station and rescheduled the case for hearing on 24.03.2023.

22
Stage 2113/01/2023

Delay condonation

No text available.

23
Stage 2209/12/2022

Delay condonation

The Tribunal granted the appellant one week to file a reply to the respondent's objections regarding the application for condonation of delay and scheduled the matter for hearing on 13.01.2023.

24
Stage 2315/11/2022

Delay condonation

No text available.

25
Stage 2410/10/2022

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent deadline for the applicant's reply. The matter is scheduled for hearing on 15.11.2022.

26
Stage 2506/09/2022

Delay condonation

The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the applicant to serve the notice via speed-post and email, scheduling the matter for hearing on 10.10.2022.

27
Stage 26Interim Order

Tribunal Order #0901126048482022-09-01-2025

The Tribunal condoned an 8-day delay in filing the appeal and directed the respondent to provide instructions and documents regarding the project's OC/CC status and possession readiness by the next hearing on 30.01.2025.

28
Stage 27Final Ruling Order

Tribunal Order #0901126048482022-20-02-2025

The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order for the promoter to hand over possession and pay delay interest (MCLR+1%) while allowing a six-month deduction for COVID-19 force majeure and permitting the promoter to levy interest on any default installments by the appellant.

29
Stage 28Interim Order

Tribunal Order #0901126048482022-26-11-2024

The Tribunal allowed the appellant's application to amend the prayer clause in the appeal and directed the applicant to upload an amended memo of appeal with changes marked in red ink.

30
Stage 29Interim Order

Tribunal Order #0901126048482022-30-01-2025

The Tribunal adjourned the appeal to 20.02.2025 and directed the respondent to produce documents regarding the project's RERA registration extension, proposed completion date, and status of the Occupancy Certificate/Completion Certificate (OC/CC).

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order for the promoter to hand over possession and pay delay interest (MCLR+1%) while allowing a six-month deduction for COVID-19 force majeure and permitting the promoter to levy interest on any default installments by the appellant. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order for the promoter to hand over possession and pay delay interest (MCLR+1%) while allowing a six-month deduction for COVID-19 force majeure and permitting the promoter to levy interest on any default installments by the appellant.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

w.e.f. 27.11.2017 till handing over possession of the unit after obtaining Occupancy/Completion Certificate (subject to deduction of six months for COVID-19 pandemic)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Azhar Ikram
  • Manish Singh

Respondent Advocate(s)

  • Mandeep Singh
  • Jayant Gupta

Official RERA Tribunal Orders (4)

INTERIM_ORDEROrder ID: 0901126048482022-09-01-2025

The Tribunal condoned an 8-day delay in filing the appeal and directed the respondent to provide instructions and documents regarding the project's OC/CC status and possession readiness by the next hearing on 30.01.2025.

FINAL_ORDEROrder ID: 0901126048482022-20-02-2025

The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order for the promoter to hand over possession and pay delay interest (MCLR+1%) while allowing a six-month deduction for COVID-19 force majeure and permitting the promoter to levy interest on any default installments by the appellant.

INTERIM_ORDEROrder ID: 0901126048482022-26-11-2024

The Tribunal allowed the appellant's application to amend the prayer clause in the appeal and directed the applicant to upload an amended memo of appeal with changes marked in red ink.

INTERIM_ORDEROrder ID: 0901126048482022-30-01-2025

The Tribunal adjourned the appeal to 20.02.2025 and directed the respondent to produce documents regarding the project's RERA registration extension, proposed completion date, and status of the Occupancy Certificate/Completion Certificate (OC/CC).