Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126045422022 by Lucknow Development Authority against Shobha Gupta before up_rera.

2
Stage 113/07/2023

Delay condonation

The Tribunal rejected the application for condonation of delay due to insufficient cause and dismissed the appeal; consequently, it directed the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement to the allottee during execution proceedings.

3
Stage 202/05/2023

Delay condonation

The Tribunal directed the parties to exchange pleadings and scheduled the defective appeal for orders on 13.07.2023.

4
Stage 321/03/2023

Delay condonation

No text available.

5
Stage 413/02/2023

Delay condonation

The Tribunal noted a missing application for condonation of delay and directed the appellant's counsel to upload it within a week, while granting 10 days for the appellant to file a reply to the respondent's objections. The matter is scheduled for hearing on 21.03.2023.

6
Stage 5Final Ruling Order

Tribunal Order #0901126045422022-13-07-2023

The Tribunal rejected the application for condonation of delay due to insufficient cause and dismissed the appeal; consequently, it directed the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement to the allottee during execution proceedings.

7
Stage 6Interim Order

Tribunal Order #0901126045422022-13-02-2023

The Tribunal noted a missing application for condonation of delay and directed the appellant's counsel to upload it within a week, while granting 10 days for the appellant to file a reply to the respondent's objections. The matter is scheduled for hearing on 21.03.2023.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the application for condonation of delay due to insufficient cause and dismissed the appeal; consequently, it directed the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement to the allottee during execution proceedings. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the application for condonation of delay due to insufficient cause and dismissed the appeal; consequently, it directed the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement to the allottee during execution proceedings.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Suryansh Narula

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126045422022-13-07-2023

The Tribunal rejected the application for condonation of delay due to insufficient cause and dismissed the appeal; consequently, it directed the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement to the allottee during execution proceedings.

INTERIM_ORDEROrder ID: 0901126045422022-13-02-2023

The Tribunal noted a missing application for condonation of delay and directed the appellant's counsel to upload it within a week, while granting 10 days for the appellant to file a reply to the respondent's objections. The matter is scheduled for hearing on 21.03.2023.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →