up_reraStatus: Completed
CASE ID: 0901126046232022

Appellant / Complainant

Antriksh Realtech Pvt. Ltd.

VS

Respondent

Raksha Vigyan Karamchari Sahkari Awas Samiti Ltd. Ghaziabad, Uttar Pradesh Real Estate Regulatory Authority

Developer Firm

antriksh realtech pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126046232022 by Antriksh Realtech Pvt. Ltd. against Raksha Vigyan Karamchari Sahkari Awas Samiti Ltd. Ghaziabad, Uttar Pradesh Real Estate Regulatory Authority before up_rera.

2
Stage 116/01/2024

Hearing

The appellant filed an application to withdraw the appeal, which was granted without objection from the respondent, resulting in the dismissal of the appeal as withdrawn.

3
Stage 212/10/2023

Hearing

No text available.

4
Stage 304/09/2023

Hearing

The Tribunal adjourned the proceedings to 12.10.2023 in response to a Bar Council of Uttar Pradesh resolution calling for a three-day strike by lawyers.

5
Stage 403/08/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for 04.09.2023.

6
Stage 523/05/2023

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel on health grounds and rescheduled the case for hearing/orders on 03.08.2023.

7
Stage 611/04/2023

Hearing

The Tribunal granted the appellant a final one-week extension to file a reply against the respondent's objections and scheduled the matter for hearing on 23.05.2023.

8
Stage 702/03/2023

Hearing

The Tribunal granted the appellant a final 10-day extension to file a reply to the respondent's objections and scheduled the next hearing for April 11, 2023.

9
Stage 831/01/2023

For Order

The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the next hearing for March 2, 2023.

10
Stage 923/12/2022

For Order

The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the next hearing for January 31, 2023.

11
Stage 1030/11/2022

For Order

No text available.

12
Stage 1101/11/2022

For Order

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and directed the respondents to share their objections via the portal, setting a timeline for the appellant's reply and scheduling the next hearing for 30.11.2022.

13
Stage 1221/09/2022

For Order

The Tribunal granted the respondents 10 days to file objections to the grounds of appeal and directed that a reply be filed by the appellant within one week thereafter, listing the matter for orders on 01.11.2022.

14
Stage 1326/08/2022

Notice

The Tribunal issued notice to Respondent No. 1 (UPRERA) and granted Respondent No. 2 two weeks to file objections, setting a hearing date for September 21, 2022.

15
Stage 1411/08/2022

Admission

The Tribunal issued notice to the respondent and outlined the procedural requirements for service of appeal documents and the timeline for filing objections and replies.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Dismissed as withdrawn Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Dismissed as withdrawn

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Siddharth Nandwani

Respondent Advocate(s)

  • Prashant Kumar Singh
TathyaGrid RERA Intelligence AI

Need to research all rulings for antriksh realtech pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →