Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126047892023 by Neha Gujrati against Wall Rock Infratech Pvt. Ltd. before up_rera.

2
Stage 122/05/2025

Hearing

The Tribunal allowed the appellant's application to withdraw the appeal, granting liberty to file a fresh complaint before U.P. RERA concerning issues arising after unit possession.

3
Stage 208/05/2025

Hearing

The Tribunal granted the appellant time to file a withdrawal application as they have obtained possession of the allotted parking slot, and adjourned the matter to 22.05.2025.

4
Stage 316/04/2025

Hearing

Upon a joint request from the counsel for both parties, the Tribunal has adjourned the matter and scheduled the next hearing for 08.05.2025.

5
Stage 419/03/2025

Hearing

The Tribunal noted the absence of the appellant's counsel and scheduled the appeal for a hearing on April 16, 2025.

6
Stage 528/02/2025

Hearing

The Tribunal noted that the parking allotment issue has been resolved by the RWA and the allottee has taken possession; the matter is listed for orders/hearing on 19.03.2025.

7
Stage 605/02/2025

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the appeal for hearing on 28.02.2025.

8
Stage 723/01/2025

Hearing

The Tribunal granted the appellant's counsel time to review newly uploaded information regarding parking availability and adjourned the matter to 05.02.2025.

9
Stage 816/01/2025

Hearing

The Tribunal noted the appellant's submission of photographic evidence and granted the respondent time to file a reply, subsequently scheduling the next hearing for 23.01.2025.

10
Stage 907/01/2025

Hearing

The Tribunal granted both parties time to upload relevant documents regarding the parking allotment issue and scheduled the matter for orders on 16.01.2025.

11
Stage 1009/12/2024

Hearing

The Tribunal granted the respondent time to seek instructions and attempt to resolve the dispute regarding allotted parking, adjourning the appeal to 07.01.2025.

12
Stage 1107/11/2024

Hearing

At the request of the respondent's counsel, the appeal has been scheduled for a hearing on December 9, 2024.

13
Stage 1227/09/2024

For Order

The Tribunal has adjourned the appeal to 07.11.2024 for final hearing/orders following a joint request from the counsels of both parties.

14
Stage 1328/08/2024

Defect Removal

The Tribunal granted an adjournment application filed by the appellant's counsel, with no objection from the respondent, and scheduled the matter for orders on 27.09.2024.

15
Stage 1429/07/2024

Defect Removal

The Tribunal directed the respondent to file objections within one week and granted the appellant one week thereafter to file a reply, scheduling the next hearing for 28.08.2024.

16
Stage 1530/05/2024

Defect Removal

The Tribunal granted the respondent 10 days to file objections and directed the appellant to file a reply within one week of receiving them, scheduling the next hearing for July 29, 2024.

17
Stage 1629/04/2024

Defect Removal

No text available.

18
Stage 1722/03/2024

Defect Removal

The Tribunal disposed of an application for listing and directed the issuance of notice to the respondent, setting a timeline for the exchange of appeal documents and objections.

19
Stage 18Final Ruling Order

Tribunal Order #0901126047892023-22-05-2025

The Tribunal allowed the appellant's application to withdraw the appeal, granting liberty to file a fresh complaint before U.P. RERA concerning issues arising after unit possession.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appellant's application to withdraw the appeal, granting liberty to file a fresh complaint before U.P. RERA concerning issues arising after unit possession. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appellant's application to withdraw the appeal, granting liberty to file a fresh complaint before U.P. RERA concerning issues arising after unit possession.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Zaid Khan

Respondent Advocate(s)

  • Amit Yadav
  • Raj Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126047892023-22-05-2025

The Tribunal allowed the appellant's application to withdraw the appeal, granting liberty to file a fresh complaint before U.P. RERA concerning issues arising after unit possession.

TathyaGrid RERA Intelligence AI

Need to research all rulings for wall rock infratech pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →