Appellant / Complainant
Uppal Chadha Hi-Tech Developers Pvt. Ltd.
Respondent
Surender Pal Aggarwal
uppal chadha hi-tech developers pvt. ltd.
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126048262023 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Surender Pal Aggarwal before up_rera.
Delay condonation
The Tribunal rejected the applications for condonation of delay in nine appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all said appeals. Additionally, the Tribunal directed that the pre-deposited amounts under Section 43(5) of the Act be transferred to the U.P. RERA for distribution to allottees during execution proceedings.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel due to health grounds and rescheduled the hearing for consideration of the condonation of delay application to 24.05.2024.
Delay condonation
The Tribunal granted an adjournment requested by the appellant's counsel due to personal difficulty and unreadiness, rescheduling the hearing for the application for condonation of delay to 23.05.2024.
Delay condonation
The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the hearing for the application for condonation of delay on 22.05.2024.
Delay condonation
The Tribunal granted an adjournment due to the respondent's counsel's health and directed that a reply be filed within a week, scheduling the hearing for April 23, 2024.
Delay condonation
The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the matter for hearing on March 18, 2024.
Delay condonation
The Tribunal granted the appellant a one-week extension to file an affidavit of service and scheduled the matter for further orders on 13.02.2024.
Delay condonation
The Tribunal allowed the appellant's application to amend the prayer clause of the appeal and directed the issuance of notice to the respondent regarding the application for condonation of delay, with the matter listed for hearing on 23.01.2024.
Delay condonation
The Tribunal granted the appellant one week to file an amendment application regarding the prayer clause of the appeal and scheduled the matter for orders on January 2, 2024.
Tribunal Order #0901126048262023-24-05-2024
The Tribunal rejected the applications for condonation of delay in nine appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all said appeals. Additionally, the Tribunal directed that the pre-deposited amounts under Section 43(5) of the Act be transferred to the U.P. RERA for distribution to allottees during execution proceedings.
Tribunal Order #0901126048262023-02-01-2024
The Tribunal allowed the appellant's application to amend the prayer clause of the appeal and directed the issuance of notice to the respondent regarding the application for condonation of delay, with the matter listed for hearing on 23.01.2024.
Tribunal Disposal & Final Award Ruling
The Tribunal rejected the applications for condonation of delay in nine appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all said appeals. Additionally, the Tribunal directed that the pre-deposited amounts under Section 43(5) of the Act be transferred to the U.P. RERA for distribution to allottees during execution proceedings. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal rejected the applications for condonation of delay in nine appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all said appeals. Additionally, the Tribunal directed that the pre-deposited amounts under Section 43(5) of the Act be transferred to the U.P. RERA for distribution to allottees during execution proceedings.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
from 08.12.2016 to date of getting OC/CC or to the date when possession of plot was offered whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Naveen Kumar Tiwari
Respondent Advocate(s)
- Samrat Vaish
Official RERA Tribunal Orders (2)
The Tribunal rejected the applications for condonation of delay in nine appeals filed by Uppal Chadha Hi-Tech Developers Pvt. Ltd., resulting in the dismissal of all said appeals. Additionally, the Tribunal directed that the pre-deposited amounts under Section 43(5) of the Act be transferred to the U.P. RERA for distribution to allottees during execution proceedings.
The Tribunal allowed the appellant's application to amend the prayer clause of the appeal and directed the issuance of notice to the respondent regarding the application for condonation of delay, with the matter listed for hearing on 23.01.2024.
Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.