up_reraStatus: Completed
CASE ID: 0901126047562024

Appellant / Complainant

Yamuna Expressway Industrial Development Authority

VS

Respondent

Deepika Dixit

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126047562024 by Yamuna Expressway Industrial Development Authority against Deepika Dixit before up_rera.

2
Stage 109/02/2026

Delay condonation

The Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic red tape do not constitute 'sufficient cause' for delay.

3
Stage 228/01/2026

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the case for orders on 09.02.2026.

4
Stage 306/01/2026

Delay condonation

The Tribunal noted the filing of a rejoinder by the appellant and adjourned the matter to 28.01.2026 due to the absence of the respondent.

5
Stage 401/12/2025

Delay condonation

The Tribunal granted a request for adjournment and scheduled the case for orders on January 6, 2026.

6
Stage 519/11/2025

Delay condonation

The Tribunal granted the appellant seven days to file a rejoinder affidavit and scheduled the appeal for hearing on December 1, 2025.

7
Stage 631/10/2025

Delay condonation

The Tribunal noted sufficient service of notice upon the respondent and granted them 10 days to file objections, with the matter scheduled for hearing on 19.11.2025.

8
Stage 709/10/2025

Delay condonation

The Tribunal issued a notice to the respondent and outlined the procedural steps for service of the appeal and application for condonation of delay, scheduling the next hearing for 31.10.2025.

9
Stage 8Final Ruling Order

Tribunal Order #0901126047562024-09-02-2026

The Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic red tape do not constitute 'sufficient cause' for delay.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic red tape do not constitute 'sufficient cause' for delay. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic red tape do not constitute 'sufficient cause' for delay.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Prashant Kumar Singh

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126047562024-09-02-2026

The Tribunal rejected the appellant's application for condonation of delay and dismissed the appeal, ruling that administrative lethargy and bureaucratic red tape do not constitute 'sufficient cause' for delay.