Appellant / Complainant
Rajesh R.
Respondent
Hebe Infrastructure Pvt. Ltd. (Mahagun Group)
hebe infrastructure pvt. ltd.
₹27,33,062
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126047552022 by Rajesh R. against Hebe Infrastructure Pvt. Ltd. (Mahagun Group) before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's entire deposited amount with interest at MCLR+1% from the date of deposit due to the developer's failure to deliver possession within the agreed timeframe.
Hearing
The Tribunal heard arguments regarding an appeal against a Regulatory Authority's decision to deny a refund request; the appellant seeks a full refund with interest due to project delays and failure to obtain OC/CC. The judgment has been reserved.
Hearing
The Tribunal noted the absence of the appellant's counsel and adjourned the appeal for orders/hearing to 25.07.2023.
Hearing
The matter was adjourned due to lack of time, with the case rescheduled for hearing on 31.05.2023.
Hearing
The Tribunal has scheduled the appeal for a hearing on May 15, 2023.
Hearing
The Tribunal granted a request from the appellant's counsel to reschedule the hearing of Appeal-597/2022 to 27.04.2023.
Hearing
The Tribunal noted the respondent's absence despite prior warnings and granted the appellant's request for more time to prepare her brief, adjourning the hearing to 25.04.2023.
Hearing
The Tribunal scheduled the case for hearing on 31.03.2023 and directed that no further adjournments will be granted, noting that the appeal will proceed based on available records if parties fail to appear.
Hearing
The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and directed the submission of a soft copy to the respondent and the e-portal.
For Order
The Tribunal granted a request for adjournment following an application from the appellant's counsel and scheduled the appeal for hearing on January 2, 2023.
For Order
The Tribunal has scheduled the case for a hearing on December 1, 2022.
Notice
The Tribunal found service of notice on the respondent to be sufficient and granted the respondent 10 days to file objections, noting that the matter may proceed ex-parte if they fail to appear or file.
Admission
The Tribunal issued notice to the respondents and established a procedural timeline for service of notice, filing of objections, and subsequent replies before the next hearing on 23.09.2022.
Tribunal Order #0901126047552022-07-05-2024
The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's entire deposited amount with interest at MCLR+1% from the date of deposit due to the developer's failure to deliver possession within the agreed timeframe.
Tribunal Order #0901126047552022-23-01-2024
The Tribunal heard arguments regarding an appeal against a Regulatory Authority's decision to deny a refund request; the appellant seeks a full refund with interest due to project delays and failure to obtain OC/CC. The judgment has been reserved.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's entire deposited amount with interest at MCLR+1% from the date of deposit due to the developer's failure to deliver possession within the agreed timeframe. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's entire deposited amount with interest at MCLR+1% from the date of deposit due to the developer's failure to deliver possession within the agreed timeframe.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR + 1%
Interest Period
from the date of deposit till the date of refund of the same
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Surangama Sharma
Official RERA Tribunal Orders (2)
The Appellate Tribunal set aside the Regulatory Authority's order and directed the respondent to refund the appellant's entire deposited amount with interest at MCLR+1% from the date of deposit due to the developer's failure to deliver possession within the agreed timeframe.
The Tribunal heard arguments regarding an appeal against a Regulatory Authority's decision to deny a refund request; the appellant seeks a full refund with interest due to project delays and failure to obtain OC/CC. The judgment has been reserved.
Need to research all rulings for hebe infrastructure pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.