Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Refund of InvestmentDelay Compensation / InterestNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

7 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126047212023 by Lucknow Development Authority against Himanshu Kumar Misra before up_rera.

Refund of InvestmentDelay Compensation / InterestNon-Compliance & Execution
2
Stage 105/03/2024

For Order

The Tribunal directed that the pre-deposited amount under Section 43(5) of the Act be transferred to the U.P. Real Estate Regulatory Authority for disbursement to the allottee following the dismissal of the promoter's appeal.

3
Stage 208/02/2024

For Order

The Tribunal noted the absence of counsel for the applicant and scheduled the defective appeal for consideration of the condonation of delay application on 05.03.2024.

4
Stage 309/11/2023

For Order

No text available.

5
Stage 426/09/2023

For Order

The Tribunal issued notice to the Lucknow Development Authority regarding an application filed by the respondent for the release of funds deposited under Section 43(5) of the Act and scheduled the matter for hearing on 09.11.2023.

6
Stage 5Final Ruling Order

Tribunal Order #0901126047212023-05-03-2024

The Tribunal directed that the pre-deposited amount under Section 43(5) of the Act be transferred to the U.P. Real Estate Regulatory Authority for disbursement to the allottee following the dismissal of the promoter's appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal directed that the pre-deposited amount under Section 43(5) of the Act be transferred to the U.P. Real Estate Regulatory Authority for disbursement to the allottee following the dismissal of the promoter's appeal. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal directed that the pre-deposited amount under Section 43(5) of the Act be transferred to the U.P. Real Estate Regulatory Authority for disbursement to the allottee following the dismissal of the promoter's appeal.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Respondent Advocate(s)

  • Atul Tripathi

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126047212023-05-03-2024

The Tribunal directed that the pre-deposited amount under Section 43(5) of the Act be transferred to the U.P. Real Estate Regulatory Authority for disbursement to the allottee following the dismissal of the promoter's appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →