up_reraStatus: Completed
CASE ID: 0901126047702023

Appellant / Complainant

Satish Kumar Meena

VS

Respondent

Blue Square Infrastructure Llp

Developer Firm

blue square infrastructure llp

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126047702023 by Satish Kumar Meena against Blue Square Infrastructure Llp before up_rera.

2
Stage 123/04/2025

Further Hearing

The appeal was dismissed as withdrawn following the appellant's request, granting them liberty to seek remedy before an appropriate forum in accordance with the law.

3
Stage 225/03/2025

Further Hearing

The Tribunal has rescheduled the hearing for Appeal-744/2023 to April 23, 2025, following a request from the respondent's counsel.

4
Stage 303/03/2025

Admission

The Tribunal has identified a question of public importance regarding whether the sale of virtual space in commercial buildings falls under the U.P. Real Estate Act and has appointed an Amicus Curiae to assist in the matter.

5
Stage 404/02/2025

Admission

The Tribunal listed the case for orders on 03.03.2025 and directed that no further adjournments shall be granted to either party.

6
Stage 506/01/2025

Admission

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 04.02.2025.

7
Stage 620/11/2024

Admission

The Tribunal has scheduled the case for orders on January 6, 2025.

8
Stage 716/10/2024

Admission

The Tribunal granted the appellant 10 days to file a rejoinder to the respondent's objections and scheduled the next hearing for November 20, 2024.

9
Stage 823/09/2024

Admission

The Tribunal granted the appellant seven days to file a rejoinder to the respondent's objections and scheduled the next hearing for October 16, 2024.

10
Stage 920/08/2024

Admission

The Tribunal granted the respondent a final seven-day extension to file objections to the grounds of appeal and provide a soft copy to the appellant, with the next hearing scheduled for 23.09.2024.

11
Stage 1022/07/2024

Admission

The Tribunal granted the respondent three days to file objections and directed that the appellant be provided with a copy within seven days, with the matter listed for hearing on 20.08.2024.

12
Stage 1122/05/2024

Admission

The Tribunal granted the respondent 10 days to file objections and directed the appellant to file a reply within one week of receiving the soft copy. The matter is scheduled for hearing on 22.07.2024.

13
Stage 1224/04/2024

Admission

The Tribunal directed the respondent to register their counsel on the portal and granted them 10 days to file objections to the appeal, with the matter scheduled for hearing on 22.05.2024.

14
Stage 1319/03/2024

Admission

The Tribunal granted an adjournment requested by the appellant's counsel due to personal illness and directed the appellant to file proof of service, including postal receipts and digital transaction reports, within one week.

15
Stage 1416/02/2024

Admission

The Tribunal issued a fresh notice to the respondent to be served via 'Dasti' in the presence of two independent witnesses and scheduled the matter for 19.03.2024.

16
Stage 1508/01/2024

Defect Removal

The Tribunal directed the Registry to convert the defective appeal into a regular appeal and ordered the issuance of notice to the respondent, with the next hearing scheduled for 16.02.2024.

17
Stage 1622/12/2023

Defect Removal

The Tribunal directed the Registry to communicate existing defects to the applicant and ordered that the appeal be listed on 08.01.2024, with a warning of dismissal if defects are not removed.

18
Stage 17Interim Order

Tribunal Order #0901126047702023-03-03-2025

The Tribunal has identified a question of public importance regarding whether the sale of virtual space in commercial buildings falls under the U.P. Real Estate Act and has appointed an Amicus Curiae to assist in the matter.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn with liberty to take remedy before appropriate forum in accordance with law Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn with liberty to take remedy before appropriate forum in accordance with law

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Nitesh Anan
  • Surangama Sharma

Respondent Advocate(s)

  • Gautam Johri

Official RERA Tribunal Orders (1)

INTERIM_ORDEROrder ID: 0901126047702023-03-03-2025

The Tribunal has identified a question of public importance regarding whether the sale of virtual space in commercial buildings falls under the U.P. Real Estate Act and has appointed an Amicus Curiae to assist in the matter.

TathyaGrid RERA Intelligence AI

Need to research all rulings for blue square infrastructure llp?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →